Home / Browse projects / Belagavi, Karnataka / KILLEDAR PRIDE
KILLEDAR PRIDE
RG-KA-29909 · RERA PRM/KA/RERA/1249/447/PR/280324/006729 · Last updated on RERA Karnataka portal: 6 Mar 2024
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
KILLEDAR PRIDE is a Mixed Development project by M/s. UNIQUE CONSTRUCTIONS in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/280324/006729 on 28 Mar 2024. Possession is promised by 31 Dec 2026.
At a glance
Project
- NameKILLEDAR PRIDE
- TypeMixed Development
- Location
- Belagavi
- 590001
- Pincode590001
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1249/447/PR/280324/006729
- ReraGenie IDRG-KA-29909
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on28 Mar 2024
- Promised completion31 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed93 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| KILLEDAR PRIDE | - | - | - | - | - | 20 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 6 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Upto Plinth Level | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| Retaining wall (All types) | - |
| RCC or MS Framed structure | - |
| Masonry Construction | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Painting | - |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | - |
| Internal and External work including landscapes as per sanctioned drawings | Not applicable |
Progress on shared amenities40
As on 6 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Sewage and Drainage System | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Piped Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Corridor/Lobbies | No | Not applicable |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | No | Not applicable |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MRS. ANJUM ZUBERAHMED KILLEDAR | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 3.47 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | KHALEEL AHEMED JALIHAL |
| Engineer | VINAY BEHERE |
| Chartered Accountant | ASHOK MUDNNUR |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed93
As listed on the registration, under the names the promoter filed them with; the newest 80 of 93 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/280324/006729 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CA CERTIFICATE REGARDING SALES OF RS. 48170000/- BU SALE OF FLATFile: CERTIFICATE OF CA FOR AMOUNT.pdf | 6 Mar 2024 |
| CLARIFICATION ABOUT COLLECTION OF AMOUNTFile: Clarification about amount in financial statement - Copy.pdf | 11 Feb 2024 |
| Source of FundFile: Source of Fund.pdf | 11 Feb 2024 |
| Source of Fund with documentsFile: Source of fund with supporting document.pdf | 11 Feb 2024 |
| Clarification about amount in financial statementFile: about financial statement.pdf | 6 Oct 2023 |
| Source of fundFile: Source of Fund.pdf | 6 Oct 2023 |
| BALANCE SHEET 2019-20 WITH CA UDINFile: Balance Sheet 2019-20 with CA UDIN.pdf | 4 Jul 2023 |
| BALANCE SHEET 2020-21 WITH CA UDINFile: Balance sheet 2020-21 with CA UDIN.pdf | 4 Jul 2023 |
| BALANCE SHEET 2021-22 WITH CA UDINFile: balance sheet 2021-22 with CA UDIN.pdf | 4 Jul 2023 |
| P & L 2019-20 WITH CA UDINFile: P & L 2019-20 with CA UDIN.pdf | 4 Jul 2023 |
| P & L 2020-21 WITH CA UDINFile: P & L 2020-21 with CA UDIN.pdf | 4 Jul 2023 |
| P & L 2021-22 WITH CA UDINFile: P & L 2021-22 with CA UDIN.pdf | 4 Jul 2023 |
| draft of agreement of saleFile: Draft of Agreement of sale.pdf | 4 Jul 2023 |
| source of water clarification with signedFile: SOURCE OF WATER.jpeg | 4 Jul 2023 |
| reference of NA orderFile: NA ORDER REFERENCE.pdf | 4 Jul 2023 |
| NA orderFile: NA order.jpeg | 4 Jul 2023 |
| about NA OrderFile: about NA order.pdf | 4 Jul 2023 |
| PROFIT AND LOSS ACCOUNT 2019-20 WITH CA UDINFile: P & L 2019-20 with CA UDIN.pdf | 10 Feb 2023 |
| PROFIT AND LOSS ACCOUNT 2020-21 WITH CA UDINFile: P & L 2020-21 with CA UDIN.pdf | 10 Feb 2023 |
| PROFIT AND LOSS ACCOUNT 2021-22 WITH CA UDINFile: P & L 2021-22 with CA UDIN.pdf | 10 Feb 2023 |
| BALANCE SHEET 2019-20 WITH CA UDINFile: Balance Sheet 2019-20 with CA UDIN.pdf | 10 Feb 2023 |
| BALANCE SHEET 2020-21 WITH CA UDINFile: Balance sheet 2020-21 with CA UDIN.pdf | 10 Feb 2023 |
| BALANCE SHEET 2021-22 WITH CA UDINFile: balance sheet 2021-22 with CA UDIN.pdf | 10 Feb 2023 |
| BANK LETTER FOR RERA DESIGNATED ACCOUNTFile: Bank Letter for RERA desingated accoun.pdf | 10 Feb 2023 |
| ABOUT CONVERSION ORDERFile: NA order.jpeg | 10 Feb 2023 |
| FORM B WITH PROJECT NAMEFile: Form B with project name.pdf | 10 Feb 2023 |
| JOINT AFFIDAVIT CUM DECLARATION WITH DEPONENT SIGNFile: Joint affidavit cum declaration.pdf | 10 Feb 2023 |
| ADVOCATE SEARCH REPORTFile: Legal Opinion.pdf | 10 Feb 2023 |
| ABOUT WATER SUPPLYFile: clarification about water supply.pdf | 10 Feb 2023 |
| HESCOM NOCFile: HESCOM NOC.pdf | 10 Feb 2023 |
| PROFORMA OF AGREEMENT AS NOTIFIEDFile: Draft of Agreement of sale.pdf | 10 Feb 2023 |
| Registration CertificateFile: Firm certificate.pdf | - |
| Partnership DeedFile: partnership deed.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: FORM 1-CA.pdf | - |
| Certificate issued by Architect Form 2File: Killedar Pride form 2.pdf | - |
| Certificate issued by Engineer Form 3File: killedar pride Form 3.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: No litigation affidavit.pdf | - |
| Certificate from Chartered AccountFile: FORM 1-CA.pdf | - |
| Balance Sheet 2021 - 2022File: balance sheet 2021-22 with CA UDIN.pdf | - |
| Balance Sheet 2020 - 2021File: Balance sheet 2020-21 with CA UDIN.pdf | - |
| Balance Sheet 2019 - 2020File: Balance Sheet 2019-20 with CA UDIN.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: P & L 2021-22 with CA UDIN.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: P & L 2020-21 with CA UDIN.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: P & L 2019-20 with CA UDIN.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: IT ack 2021-22.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: IT ack 2020-21.pdf | - |
| Income Tax Return Acknowledgement 2019 - 2020File: IT ack 2019-20.pdf | - |
| Killedar Building Permission | - |
| Water NOC | - |
| KILLEDAR PRIDE | - |
| KILLEDAR PRIDE | - |
| KILLEDAR PRIDE | - |
| KILLEDAR PRIDE | - |
| KILLEDAR PRIDE | - |
| PROJECT SPECATION (1) | - |
| KILLEDAR PRIDE | - |
| KILLEDAR PRIDE | - |
| Stability Certificate Killedar | - |
| Killedar JVD | - |
| Draft of Agreement of sale | - |
| Allotment Letter | - |
| From B_compressed | - |
| Sec 3 Affidavit Killedar | - |
| Joint affidavit cun declaration Killedar | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Elite Residency II | CTS 4857/118 , LAST BUS STOP,DOUBLE ROAD , SADASHIV NAGAR ,BELAGAVI | Ongoing | Mar 2026 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Belagavi
Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.
Keep KILLEDAR PRIDE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Belagavi460+ in Belagavi
Filed coordinates, straight-line distance. 54 registered projects within 2 km.
SHIVNERI Apartment
SHIVNERI CONSTRUCTIONS
ORIONIS OPAL
M/s. VARDHAMAN VENTURES
NORTH EAST AVENUE
Pristine Developer and Builders
NORTH ENCLAVE
PRISTINE CONSTRUCTIONS
AADDI HOMES
PRATAP NALAVADE
MOTI MAHAL
A H REALTY
See every Belagavi project, with the district possession charts
Builder: M/s. UNIQUE CONSTRUCTIONS
M/s. UNIQUE CONSTRUCTIONS has 5 registrations on RERA Karnataka, including ELLITE RESIDENCY I and KILLEDAR PRIDE 2. Its filings declare 2 earlier projects, none of them declared completed. Read the full track record. See more projects on the Belagavi district page.
Frequently asked questions
What are my rights if KILLEDAR PRIDE is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of KILLEDAR PRIDE?
The registered promoter entity is M/s. UNIQUE CONSTRUCTIONS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in KILLEDAR PRIDE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at KILLEDAR PRIDE?
The professionals named in the filing: Architect: KHALEEL AHEMED JALIHAL; Engineer: VINAY BEHERE; Chartered Accountant: ASHOK MUDNNUR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KILLEDAR PRIDE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback