Home / Browse projects / Bengaluru Urban, Karnataka / Oceanus Vista II

Registration approved No litigation declared Residential/Group Housing project

Oceanus Vista II

By Oceanus Dwellings Pvt Ltd

RG-KA-69386 · RERA PRM/KA/RERA/1251/446/PR/171214/001322 · Last updated on RERA Karnataka portal: 20 Jan 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 80 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Feb 2026Possession promisedmoved 80 months from the original
17 of 17Construction stages doneevery applicable stage filed complete
74 of 119Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 75 documents Report an error

Oceanus Vista II is a Residential/Group Housing project by Oceanus Dwellings Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/171214/001322 on 14 Dec 2017. Possession is promised by 28 Feb 2026. The completion date has moved by 80 months from the original filing. 45 of the 119 units on this registration are recorded sold or booked, and 17 of 17 construction stages are filed complete.

At a glance

Project

  • NameOceanus Vista II
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/171214/001322
  • ReraGenie IDRG-KA-69386

Builder

  • NameOceanus Dwellings Pvt Ltd
  • Entity typeCompany
  • CINU07010KA2003PTC031632
  • Authorized SignatoryP K CHACKO
  • OthersANAND G
  • Other registrations3 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredDec 2017First promiseJun 2019Revised toFeb 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on14 Dec 2017
  • Promised completion28 Feb 2026
  • Revised completionRevised to 28 Feb 2026 (originally 28 Jun 2019)
  • Buildings2 building records
  • Documents filed75 files

Current status

38%45 of 119 units booked
100.0%Of the estimated cost spent so far

Figures as on 20 Jan 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 4---78078
Tower 5---41041

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 20 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

17 of 17 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Painting100%
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawings100%

Progress on shared amenities41

As on 20 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsYes100%
Sewage and Drainage SystemYes100%
Parks & Tree plantingYes100%
Street LightingYes100%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservationYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes100%
Emergency Evacuation servicesYes100%
Storm water drainsYes100%
Use of renewable energyYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseYes100%
Community HallYes100%
Outdoor Sports facilityYes100%
Indoor Sports facilityYes100%
Swimming PoolYes100%
GymYes100%
ParksYes100%
Power BackupYes100%
GasYes100%
Water and SanitationYes100%
Air Conditioning And incerntionYes100%
StaircasesYes100%
LiftsYes100%
Staircases and Lift lobbies, corridor,lobbies, corridorYes100%
Fire escapesYes100%
Common entrance and exit for the building / common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areas and common storage spacesYes100%
Provision for lodging of management staff and security staffYes100%
Water conservation and renewable energyYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,176 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 30.34 cr
Cost incurredRs 30.34 cr
Spent of the estimate100.0%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 21.06 crRs 25.70 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 4.64 crRs 4.64 cr
On-site expenditure-Site OverheadRs 4.25 cr-
On-site expenditure-Consultants FeesRs 39.00 lakh-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJun 2019 → Mar 2021

No reason recorded in the filing

EX/PRM/KA/RERA/1251/446/PR/191014/001322Mar 2021 → Jun 2020

Reason as filed by the promoterothers

ExtensionJun 2020 → Feb 2026

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed75

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/171214/001322 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Q3 25-26 Vista II.pdf20 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5, Q3,2015-26, Oceanus Vista 11 T4 &T5.pdf20 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6~1.PDF20 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)20 Jan 2026
Q3 2025-26 Fire and Safety20 Jan 2026
CertificateFile: certificate incorporation ODPL.pdf-
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: Arc certificate - work completed vista II.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engg certificate - work completed vista II.pdf-
CA Certificate for Funds UtilizationFile: Oceanus_Vista_Funds_Utilzation_Certificate (1).pdf-
Architect Certificate for Pending Work Completion Schedule.File: Arc certificate - work pending vista II.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engg certificate - work pending vista II.pdf-
CA Certificate for Funds required for Project CompletionFile: Oceanus_Vista_Funds_Requried_Certificate.pdf-
AffidavitFile: Form B - Vista II.pdf-
Latest Encumbrance CertificateFile: EC - Vista II.pdf-
Consent letter from 2/3rd of AllotteesFile: Posession already given to clients letter.pdf-
Details Of Sold/ Un-sold UnitsFile: Sold Units.pdf-
Document 1File: Vista II - CC.pdf-
Document 2File: Bank Statement.pdf-
Vista II - CC-
MYSCAN_20170727_0003-
MYSCAN_20170727_0003-
SALE DEED VISTA 2-
AGREEMENT VISTA 2-
MYSCAN_20170727_0003-
MYSCAN_20170727_0009-
Sale deed - 5586-
MYSCAN_20170727_0009-
MYSCAN_20170727_0003-
ALLOTMENT LETTER-
Oceanus Vista-II - Brouchure-
REvised NOC + 6 towers-
CONSTRUCTION SPECIFICATIONS OF OCEANUS VISTA 2-
Tax paid - 16-17-Vista I & II-
Vista I&II -Khata-
Jda of Pullamma and others-
11E sktech-
Conversion order 9-2-
fire NOc-
AAI - NOC-
BESCOM NOC-
Vista - BWSSB NOC-
KSPCB NOC-
MoEF EC-
MYSCAN_20170727_0003-
Balance Sheet 2015 - 2016File: Final Accounts 2015-16.pdf-
Balance Sheet 2014 - 2015File: final accounts & Cash flow 14-15.pdf-
Balance Sheet 2013 - 2014File: final accounts 2013-14.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Final Accounts 2015-16.pdf-
Audited Profit and Loss Statement 2014 - 2015File: final accounts & Cash flow 14-15.pdf-
Audited Profit and Loss Statement 2013 - 2014File: final accounts 2013-14.pdf-
Director's Report 2015 - 2016File: auditors report.pdf-
Director's Report 2014 - 2015File: directors report.pdf-
Director's Report 2013 - 2014File: directiors report.pdf-
Cash Flow Statement 2015 - 2016File: cash flow statement ODPL 2015-16-1.pdf-
Cash Flow Statement 2014 - 2015File: final accounts & Cash flow 14-15.pdf-
Auditor's Report 2015 - 2016File: auditors report.pdf-
Auditor's Report 2014 - 2015File: auditors report.pdf-
Auditor's Report 2013 - 2014File: AUDITORS REPORT - ODPL 2013-14.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: IT acknowldgement.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: IT acknowledgement.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: IT ackomwledgment.pdf-
Form B-
Prospectus/BrochureFile: N A.pdf-
Advertisement Copy 1File: N A.pdf-
Tower Excel SheetFile: PRMKARERA1251446PR171214001322.xlsx-
Loan raised documentFile: Deed of Release.pdf-
Stability CertificateFile: Structural Stability Certificate.pdf-
NOC issued by the Fire Force department after completion of workFile: Fire CC.pdf-
Occupancy CertificateFile: Vista II OC.pdf-
Consent for operation issued by KSPCBFile: Oceanus Vista CFO.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Electircal Inspectorate.pdf-
Architect certificate for having completed the work(in format no 5)File: Form-5 Architect Closure.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: Vista II Form 4CC.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Closure Affidavit.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Oceanus Freesia Enclave-Completed-No date filed

How this compares with Bengaluru Urban

38%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 80 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Oceanus Vista II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Oceanus Dwellings Pvt Ltd

Oceanus Dwellings Pvt Ltd has 4 registrations on RERA Karnataka, including Oceanus White Meadows and Oceanus Classic. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Oceanus Vista II is delayed beyond 28 Feb 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Oceanus Vista II?

The registered promoter entity is Oceanus Dwellings Pvt Ltd, a company as per the filing. Its CIN U07010KA2003PTC031632 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Oceanus Vista II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in Oceanus Vista II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Oceanus Vista II. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Oceanus Vista II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.