Home / Browse projects / Bengaluru Urban, Karnataka / OZONE CHAMBERS

Registration approved No litigation declared Commercial project

OZONE CHAMBERS

By ITALIX LIVING SPACES PVT LTD

RG-KA-70607 · RERA TOR/PRM/KA/RERA/1251/310/PR/200109/001521 · Last updated on RERA Karnataka portal: 24 Feb 2026

Source: official RERA Karnataka filing

Red flags

  • 2 complaints at RERA Karnataka
  • Completion date moved by 75 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
Dec 2025Possession promisedmoved 75 months from the original
0 of 17Construction stages donefurthest along: Earth work and other leveling..., 98%
0 of 16Units unsoldnot recorded sold or booked
2Complaints at RERA Karnatakaon this registration
Jump to the 67 documents Report an error

OZONE CHAMBERS is a Commercial project by ITALIX LIVING SPACES PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as TOR/PRM/KA/RERA/1251/310/PR/200109/001521 on 9 Jan 2020. Possession is promised by 31 Dec 2025. The completion date has moved by 75 months from the original filing. 16 of the 16 units on this registration are recorded sold or booked, and 0 of 17 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameOZONE CHAMBERS
  • TypeCommercial
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.TOR/PRM/KA/RERA/1251/310/PR/200109/001521
  • ReraGenie IDRG-KA-70607

Builder

  • NameITALIX LIVING SPACES PVT LTD
  • Entity typeCompany
  • CINU45500KA2018PTC115146
  • Authorized SignatoryMr. DURBHAKULA VAMSI SAI
  • DirectorsVASUDEVAN SATHYAMOORTHY, DURBHAKULA VAMSI SAI
  • Other registrations3 more →
  • No longer live1 withdrawn or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredJan 2020First promiseSep 2019Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on9 Jan 2020
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Sep 2019)
  • Buildings1 building record
  • Documents filed67 files

Current status

100%16 of 16 units booked
54.2%Of the estimated cost spent so far

Figures as on 24 Feb 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Ozone Chamber---01616

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 24 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 17 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 98%.

Building: 31% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work98%
Foundation footing work70%
Retaining wall (All types)50%
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
RCC or MS Framed structure0%
Masonry construction: Bricks, Concrete blocks etc53%
Plastering inside , outside & Ceiling42%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification22%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing50%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network50%
Weather Proof work(tile,concrete)50%
Painting0%
Elevation work0%
Internal and External work including landscapes as per santioned drawings50%

Progress on shared amenities41

As on 24 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Internal Roads & FootpathsYes0%
Sewage and Drainage SystemYes0%
Parks & Tree plantingYes0%
Street LightingYes0%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservationYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes0%
Emergency Evacuation servicesYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
GasNoNot applicable
Water and SanitationYes0%
Air Conditioning And incerntionYes0%
StaircasesYes55%
LiftsYes55%
Staircases and Lift lobbies, corridor,lobbies, corridorYes55%
Fire escapesYes0%
Common entrance and exit for the building / common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes55%
Outer WallYes55%
Open parking areas and common storage spacesYes0%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,046 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 245.09 cr
Cost incurredRs 132.90 cr
Spent of the estimate54.23%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 245.09 crRs 132.90 cr

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionSep 2019 → Mar 2021

No reason recorded in the filing

EX/PRM/KA/RERA/1251/310/PR/200908/001521Mar 2021 → Sep 2020

Reason as filed by the promoterAwaiting Approvals; Delay in Approvals

ExtensionSep 2020 → Dec 2025

No reason recorded in the filing

Complaints filed with RERA Karnataka2

Case no.ComplainantRespondentFiled
01895/2023-ITALIX LIVING SPACES PVT LTD30/12/2023
00290/2026-ITALIX LIVING SPACES PVT LTD24/03/2026

Documents filed67

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number TOR/PRM/KA/RERA/1251/310/PR/200109/001521 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: RERA CA FORM 4 DEC 2025 OZONE CHAMBERS.pdf24 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: dec.pdf24 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer (QU)_Chambers Q3 Dec-2025 (1).pdf24 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)24 Feb 2026
Q3 2025-26 KPTCL- BESCOM24 Feb 2026
Q3 2025-26 Fire and Safety24 Feb 2026
Q3 2025-26 Airport Authority of India24 Feb 2026
Q3 2025-26 BSNL/Telecommunication Department24 Feb 2026
CertificateFile: COI MOA AOA ITALIX.PDF-
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: Affidavit for Extension OC.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Certificate Ozone chambers.pdf-
CA Certificate for Funds UtilizationFile: CA certificate.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Affidavit for Extension OC.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer Certificate Ozone chambers.pdf-
CA Certificate for Funds required for Project CompletionFile: CA certificate.pdf-
AffidavitFile: Affidavit for Extension OC.pdf-
Latest Encumbrance CertificateFile: EC.pdf-
Consent letter from 2/3rd of AllotteesFile: Consent Letter.pdf-
Details Of Sold/ Un-sold UnitsFile: Sold & unsold units.xlsx-
Document 1File: Form B Declaration.pdf-
Document 2File: Bank statement.pdf-
Document 3File: Affidavit for Comm Sec 18.pdf-
Document 4File: Partial C C for Resi Commercial.pdf-
Document 5File: CA certificate - funds required Chambers.pdf-
Document 6File: CA certificate - fund utilized Chambers.pdf-
COMMENCEMENT CERTIFICATE (1)-
Approved Building Plan-
Approved Layout Plan-
Sale deed final-
Elevation Section-
BDA_DP_Signed_Commercial-
Project Specification Commercial FINAL-
EC-
Sec 3 Affidavit-
BBMP Khatha and Extract-
Note Raheja Chambers-
Relinquish Deed-
FIRE Noc-
Airports Authority NOC-
KSPCB Noc-
MOEF Noc-
Approved Layout Plan-
Elevation Section-
conversion orders-
Title Search Report-
Balance Sheet 2018 - 2019File: Declaration for Financial Details.pdf-
Balance Sheet 2017 - 2018File: Declaration for Financial Details.pdf-
Balance Sheet 2016 - 2017File: Declaration for Financial Details.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Declaration for Financial Details.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Declaration for Financial Details.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Declaration for Financial Details.pdf-
Director's Report 2018 - 2019File: Declaration for Financial Details.pdf-
Director's Report 2017 - 2018File: Declaration for Financial Details.pdf-
Director's Report 2016 - 2017File: Declaration for Financial Details.pdf-
Cash Flow Statement 2018 - 2019File: Declaration for Financial Details.pdf-
Cash Flow Statement 2017 - 2018File: Declaration for Financial Details.pdf-
Auditor's Report 2018 - 2019File: Declaration for Financial Details.pdf-
Auditor's Report 2017 - 2018File: Declaration for Financial Details.pdf-
Auditor's Report 2016 - 2017File: Declaration for Financial Details.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: Declaration for Financial Details.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: Declaration for Financial Details.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: Declaration for Financial Details.pdf-
Form B-
Prospectus/BrochureFile: Ozone Chambers ebrochure_compressed (1).pdf-
Advertisement Copy 1File: Ozone Chambers ebrochure_compressed (1).pdf-
Tower Excel SheetFile: TORPRMKARERA1251310PR200109001521 (1).xlsx-

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 75 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep OZONE CHAMBERS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: ITALIX LIVING SPACES PVT LTD

ITALIX LIVING SPACES PVT LTD has 4 registrations on RERA Karnataka, including Pebble Bay -Koramangala Phase I and OZONE CHAMBERS. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if OZONE CHAMBERS is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of OZONE CHAMBERS?

The registered promoter entity is ITALIX LIVING SPACES PVT LTD, a company as per the filing. Its CIN U45500KA2018PTC115146 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in OZONE CHAMBERS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against OZONE CHAMBERS?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

What should I check before booking in OZONE CHAMBERS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OZONE CHAMBERS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OZONE CHAMBERS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.