Registration transferred No litigation declared Plotted Development project

Oxigen Phase 1

By Excel Dwellings Oxigen Pvt Ltd

RG-KA-12629 · RERA PRM/KA/RERA/1251/308/PR/171031/001644 · Last updated on RERA Karnataka portal: 24 Feb 2026

Source: official RERA Karnataka filing

Red flags

  • Registration transferred
  • 1 complaint at RERA Karnataka
  • Completion date moved by 78 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
Aug 2028Possession promisedmoved 78 months from the original
1Complaints at RERA Karnatakaon this registration
Jump to the 57 documents Report an error

Oxigen Phase 1 is a Plotted Development project by Excel Dwellings Oxigen Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/171031/001644 on 31 Oct 2017. Possession is promised by 30 Aug 2028. The completion date has moved by 78 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameOxigen Phase 1
  • TypePlotted Development
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/171031/001644
  • ReraGenie IDRG-KA-12629

Builder

  • NameExcel Dwellings Oxigen Pvt Ltd
  • Entity typeCompany
  • CINU70200KA2014PTC074700
  • Authorized SignatoryAllu Siva Rama Krishna Reddy

Key dates

this monthRegisteredOct 2017First promiseFeb 2022Revised toAug 2028

Key facts

Registration and timeline

  • StatusRegistration transferred
  • Registered on31 Oct 2017
  • Promised completion30 Aug 2028
  • Revised completionRevised to 30 Aug 2028 (originally 28 Feb 2022)
  • BuildingsNot stated in filing
  • Documents filed57 files

Current status

0.0%Of the estimated cost spent so far

Figures as on 24 Feb 2026, this project's latest RERA Karnataka filing.

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area192,527 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 23.10 cr
Spent of the estimate0.0%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 22.00 cr-
Administrative CostsRs 80.00 lakh-
On-site expenditure-Consultants FeesRs 30.00 lakh-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionFeb 2022 → Nov 2022

No reason recorded in the filing

ExtensionNov 2022 → Nov 2023

Reason as filed by the promoterothers

ExtensionNov 2023 → Aug 2028

No reason recorded in the filing

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
CMP/201224/0007314-Excel Dwellings Oxigen Pvt Ltd24/12/2020

Documents filed57

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/171031/001644 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA certificate Dec 25.pdf24 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Dec 2025.pdf24 Feb 2026
Q3 2025-26 Water supply and sewage board24 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)24 Feb 2026
Q3 2025-26 KPTCL- BESCOM24 Feb 2026
Affidavit cum declarationFile: Affidavit cum declaration.pdf13 Jan 2026
EC Sy no 68-1,2,3,4File: EC Sy no 68-1,2,3,4.pdf3 Jan 2026
EC Sy no 91, 92, 93File: EC Sy no 91, 92, 93.pdf3 Jan 2026
EC Sy no 95File: EC Sy no 95.pdf3 Jan 2026
EC Sy no 96File: EC Sy no 96.pdf3 Jan 2026
EC Sy no 97-1, 2, 3, 4File: EC Sy no 97-1, 2, 3, 4.pdf3 Jan 2026
EC Sy no 98-1File: EC Sy no 98-1.pdf3 Jan 2026
EC Sy no 69-2File: EC Sy no 69-2.pdf3 Jan 2026
signed sold and unsold sitesFile: signed sold and unsold sites.pdf3 Jan 2026
CertificateFile: Oxigen - COI.pdf-
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: Architect Certificate for Work Completion Schedule till Date.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Certificate for Work completed.pdf-
CA Certificate for Funds UtilizationFile: CA Certificate Fund Utilisation.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect Certificate for Pending Work Completion Schedule.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer Certificate for Pending Work.pdf-
CA Certificate for Funds required for Project CompletionFile: CA Certificate Fund Requirement.pdf-
AffidavitFile: Extension Affidavit.pdf-
Latest Encumbrance CertificateFile: EC of all Sy Nos.pdf-
Details Of Sold/ Un-sold UnitsFile: Sold UnsoldDetails.xlsx-
Document 1File: 40 % Release Order.pdf-
Commencement Certificate-
Oxigen - BMRDA Approved Plan BP-compressed-
Oxigen Approved Phase 1-
SALE DEED MASTER COPY (1)-
SALE AGREEMENT MASTER COPY-
Oxigen Phase 1 Sale Deed_rtc_opt-
Oxigen - BMRDA Approved Plan BP-compressed-
Oxigen Approved Phase 1-
Allotment Letter Format-
Brochure-
NOC-
Project Specifications Phase 1-
ECS-
Khatha Phase 1_Opt-
JDA-oxigen-1-compressed-
Oxigen Phase 1 Conversion Copies_Opt-
Oxigen Phase 1 Relinquish Deed-
Balance Sheet 2015 - 2016File: Financials 2015-16.pdf-
Balance Sheet 2014 - 2015File: Financials 14-15.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Financials 2015-16.pdf-
Audited Profit and Loss Statement 2014 - 2015File: Financials 14-15.pdf-
Director's Report 2015 - 2016File: Excel Oxigen - Director Report - 15-16.pdf-
Director's Report 2014 - 2015File: Excel Oxigen - Boards' Report - 2014-2015.pdf-
Cash Flow Statement 2015 - 2016File: Financials 2015-16.pdf-
Cash Flow Statement 2014 - 2015File: Financials 14-15.pdf-
Auditor's Report 2015 - 2016File: Audit report edopl 2015-16 -2.pdf-
Auditor's Report 2014 - 2015File: audit report 14-15.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR15-16.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR 14-15.pdf-
FORM B-
Plot Excel SheetFile: PRMKARERA1251308PR171031001644 (1).xlsx-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 78 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Oxigen Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Excel Dwellings Oxigen Pvt Ltd

Excel Dwellings Oxigen Pvt Ltd has 1 registration on RERA Karnataka, including Oxigen Phase 1. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Oxigen Phase 1 is delayed beyond 30 Aug 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Oxigen Phase 1?

The registered promoter entity is Excel Dwellings Oxigen Pvt Ltd, a company as per the filing. Its CIN U70200KA2014PTC074700 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Oxigen Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Oxigen Phase 1?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

What should I check before booking in Oxigen Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Oxigen Phase 1. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Oxigen Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.