OHANA

By A ONE SHELTERS PRIVATE LIMITED

RG-KA-10201 · RERA PRM/KA/RERA/1251/446/PR/171031/000634

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Dec 2023Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 53 documents Report an error

OHANA is a Residential/Group Housing project by A ONE SHELTERS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/171031/000634 on 31 Oct 2017. Possession is promised by 20 Dec 2023. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameOHANA
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/171031/000634
  • ReraGenie IDRG-KA-10201

Builder

  • NameA ONE SHELTERS PRIVATE LIMITED
  • Entity typeCompany
  • CINU70101KA2007PTC044172
  • Authorized SignatoryNIRAJ AHUJA
  • DirectorNIRAJ AHUJA
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredOct 2017First promiseMar 2023Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on31 Oct 2017
  • Promised completion20 Dec 2023
  • Revised completionRevised to 20 Dec 2023 (originally 20 Mar 2023)
  • Buildings1 building record
  • Documents filed53 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
OHANA---2850285

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymNoNot applicable
ParksYes-
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionYes-
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area14,229 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 125.00 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2023 → Dec 2023

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed53

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/171031/000634 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Form 1.pdf-
A1 CC-
scan0162-
scan0162-
draft sale deed-
draft sale deed-
khata-
scan0163-
scan0160-
BOOKING ALLOTMENT LETTER -
brouchre-
Airport NOC-
brouchre-
ilovepdf_merged-
KATHA-
SUP JDA 5102016-
ilovepdf_merged (1)-
33 BBMP Conversion Order-ilovepdf-compressed-
scan0163-
Balance Sheet 2015 - 2016File: bc sheet 2016.pdf-
Balance Sheet 2014 - 2015File: b sheet 2015.pdf-
Balance Sheet 2013 - 2014File: balance sheet 2014.pdf-
Audited Profit and Loss Statement 2015 - 2016File: p and L 2016.pdf-
Audited Profit and Loss Statement 2014 - 2015File: p l 2015.pdf-
Audited Profit and Loss Statement 2013 - 2014File: P&L 2014.pdf-
Director's Report 2015 - 2016File: DR2016.pdf-
Director's Report 2014 - 2015File: DR2015.pdf-
Director's Report 2013 - 2014File: BL2014.pdf-
Cash Flow Statement 2015 - 2016File: cash 2016.pdf-
Cash Flow Statement 2014 - 2015File: cash 2015.pdf-
Auditor's Report 2015 - 2016File: Ar2016.pdf-
Auditor's Report 2014 - 2015File: Ar2015.pdf-
Auditor's Report 2013 - 2014File: BL2014.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR 2017.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR 2016.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: ITR 2014.pdf-
form B-
Tower Excel SheetFile: PRM_KA_RERA_1251_446_PR_171031_000634.xlsx-
Loan raised documentFile: CHARGE SATISFACTION LETTER.pdf-
Stability CertificateFile: Stability Certificate.pdf-
NOC issued by the Fire Force department after completion of workFile: Fire Dept Completion Certificate.pdf-
Occupancy CertificateFile: Occupation Certificate.pdf-
Consent for operation issued by KSPCBFile: KSPCB CFO Copy.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: BESCOM Sanction.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM Sanction.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: BWSSB- Payment Receipt.pdf-
Architect certificate for having completed the work(in format no 5)File: Completion Architect Certificate.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: FORM 4 C C.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Completion Affidavit.pdf-
Completion Engineer CertificateFile: Completion Engineer Certificate.pdf-
Fire Dept Completion CertificateFile: Fire Dept Completion Certificate.pdf-
LIFT License-OhanaFile: LIFT License-Ohana.pdf-
Occupation CertificateFile: Occupation Certificate.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep OHANA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: A ONE SHELTERS PRIVATE LIMITED

A ONE SHELTERS PRIVATE LIMITED has 2 registrations on RERA Karnataka, including OHANA and Ohana Block E. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if OHANA is delayed beyond 20 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of OHANA?

The registered promoter entity is A ONE SHELTERS PRIVATE LIMITED, a company as per the filing. Its CIN U70101KA2007PTC044172 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in OHANA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in OHANA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OHANA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OHANA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.