Home / Browse projects / Belagavi, Karnataka / NORTH EAST AVENUE

Registration approved No litigation declared Mixed Development project

NORTH EAST AVENUE

By Pristine Developer and Builders

RG-KA-94933 · RERA PRM/KA/RERA/1249/447/PR/240522/004916 · Last updated on RERA Karnataka portal: 5 Mar 2022

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2023Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 68 documents Report an error

NORTH EAST AVENUE is a Mixed Development project by Pristine Developer and Builders in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/240522/004916 on 24 May 2022. Possession is promised by 31 Dec 2023.

At a glance

Project

  • NameNORTH EAST AVENUE
  • TypeMixed Development
  • Location
    • Belagavi
    • 590001
  • Pincode590001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1249/447/PR/240522/004916
  • ReraGenie IDRG-KA-94933

Builder

  • NamePristine Developer and Builders
  • Entity typePartnership Firm
  • GSTIN29AAZFP8117E1ZM
  • Authorized SignatoryMOHAMMED USMAN M SHAIKH

Key dates

this monthRegisteredMay 2022PromisedDec 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on24 May 2022
  • Promised completion31 Dec 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed68 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
North East Aevnue-----27

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 5 Mar 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 5 Mar 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceNoNot applicable
Outer WallYes-
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area722 sq m
Named landowners1
LandownerVillageDistrict
SALAUDDIN BASHIR AHMED KHATIB--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 4.00 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 4.00 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHAHBAZ KHATIB
EngineerVINAY JANARDA BEHERE
Chartered AccountantChannabasavraj Umesh Bolmal

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed68

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/240522/004916 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
clarification why the Registration of the Gift Deed is not applicableFile: about Gift Deed Registration.pdf5 Mar 2022
proforma of Agreement of saleFile: Format of Agreement of sale (1).pdf5 Mar 2022
BALANCE SHEET 2020-21 WITH UDINFile: BALANCE SHEET.pdf13 Feb 2022
PROFIT AND LOSS 2020-21 WITH UDINFile: PROFIT AND LOSS ACCOUNT.pdf13 Feb 2022
CLARIFICATION ABOUT PENT HOUSE HEIGHTFile: Clarification about Pent House height.pdf13 Feb 2022
ATTESTED COPY OF POLLUTION NOCFile: ATTESTED POLLUTION NOC.pdf13 Feb 2022
WATER NOCFile: Water Board NOC.PDF13 Feb 2022
DEMARCATION OF PROVISION OF STP IN APPROVED BUILDING PERMISSIONFile: Provision of the STP in the Building permission approved plan.pdf13 Feb 2022
ABOUT REGISTRATION OF THE GIFT DEEDFile: about Gift Deed Registration.pdf13 Feb 2022
DRAFT OF SALE DEEDFile: DEED OF SALE FIRST FLAT KHATIB - BLANK FORMAT 11-02-2022-converted.pdf13 Feb 2022
DRAFT OF AGREEMENT OF SALEFile: AGREEMENT OF SALE FIRST FLAT- BLANK FORMAT-converted.pdf13 Feb 2022
FIRM CERTIFICATEFile: firm certificate pristine.pdf19 Jan 2022
ABOUT P & l AND BALANCE SHEET 2020-21File: ABOUT P & L AND Balance sheet 2020-21.pdf19 Jan 2022
POLLUTION NOCFile: POLLUTION NOC (2).pdf19 Jan 2022
ABOUT REGISTRATION OF GIFT DEEDFile: about Gift Deed Registration.pdf19 Jan 2022
Section 3(1) notarized affidavitFile: notarized Sec 3 Affidavit.pdf19 Jan 2022
Provision of STP in the project is demarcatedFile: Demarcation of Septic tank in Approved plan.pdf19 Jan 2022
clarification about BrochureFile: CLARIFICATION ABOUT BROUCHER.jpeg19 Jan 2022
format of agreement of sale with details of vendors, Project specifications, Payment plan, timelinesFile: AGREEMENT OF SALE FIRST FLAT- BLANK FORMAT (1).pdf19 Jan 2022
approved building drawing showing the clear height of the building with elevation and section planFile: Building permission approved plan with elevation, section plan and height of the building.19 Jan 2022
Registration CertificateFile: firm certificate pristine.pdf-
Partnership DeedFile: PARTNERSHIP DEED (1).pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form 1_compressed.pdf-
Certificate issued by Architect Form 2File: Form 2.jpeg-
Certificate issued by Engineer Form 3File: Form 3.jpeg-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Form 1_compressed.pdf-
Commencement certificate (2)-
HESCOM NOC-
APPROVED PLAN (1)-
Building permission approved plan-
APPROVED PLAN (1)-
APPROVED PLAN (1)-
APPROVED PLAN (1)-
Self attested Project Specification-
APPROVED PLAN (1)-
Stability certificate-
Joint Development agreement-
oral Gift Deed-
AGREEMENT OF SALE FIRST FLAT- BLANK FORMAT-
Proforma of Allotment letter-
Form B_compressed-
Affidavit Sec 3(1)-
Affidavit cum declaration-
HESCOM NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
POLLUTION NOC (1)_compressed-
DEVELOPMENT DETAILS PAGE-

How this compares with Belagavi

24%of Belagavi projects moved their completion datethis one has not
0%of Belagavi registrations are shown as withdrawn or revokedthis one is not

Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.

Keep NORTH EAST AVENUE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Belagavi460+ in Belagavi

2 kmNORTH EAST AVENUEOther 61Dot size: filed unitsN

Filed coordinates, straight-line distance. 61 registered projects within 2 km.

Builder: Pristine Developer and Builders

Pristine Developer and Builders has 1 registration on RERA Karnataka, including NORTH EAST AVENUE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Belagavi district page.

Frequently asked questions

What are my rights if NORTH EAST AVENUE is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of NORTH EAST AVENUE?

The registered promoter entity is Pristine Developer and Builders, a partnership firm as per the filing. Its GSTIN 29AAZFP8117E1ZM can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in NORTH EAST AVENUE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at NORTH EAST AVENUE?

The professionals named in the filing: Architect: SHAHBAZ KHATIB; Engineer: VINAY JANARDA BEHERE; Chartered Accountant: Channabasavraj Umesh Bolmal. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NORTH EAST AVENUE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NORTH EAST AVENUE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NORTH EAST AVENUE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.