Home / Browse projects / Bengaluru Urban, Karnataka / ORION PALM DEW

Registration approved Mixed Development project

ORION PALM DEW

By M/s Orion Projects

RG-KA-07929 · RERA PRM/KA/RERA/1251/446/PR/200113/003152 · Last updated on RERA Karnataka portal: 11 Nov 2024

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 25 months
  • 3 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Apr 2025Possession promisedmoved 25 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 88 documents Report an error

ORION PALM DEW is a Mixed Development project by M/s Orion Projects in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/200113/003152 on 13 Jan 2020. Possession is promised by 30 Apr 2025. The completion date has moved by 25 months from the original filing.

At a glance

Project

  • NameORION PALM DEW
  • TypeMixed Development
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/200113/003152
  • ReraGenie IDRG-KA-07929

Builder

  • NameM/s Orion Projects
  • Entity typePartnership Firm
  • Authorized SignatoryRAJU M VARGHESE
  • Board MembersKURIEN VARGHESE, BIJU JOSEPH, THOMAS A THARAKAN

Key dates

this monthRegisteredJan 2020First promiseMar 2023Revised toApr 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on13 Jan 2020
  • Promised completion30 Apr 2025
  • Revised completionRevised to 30 Apr 2025 (originally 31 Mar 2023)
  • Buildings1 building record
  • Documents filed88 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Orion Palm Dew-----34

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 11 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities38

As on 11 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymYes-
ParksNoNot applicable
Power BackupNoNot applicable
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,700 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 19.20 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJacob Chacko
EngineerSREE KUMAR M

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2023 → not stated

No reason recorded in the filing

EX/PRM/KA/RERA/1251/446/PR/250318/003152not stated → Dec 2024

Reason as filed by the promoterAwaiting OC

ExtensionDec 2024 → Apr 2025

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed88

As listed on the registration, under the names the promoter filed them with; the newest 80 of 88 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/200113/003152 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Modification Plan Digitally SignedFile: PRJ_0217_22-23-1.pdf11 Nov 2024
LisenseFile: Building Lisense.pdf11 Nov 2024
Covering LetterFile: Covering Letter.pdf11 Nov 2024
Engineer Work CompletedFile: Engg Work Completed.pdf11 Nov 2024
Engineer Work PendingFile: Engineer Pending Work.pdf11 Nov 2024
Form 7 AffidavitFile: Affidavit for Project Extension.pdf11 Nov 2024
Form B UpdatedFile: Form B Updated.pdf3 Oct 2024
Upto Date ECFile: EC 3:3.pdf3 Oct 2024
Bulding LisenseFile: Building Lisense.pdf3 Oct 2024
Modified PlanFile: Modified Plan Orginal.pdf3 Oct 2024
Sold and Unsold UnitsFile: Sold and Unsold Units Signed.pdf9 Jan 2023
StructuralFile: Structural.pdf9 Jan 2023
Certificate from ArchitectFile: Architect.pdf9 Jan 2023
Previous Building LisenceFile: Building Liscence.PDF9 Jan 2023
Previous PlanFile: Elevation Second Third Plan.pdf9 Jan 2023
Previous sanctioned planFile: Site Ground and First plans.pdf9 Jan 2023
ORIONFile: Orion Query Final.pdf31 Dec 2019
CertificateFile: registration of firm.PDF-
Project Details-
Modified plan details site plan, floor plans, Plan Licence LetterFile: Building Lisence.pdf-
Elevation, Sections, Specifications ( If changes are there )File: Approved Plan.PDF-
List Of AllotteesFile: Consent Letters_compressed.pdf-
Consent LetterFile: Consent Letters_compressed.pdf-
Chartered Accountant CertificateFile: CA Certificate.pdf-
Notarized AffidavitFile: Afidavit.pdf-
Engineer CertificateFile: Document 595.pdf-
Architect CertificateFile: Document 596.pdf-
Structural Engineer Certificate for stability of structureFile: Document 595.pdf-
Modification of Plan DetailsFile: Plan Compressed.pdf-
Modification of Plan DetailsFile: Approved Plan.PDF-
Modification of Plan DetailsFile: commencement certificate 001.pdf-
Modification of Plan DetailsFile: commencement certificate 001.pdf-
Modification of Plan DetailsFile: SOLD AND UNSOLD FLATS.pdf-
Document 1File: NOC KSPCB.pdf-
Document 2File: NOC BESCOM.pdf-
Challan Paid ReceiptFile: Demand Note.pdf-
Building LisenceFile: Building Lisence.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Architect Ex1.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer Work Ex5.pdf-
CA Certificate for Funds UtilizationFile: Form Ex3 CA utilized fund.pdf-
Architect Certificate for Pending Work Completion Schedule.File: architect pending works.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engg pending works.pdf-
CA Certificate for Funds required for Project CompletionFile: Form Ex4 CA fund required.pdf-
AffidavitFile: Form 7 Affidavit.pdf-
Consent letter from 2/3rd of AllotteesFile: Consent Letter.pdf-
Details Of Sold/ Un-sold UnitsFile: Sold and Unsold units.pdf-
Document 1File: Consent Letters All Merged.pdf-
Document 2File: FEES PAID RECEIPT (1).pdf-
Approved Liscence-
Plan Merged-
Sale deed of Orion Projects-
Sale Agreement oforion projects - blank (2)-
Sale Deed and RTC-
Plan Merged_compressed-
Plan Merged_compressed-
allotment 1-
Yet to be Provided-
Specifications 2-
EC Merged Final-
3 (1) Affidavit_compressed-
Affidavit Joint_compressed-
KHATHA-
JDA and GPA compressed-
Approved Liscence-
CONVERSION ORDERS Compressed-
PTCL and 79 A B-
Yet to be Provided-
Yet to be Provided-
Yet to be Provided-
Plan Compressed-
Plan Merged_compressed-
Plan Merged_compressed-
CONVERSION ORDERS Compressed-
Balance Sheet 2018 - 2019File: financial statement 2019-20.PDF-
Balance Sheet 2017 - 2018File: financial statement 2018-19.PDF-
Balance Sheet 2016 - 2017File: Financial Statement 2017-18.PDF-
Income Tax Return Acknowledgement 2018 - 2019File: financial statement 2019-20.PDF-
Income Tax Return Acknowledgement 2017 - 2018File: financial statement 2018-19.PDF-
Income Tax Return Acknowledgement 2016 - 2017File: Financial Statement 2017-18.PDF-
Affidavit Form B_compressed-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 25 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ORION PALM DEW on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: M/s Orion Projects

M/s Orion Projects has 1 registration on RERA Karnataka, including ORION PALM DEW. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ORION PALM DEW is delayed beyond 30 Apr 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ORION PALM DEW?

The registered promoter entity is M/s Orion Projects, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ORION PALM DEW?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ORION PALM DEW?

The professionals named in the filing: Architect: Jacob Chacko; Engineer: SREE KUMAR M. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ORION PALM DEW?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ORION PALM DEW. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ORION PALM DEW to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.