Red flags

  • Completion date moved by 14 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2022Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 68 documents Report an error

Om Shyam is a Residential / Group Housing project by Dhirajlal Kamdar in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800002462 on 1 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2022. The completion date has moved by 14 months from the original filing.

At a glance

Project

  • NameOm Shyam
  • TypeResidential / Group Housing
  • Location
    • Kurla
    • Mumbai Suburban
    • 400077
  • Pincode400077
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800002462
  • ReraGenie IDRG-MH-08617

Builder

  • NameDhirajlal Kamdar
  • Entity typeIndividual
  • Other registrations2 more →
  • Completed2 of 3

Key dates

this monthRegisteredAug 2017First promiseApr 2021Revised toJun 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on1 Aug 2017
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 14 Apr 2021)
  • Buildings1 building record
  • Documents filed68 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Om ShyamNA190000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Om Shyam: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities17

As on 9 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes0%
Fitness CenterYes100%
Society officeYes100%

Parking filed35

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots35
Closed/Covered10
Open Space25

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area562 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Om Shyam Apartments Coop Hsg LtdKurlaMumbai Suburban

Approvals and building plan

Permissible FSI1821.88
Proposed, not sanctioned1,705 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPlot No 17 Tilak Road Ghatkopar East Mumbai 400077

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSetsquares Architects Swapnil Dashrath Sawant
PartnerRole in project
DNK Developers-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800010329Apr 2021 → Dec 2021

Reason as filed by the promoter1. In order to get the approval of the plans and the commencement certificate for the balance 16th floor and the entire 17th floor, the Promoter applied to the MCGM for availing the benefit of Regulation 33(7)(B) of the Development Control Regulations, 2034. Under the aforesaid Regulation, the benefits are granted on the basis of the number of existing members of the cooperative housing society. 2. In the present case since there were 9 members, the application was made on the basis that benefits corresponding to 9 members would be granted. However, later on it was discovered that out of the 9

EXT51800009377Apr 2021 → Jul 2021

Reason as filed by the promoter1. In order to get the approval of the plans and the commencement certificate for the balance 16th floor and the entire 17th floor, the Promoter applied to the MCGM for availing the benefit of Regulation 33(7)(B) of the Development Control Regulations, 2034. Under the aforesaid Regulation, the benefits are granted on the basis of the number of existing members of the cooperative housing society. 2. In the present case since there were 9 members, the application was made on the basis that benefits corresponding to 9 members would be granted. However, later on it was discovered that out of the 9

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jul 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 15 Mar 2023

Documents filed68

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Other - TechnicalFile: OS - RERA Letter.pdf9 May 2023
Other - TechnicalFile: OS - UPLOADED DOCUMENTS SCREEN SHOT.pdf9 May 2023
Certificates of CA (Form 3)File: FORM 3_compressed.pdf28 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf10 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5.pdf10 Apr 2023
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4.pdf10 Apr 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society registration certificate.pdf7 Apr 2023
Status of ConveyanceFile: Conveyance Deed_1-73.pdf7 Apr 2023
Status of ConveyanceFile: Conveyance Deed_74-146.pdf7 Apr 2023
Other - LegalFile: PRC_compressed.pdf7 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OS - 2301311_OC_signed.pdf15 Mar 2023
Disclosure of sold/ booked inventoryFile: Details of Inventory.pdf19 Aug 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Cooperative Housing Society Letter.pdf26 Jul 2021
Declaration about Commencement CertificateFile: Declaration about CC.pdf22 Jul 2021
Disclosure of sold/ booked inventoryFile: Sold Allotted Inventory.pdf22 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A-1.pdf21 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A-2.pdf21 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A-3.pdf21 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A-4.pdf21 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A-5.pdf21 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A-6.pdf21 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A-7.pdf21 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A-8.pdf21 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A-9.pdf21 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A-10.pdf21 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-2020.pdf21 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-2021.pdf21 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: Drawing Page 01.pdf22 Jul 2020
Commencement Certificates / NA Order for plotted developmentFile: Drawing Page 02.pdf22 Jul 2020
Commencement Certificates / NA Order for plotted developmentFile: Drawing Page 03.pdf22 Jul 2020
Commencement Certificates / NA Order for plotted developmentFile: Drawing Page 04.pdf22 Jul 2020
Commencement Certificates / NA Order for plotted developmentFile: Amended Plan Approval Letter 17th January 2020.pdf19 Jul 2020
Commencement Certificates / NA Order for plotted developmentFile: FurtherCC 29-01-2020.pdf19 Jul 2020
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf16 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: Amended Plan Approval.pdf16 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: Plan I.pdf16 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: Plan II.pdf16 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Om Shyam Form 2.pdf16 Dec 2019
Certificates of CA (Form 3)File: Om Shyam Form 3.pdf16 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Om Shyam Form 5.pdf16 Dec 2019
Certificates of CA (Form 5)File: RERA AUDIT CERTIFICATE 2017-18.pdf15 Oct 2018
Declaration in FORM BFile: DA - OS_Part1.pdf12 Sep 2017
Declaration in FORM BFile: DA - OS_Part2.pdf12 Sep 2017
Declaration in FORM BFile: DA - OS_Part3.pdf12 Sep 2017
Declaration in FORM BFile: DA - OS_Part4.pdf12 Sep 2017
Declaration in FORM BFile: DA - OS_Part5.pdf12 Sep 2017
Declaration in FORM BFile: DA - OS_Part6.pdf12 Sep 2017
Declaration in FORM BFile: DA - OS_Part7.pdf12 Sep 2017
Declaration in FORM BFile: DA - OS_Part8.pdf12 Sep 2017
Declaration in FORM BFile: DA - OS_Part9.pdf12 Sep 2017
Declaration in FORM BFile: DA - OS_Part10.pdf12 Sep 2017
Declaration in FORM BFile: DA - OS_Part11.pdf12 Sep 2017
Certificates of CA (Form 3)File: Om Shyam CA Certificate.pdf29 Jul 2017
Layout approvalFile: Further CC Om Shyam.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Further CC Om Shyam.pdf28 Jul 2017
Declaration in FORM BFile: Om Shyam Promoter Form B.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: OmShyam_Engineer_Certificate_Computer_Help.pdf27 Jul 2017
Proforma of Allotment letterFile: Om Shyam Allotment Letter.pdf27 Jul 2017
Proforma of Allotment letterFile: Draft Agreement for Sale - Om Shyam RERA Format.pdf26 Jul 2017
PAN CardFile: PAN Card.pdf25 Jul 2017
Details of encumbrancesFile: Om Shyam Encumbrance.pdf25 Jul 2017
Building plan approvalFile: Om Shyam IOD.pdf23 Jul 2017
Copy of the legal title reportFile: Title certificate.pdf23 Jul 2017
Building Plan Approval (IOD)File: Om Shyam IOD.pdf23 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Om Shyam CC - I.pdf23 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Further CC Om Shyam.pdf23 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Om Shyam Plans.pdf23 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form 1 Om shyam.pdf22 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 14 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Om Shyam on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmOm ShyamCompleted 133Lapsed / revoked 105Other 142Dot size: filed unitsN

Filed coordinates, straight-line distance. 380 registered projects within 2 km.

Builder: Dhirajlal Kamdar

Dhirajlal Kamdar has 3 registrations on MahaRERA, including Om Shyam and Bindu / Vidyavihar. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Om Shyam is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Om Shyam?

The registered promoter entity is Dhirajlal Kamdar, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Om Shyam?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Om Shyam?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Om Shyam?

The professionals named in the filing: Architect: Setsquares Architects Swapnil Dashrath Sawant. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Om Shyam?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Om Shyam. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Om Shyam to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.