Red flags

  • No red flags in this filing

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2018Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 44 documents Report an error

Parimala Skyview is a Residential/Group Housing project by Vishnu Priya Group of builders and Developers in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/171214/001051 on 14 Dec 2017. Possession is promised by 4 Dec 2018.

At a glance

Project

  • NameParimala Skyview
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/171214/001051
  • ReraGenie IDRG-KA-81717

Builder

  • NameVishnu Priya Group of builders and Developers
  • Entity typePartnership Firm
  • Authorized SignatoryAnil Kumar Muthyala
  • DirectorVidya Sagar Muthyala
  • Declared earlier projects1 →

Key dates

this monthRegisteredDec 2017PromisedDec 2018

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on14 Dec 2017
  • Promised completion4 Dec 2018
  • Revised completionNone
  • Buildings1 building record
  • Documents filed44 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Parimala Skyview---94094

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,048 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 35.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAni Sambyal
EngineerAcme Consultants INC

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed44

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/171214/001051 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: VPG registered reconstitution firms certificate (1).pdf-
Architect Certificate for Work Completion Schedule till DateFile: Architect Certificate-Work completed.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Certificate-Work completed.pdf-
CA Certificate for Funds UtilizationFile: CA Fund Utilisation Certificate.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect Certificate-Work Pending.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer Certificate-Work pending.pdf-
CA Certificate for Funds required for Project CompletionFile: CA Fund Required Certificate.pdf-
AffidavitFile: Seeking for Extension Affidavit.pdf-
Latest Encumbrance CertificateFile: EC.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails (1).xlsx-
Document 1File: BWSSB NOC Affidavit.pdf-
Parimala Skyview CC endorsement-
deleted_Parimala Skyview BBMP approval blue prints 5mb-ilovepdf-compressed (3) (2)-
Parimala Skyview BBMP approval blue prints 4mb-
skyview_sale_Deed_draft-
vps_sale_agreement_proforma-
combinepdf (1)-
skyview allotment letter-
SkyView-Brochure-
skyview_all_nocs-
SPECIFICATIONS OF THE SCHEDULE FLAT-
Skyview EC 11-9-12 to 15-2-16-
Hope Farm katha & Extact14-15-
hopefarm conversion order-
bescom noc (1)-
BWSSB noc-
Pollution noc-
BSNL noc-
Balance Sheet 2015 - 2016File: BS VPG 2015-2016.pdf-
Balance Sheet 2014 - 2015File: BS VPG 2014-2015.pdf-
Balance Sheet 2013 - 2014File: BS VPG 2013-2014.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P&l PVG 2015-2016.pdf-
Audited Profit and Loss Statement 2014 - 2015File: P&l PVG 2014-2015.pdf-
Audited Profit and Loss Statement 2013 - 2014File: P&l PVG 2013-2014.pdf-
Cash Flow Statement 2015 - 2016File: Parimala Skyview cashflows.pdf-
Auditor's Report 2015 - 2016File: Auditor Report 2015-2016.pdf-
Auditor's Report 2014 - 2015File: Auditor Report 2014-2015.pdf-
Auditor's Report 2013 - 2014File: Auditor Report 2013-2014.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITRA 2015-2016.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITRA 2014-2015.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: ITRA 2013-2014.pdf-
declaration-supported-by-an-affidavit-which-shall-be-signed-by-the-promoter-or-any-person--
Prospectus/BrochureFile: Skyview Brochure with elevation pic compressed.pdf-
Tower Excel SheetFile: PRMKARERA1251446PR171214001051 (1).xlsx-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Parimala Riviera-CompletedAug 2017No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Parimala Skyview on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Vishnu Priya Group of builders and Developers

Vishnu Priya Group of builders and Developers has 1 registration on RERA Karnataka, including Parimala Skyview. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Parimala Skyview is delayed beyond 4 Dec 2018?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Parimala Skyview?

The registered promoter entity is Vishnu Priya Group of builders and Developers, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Parimala Skyview?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Parimala Skyview?

The professionals named in the filing: Architect: Ani Sambyal; Engineer: Acme Consultants INC. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Parimala Skyview?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Parimala Skyview. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Parimala Skyview to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.