Registration approved Residential/Group Housing project

Northwinds-2

By Gaurav & Patel Developers

RG-KA-05919 · RERA PRM/KA/RERA/1251/309/PR/211008/004350 · Last updated on RERA Karnataka portal: 5 Oct 2021

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2022Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 100 documents Report an error

Northwinds-2 is a Residential/Group Housing project by Gaurav & Patel Developers in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/211008/004350 on 8 Oct 2021. Possession is promised by 30 Jun 2022.

At a glance

Project

  • NameNorthwinds-2
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/211008/004350
  • ReraGenie IDRG-KA-05919

Builder

  • NameGaurav & Patel Developers
  • Entity typePartnership Firm
  • Authorized SignatorySrinivas G Patel
  • OthersSrinivas G Patel, V Chandrasekar, Srinivas G Patel

Key dates

this monthRegisteredOct 2021PromisedJun 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on8 Oct 2021
  • Promised completion30 Jun 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed100 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
01---28028

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 5 Oct 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing workNot applicable
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 5 Oct 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsNoNot applicable
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,337 sq m
Named landowners1
LandownerVillageDistrict
Srinivas G Patel and others--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 7.50 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectB Sathyanarayana
EngineerB Sathyanarayana

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed100

As listed on the registration, under the names the promoter filed them with; the newest 80 of 100 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/211008/004350 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
NOCFile: NOC Water.pdf5 Oct 2021
BESCOM-NOCFile: NOC-BESCOM.pdf25 Aug 2021
BWSSB-NOCFile: NOC-BWSSB.pdf25 Aug 2021
Bank account in the name of the project Northwinds-2File: Bank passbook details.pdf16 Aug 2021
Sec 3(1) non violation AffidavitFile: Sec 3(1) Non-violation Affidavit.pdf16 Aug 2021
NOC-BWSSBFile: NOC-Water.pdf16 Aug 2021
NOC-PCBFile: NOC-KSPCB.pdf16 Aug 2021
Clarification about advertisementFile: Clarification about Advertisement.pdf16 Aug 2021
Occupancy CertificateFile: Occupancy Certificate.pdf16 Aug 2021
Penalty detailsFile: Penalty details.pdf1 Apr 2021
Sale deed site no.58 Linga ReddyFile: site no.58_Linga Reddy_opt.pdf1 Apr 2021
Sale deed site no.59_Prakash babuFile: site no.59_Prakash babu_opt.pdf1 Apr 2021
Sale deed site no.60_Ashok BabuFile: site no.60_Ashok Babu_opt.pdf1 Apr 2021
Sale deed site no.61_Ashok BabuFile: site no.61_Ashok Babu_opt.pdf1 Apr 2021
Sale deed site no.62& 63_Prakash BabuFile: site no.62& 63_Prakash Babu_opt.pdf1 Apr 2021
Sale deed site no.64_Srinivas G PatelFile: site no.64_Srinivas G Patel_opt.pdf1 Apr 2021
Sale deed site no.65_Srinivas G patelFile: site no.65_Srinivas G patel_opt.pdf1 Apr 2021
Sale deed site no.66_Ramesh BabuFile: site no.66_Ramesh Babu_opt.pdf1 Apr 2021
Sale deed site no.67_Srinivasa ReddyFile: site no.67_Srinivasa Reddy_opt.pdf1 Apr 2021
Sale deed site no.68_Srinivas G patelFile: site no.68_Srinivas G patel_opt.pdf1 Apr 2021
Sale deed site no.69_ShivanandFile: site no.69_Shivanand_opt.pdf1 Apr 2021
Encumbrance certificateFile: EC from 01.04.2004 10.12.2020.pdf1 Apr 2021
Notarised Form BFile: Form B declaration supported by Affidavit.pdf1 Apr 2021
Notarised joint affidavitFile: Affidavit cum declaration.pdf1 Apr 2021
Associated vendor detailsFile: Associated details.pdf1 Apr 2021
PlanFile: plan.pdf1 Apr 2021
Project specificationsFile: Specifications.pdf1 Apr 2021
Affidavit under sec 3(1)File: Affidavit.pdf1 Apr 2021
KSPCB NOCFile: KSPCB_CFE Consent.pdf1 Apr 2021
BWSSB ACKFile: BWSSB-ACK.pdf1 Apr 2021
Occupancy certificateFile: Occupancy certificate.pdf.pdf1 Apr 2021
KAT IA ORDERFile: North Winds KAT.pdf27 Dec 2019
CertificateFile: gp.pdf-
Patel CC-
PLAIN SHEET-
b final-
PLAIN SHEET-
Patel sale agreement-
Patel Amalgamation deed -
b final-
PLAIN SHEET-
Patel_Allotment letter-
PLAIN SHEET-
PLAIN SHEET-
Patel EC -
Patel_Khata-
Patel JDA-
PLAIN SHEET-
Conversion_gaurav & Pat-
PLAIN SHEET-
PLAIN SHEET-
PLAIN SHEET-
PLAIN SHEET-
PLAIN SHEET-
PLAIN SHEET-
Patel BWSSSB-
Patel KSPCB-
PLAIN SHEET-
PLAIN SHEET-
PLAIN SHEET-
Unnamed document-
PLAIN SHEET-
PLAIN SHEET-
PLAIN SHEET-
PLAIN SHEET-
PLAIN SHEET-
PLAIN SHEET-
PLAIN SHEET-
PLAIN SHEET-
PLAIN SHEET-
PLAIN SHEET-
Patel Conversion-
PLAIN SHEET-
Balance Sheet 2016 - 2017File: Patel Bal sheet_16-17.pdf-
Balance Sheet 2015 - 2016File: Patel Bal sheet_15-16.pdf-
Balance Sheet 2014 - 2015File: PLAIN SHEET.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Patel Bal sheet_16-17.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Patel Bal sheet_15-16.pdf-
Audited Profit and Loss Statement 2014 - 2015File: PLAIN SHEET.pdf-
Director's Report 2016 - 2017File: PLAIN SHEET.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Northwinds-2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmNorthwinds-2Other 50Dot size: filed unitsN

Filed coordinates, straight-line distance. 50 registered projects within 2 km.

Builder: Gaurav & Patel Developers

Gaurav & Patel Developers has 1 registration on RERA Karnataka, including Northwinds-2. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Northwinds-2 is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Northwinds-2?

The registered promoter entity is Gaurav & Patel Developers, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Northwinds-2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Northwinds-2?

The professionals named in the filing: Architect: B Sathyanarayana; Engineer: B Sathyanarayana. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Northwinds-2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Northwinds-2. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Northwinds-2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.