Home / Browse projects / Bengaluru Urban, Karnataka / Oakstone Lakeview

Registration approved No litigation declared Residential/Group Housing project

Oakstone Lakeview

By OAKSTONE VENTURES

RG-KA-42564 · RERA PRM/KA/RERA/1251/309/PR/190822/005168 · Last updated on RERA Karnataka portal: 18 Aug 2022

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Oct 2024Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 97 documents Report an error

Oakstone Lakeview is a Residential/Group Housing project by OAKSTONE VENTURES in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/190822/005168 on 19 Aug 2022. Possession is promised by 31 Oct 2024.

At a glance

Project

  • NameOakstone Lakeview
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
    • 560086
  • Pincode560086
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/190822/005168
  • ReraGenie IDRG-KA-42564

Builder

  • NameOAKSTONE VENTURES
  • Entity typePartnership Firm
  • GSTIN29AAHFO5387K1ZI
  • Authorized Signatorymallikarjuna ramineni

Key dates

this monthRegisteredAug 2022PromisedOct 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on19 Aug 2022
  • Promised completion31 Oct 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed97 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Oakstone Lakeview---84084

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 18 Aug 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities54

As on 18 Aug 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areasYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable
OH TankYes-
STPYes-
SumpYes-
Watch Man RoomYes-
ToiletYes-
Parking Stair CaseYes-
Lift Machine RoomYes-
Stair case Head RoomYes-
Electrical RoomYes-
Generator RoomYes-
GYMYes-
jogging TrackYes-
Shuttle CourtYes-
Cricket NetYes-

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,046 sq m
Named landowners2
LandownerVillageDistrict
V Lakshmi--
V Lakshmi--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 18.00 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 15.95 cr-
Payment of taxesRs 80.00 lakh-
On-site expenditure-Salaries of workersRs 45.00 lakh-
On-site expenditure-Site OverheadRs 30.15 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 30.00 lakh-
On-site expenditure-Consultants FeesRs 20.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectT V Srinivas
EngineerG Mohan Reddy
Chartered AccountantHemdari Kolla

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed97

As listed on the registration, under the names the promoter filed them with; the newest 80 of 97 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/190822/005168 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Supplemental Partnership DeedFile: SupplementaryDeed.pdf18 Aug 2022
BESCOM NOC PAYMENT RECEIPTFile: BESCOMNOCPAYMENTRECEIPT.pdf14 Jun 2022
BWSSB NOC PAYMENT RECEIPTFile: BWSSBNOCPAYMENTRECEIPT.pdf14 Jun 2022
Highlighted STP demarcated site plan along with STP design and drawings based on the KSPCBFile: KSPCBNOCSTPDEMARCATIONREPORT.pdf14 Jun 2022
Extract of Master PlanFile: BDA Master Plan Merged.pdf6 Jun 2022
Upload Location and Demarcation Drawing. (Village map Based)File: Village Map view.pdf6 Jun 2022
Break up development Details - Inventory wiseFile: Oakstone ventures Oakstone Lake View - uploaded.xlsx6 Jun 2022
BWSSB NOC along with the copy of fee paid receiptFile: BWSSB Noc,Payment Receipt - 2.pdf6 Jun 2022
BESCOM NOC along with the copy of fee paid receiptFile: BESCOM NOC, Payment Receipt - 1.pdf6 Jun 2022
Highlighted STP demarcated site plan along with STP design and drawingsFile: KSPCB NOC,STP Demarcation, Report - 3.pdf6 Jun 2022
Designated Bank account DetailsFile: Bank Name - Document to upload.pdf14 May 2022
Chartered Accountant certificate in FORM 01File: CA Certificate.pdf14 May 2022
breakup of development details and inventory DetailsFile: Oakstone ventures Oakstone Lake View - uploaded.xlsx14 May 2022
BWSSB NOCFile: BWSSB NOC Application for upload.pdf14 May 2022
BESCOM NOCFile: BESCOM NOC - Applied for upload.jpg14 May 2022
Agreement for SaleFile: Agreement for sale.pdf14 May 2022
2.1 notarized Non- litigation affidavitFile: No Dispute.pdf13 Apr 2022
2.2 notarized form-B in RERAFile: Form B.pdf13 Apr 2022
2.3 Notarized JA cum Declaration in RERAFile: JDA.pdf13 Apr 2022
2.4 ec incomplete hence need EC FROM2005 TO uptodateFile: EC.pdf13 Apr 2022
2.4 ec incomplete hence need EC FROM2005 TO uptodateFile: EC1.pdf13 Apr 2022
2.5 title deed/other registered documents in the name of v k babu for project synoFile: Sale Deed.pdf13 Apr 2022
2.5 title deed/other registered documents in the name of v k babu for project synoFile: Sale Deed1-compressed.pdf13 Apr 2022
2.6 Upload the certified ub-registrar regarding value of the propertyFile: Guidance Value.pdf13 Apr 2022
3. 1) Upload Single layout Plan. 2)Upload Single layout Order.File: Conversion 22 5, 22 6_compressed.pdf13 Apr 2022
3.1) Upload Single layout Plan. 2)Upload Single layout Order.File: Mutation.pdf13 Apr 2022
3. 1) Upload Single layout Plan. 2)Upload Single layout Order.File: RTC.pdf13 Apr 2022
3.7 Original KSPCB NOCFile: Pollution.pdf13 Apr 2022
3.7 STP Demarcation DetailsFile: STP.pdf13 Apr 2022
4. 7upload the section 3(1) notarized affidavitFile: 3(1).pdf13 Apr 2022
4.8 NOC issued by BWSSBFile: NOC (3).pdf13 Apr 2022
4.9 AOSFile: AOS.pdf13 Apr 2022
4.10 correct copy of self attested project specificationFile: Project Specification.pdf13 Apr 2022
4.11 highlighted STP demarcated sit plan along with STP design and drawingsFile: STP.pdf13 Apr 2022
RTC, survey 22/5-
Mutation, survey 22/5-
Encumbrance Certificate, survey 22/5-
Conversion/Alienation Order, survey 22/5-
Sale/Title/Gift Deed, survey 22/5-
JDA, survey 22/5-
Khatha, survey 22/5-
RTC, survey 22/6-
Mutation, survey 22/6-
Encumbrance Certificate, survey 22/6-
Conversion/Alienation Order, survey 22/6-
Sale/Title/Gift Deed, survey 22/6-
JDA, survey 22/6-
Khatha, survey 22/6-
Registration CertificateFile: partnership deed - Compressed.pdf-
Partnership DeedFile: partnership deed - Compressed.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Legal opinion.pdf-
Project Plan-
Project Specification-
581 licence - Building Plan Approval-
581 licence - Building Plan Approval-
Legal opinion-
JDA_compressed-
Conversion 22 5, 22 6_compressed-
Gift deed-
Proforma Agreement to sale-
Sale Deed Proforma-
Brouchure - RERA_compressed-
Form B Declaration - Oakstone_compressed-
Form B Declaration - Oakstone_compressed-
JDA-
NOC Application-
NOC Application-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Oakstone Lakeview on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmOakstone LakeviewOther 51Dot size: filed unitsN

Filed coordinates, straight-line distance. 51 registered projects within 2 km.

Builder: OAKSTONE VENTURES

OAKSTONE VENTURES has 1 registration on RERA Karnataka, including Oakstone Lakeview. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Oakstone Lakeview is delayed beyond 31 Oct 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Oakstone Lakeview?

The registered promoter entity is OAKSTONE VENTURES, a partnership firm as per the filing. Its GSTIN 29AAHFO5387K1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Oakstone Lakeview?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Oakstone Lakeview?

The professionals named in the filing: Architect: T V Srinivas; Engineer: G Mohan Reddy; Chartered Accountant: Hemdari Kolla. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Oakstone Lakeview?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Oakstone Lakeview. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Oakstone Lakeview to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.