Home / Browse projects / Bengaluru Urban, Karnataka / Nitesh Napa Valley

Registration approved No litigation declared Residential/Group Housing project

Nitesh Napa Valley

By True-Blue Realty Private Limited

RG-KA-79096 · RERA TOR/PRM/KA/RERA/1251/309/PR/211028/002104 · Last updated on RERA Karnataka portal: 16 Jan 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 57 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Dec 2025Possession promisedmoved 57 months from the original
7 of 17Construction stages donefurthest along: Plastering inside, 99%
4 of 134Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 91 documents Report an error

Nitesh Napa Valley is a Residential/Group Housing project by True-Blue Realty Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as TOR/PRM/KA/RERA/1251/309/PR/211028/002104 on 28 Oct 2021. Possession is promised by 31 Dec 2025. The completion date has moved by 57 months from the original filing. 130 of the 134 units on this registration are recorded sold or booked, and 7 of 17 construction stages are filed complete.

At a glance

Project

  • NameNitesh Napa Valley
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.TOR/PRM/KA/RERA/1251/309/PR/211028/002104
  • ReraGenie IDRG-KA-79096

Builder

  • NameTrue-Blue Realty Private Limited
  • Entity typeCompany
  • CINU45202KA2020PTC132034
  • Authorized SignatoryDega Venkatarami Reddy

Key dates

this monthRegisteredOct 2021First promiseMar 2021Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on28 Oct 2021
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Mar 2021)
  • Buildings4 building records
  • Documents filed91 files

Current status

97%130 of 134 units booked
98.6%Of the estimated cost spent so far

Figures as on 16 Jan 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A ( G+2 Floor ) A Type Villas---25025
Block B ( G+2 Floor ) B Type Villas---86086
Block C ( G+2 Floor ) C Type Villas---22022
Club House---101

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 16 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 17 construction stages are filed complete. The stage furthest along is Plastering inside, at 99%.

Building: 99% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling99%
Joinery: Doors, Windows, Ventilators etc99%
Basic work of Water supply, Sanitary and Electrification99%
Dadoing, Skirting, Flooring, Tiles work (All types)99%
Railing and Grill fixing99%
Electrification, Water supply and Sanitary Finishing99%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)99%
Painting99%
Elevation work99%
Internal and External work including landscapes as per santioned drawings99%

Progress on shared amenities41

As on 16 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes99%
Internal Roads & FootpathsYes99%
Sewage and Drainage SystemYes99%
Parks & Tree plantingYes90%
Street LightingYes90%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes99%
Water conservationYes99%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes100%
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes99%
Use of renewable energyYes0%
Water conservation/rain water harvesting/recharge of ground waterYes99%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseYes100%
Community HallNoNot applicable
Outdoor Sports facilityYes100%
Indoor Sports facilityYes100%
Swimming PoolYes100%
GymNoNot applicable
ParksYes100%
Power BackupYes99%
GasNoNot applicable
Water and SanitationYes99%
Air Conditioning And incerntionNoNot applicable
StaircasesYes100%
LiftsNoNot applicable
Staircases and Lift lobbies, corridor,lobbies, corridorNoNot applicable
Fire escapesYes0%
Common entrance and exit for the building / common portico/foyer/verandahYes99%
BasementNoNot applicable
TerraceYes100%
Outer WallYes100%
Open parking areas and common storage spacesYes100%
Provision for lodging of management staff and security staffYes100%
Water conservation and renewable energyYes99%

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area81,442 sq m
Named landowners2
LandownerVillageDistrict
Ansar M--
Kailashnath Patil and SHAKUNTALA S. SUGANDHI--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 156.73 cr
Cost incurredRs 154.58 cr
Spent of the estimate98.63%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 156.73 crRs 154.58 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDesign Front Architects
EngineerBase Engineering Services

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2021 → Sep 2021

No reason recorded in the filing

EX/PRM/KA/RERA/1251/309/PR/220225/002104Sep 2021 → Dec 2022

Reason as filed by the promoterothers

ExtensionDec 2022 → Dec 2025

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed91

As listed on the registration, under the names the promoter filed them with; the newest 80 of 91 are shown. The files themselves are available at source: search the registration number TOR/PRM/KA/RERA/1251/309/PR/211028/002104 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM-4 CA Q3 2025 26.pdf16 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: FORM-5 ARCHITECT Q3 2025 26.pdf16 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 ENGINEER Q3 2025 26.pdf16 Jan 2026
Q3 2025-26 Registration documentFile: Brieft on Project Transfer Association Details.pdf16 Jan 2026
Affidavit For ExtentionFile: Affidavit For Extention.pdf24 Jan 2022
Affidavit com DeclarationFile: Affidavi cum Declaration.pdf24 Jan 2022
Allottees Consent LetterFile: Concent Letter from Purchasers_compressed.pdf24 Jan 2022
Structural Stability Certificate BuildingFile: Stability Certificate.jpg24 Jan 2022
STP-Drawing with brief noteFile: STP drawing_merged_compressed.pdf24 Jan 2022
notarized Joint affidavit cum declaration of incoming promoterFile: Affidavit of incoming promoter.pdf3 Dec 2020
Affidavit of outgoing promoterFile: Affidavit of outgoing promoter.pdf3 Dec 2020
notarized FOrm B of incoming promoterFile: Form B of new developer.pdf3 Dec 2020
New list of allotteesFile: List of 44 Villas.pdf3 Dec 2020
New list of RERA cases of projectFile: List Of All Complaints.pdf3 Dec 2020
Cheque of RERA account by name 'True-Blue Realty Private Limited RERA Account'File: RERA Account cheque.pdf3 Dec 2020
Allottee consent letters - 1File: Consent Letters I (8 Nos)_compressed.pdf3 Dec 2020
Allottee consent letters - 2File: Consent Letters II (13 Nos.).pdf3 Dec 2020
Allottee consent letters - 3File: Consent Letters III (13 Nos).pdf3 Dec 2020
Allottee consent letters - 4File: Consent Letter IV (5 Nos).pdf3 Dec 2020
Allottee consent letters - 5File: Consent Letters V (6 Nos).pdf3 Dec 2020
EC - 09.12.2015 to 25.02.2016 (Sy No.24)File: 19. BD-NNV-EC - from - 09.12.2015 to 25.02.2016 (Sy No.24).pdf3 Dec 2020
EC - 01.04.2004 to 08.09.2016 (Sy No.24)File: 20. BD-NNV-EC - from - 01.04.2004 to 08.09.2016 (Sy No.24).pdf3 Dec 2020
EC - 25.02.2016 to 11.07.2016 (Sy No.24)File: 21. BD-NNV-EC - from - 25.02.2016 to 11.07.2016 (Sy No.24).pdf3 Dec 2020
EC - 11.07.2016 to 16.03.2017 (Sy No.24)File: 22. BD-NNV-EC - from - 11.07.2016 to 16.03.2017 (Sy No.24).pdf3 Dec 2020
EC - 01.03.2017 to 07.08.2017 ( Sy No.24)File: 23. BD-NNV-EC - from - 01.03.2017 to 07.08.2017 ( Sy No.24).pdf3 Dec 2020
EC - 08.09.2016 to 06.11.2020 (Sy No.24)File: 24. BD-NNV -EC - from - 08.09.2016 to 06.11.2020 (Sy No.24) .pdf3 Dec 2020
EC - 09.12.2013 to 25.02.2016 (Sy No.26)File: 21. BD-NNV-EC - from - 09.12.2013 to 25.02.2016 (Sy No.26).pdf3 Dec 2020
EC - 09.12.2015 to 25.02.2016 (Sy No.26)File: 22. BD-NNV-EC - from - 09.12.2015 to 25.02.2016 (Sy No.26).pdf3 Dec 2020
EC - 01.04.2004 to 03.09.2016 (Sy No 26)File: 23. BD-NNV-EC - from - 01.04.2004 to 03.09.2016 (Sy No 26).pdf3 Dec 2020
EC - 25.02.2016 to 11.07.2016 (Sy No.26)File: 24. BD-NNV-EC - from - 25.02.2016 to 11.07.2016 (Sy No.26).pdf3 Dec 2020
EC - 11.07.2016 to 16.03.2017 (Sy No.26)File: 25. BD-NNV-EC - from - 11.07.2016 to 16.03.2017 (Sy No.26).pdf3 Dec 2020
EC - 01.03.2017 to 07.08.2017 (Sy No.26)File: 26. BD-NNV-EC - from - 01.03.2017 to 07.08.2017 (Sy No.26).pdf3 Dec 2020
EC - 04.09.2016 to 06.11.2020 (Sy No.26)File: 27. BD-NNV-EC - from - 04.09.2016 to 06.11.2020 (Sy No.26).pdf3 Dec 2020
Conversion Order (Sy. No.26)File: Conversion - Sy No-26.pdf3 Dec 2020
Conversion Order (Sy. No.24 - 1)File: Conversion Order - No.151 - Sy No.24.pdf3 Dec 2020
Conversion Order (Sy. No.24 - 2)File: Conversion Order -30.06.2010 - Sy No.24.pdf3 Dec 2020
Total number of units and Proposed cover under this phase demarcation - Mirza 1File: 2013.07.10 - Allocation Agreement Mirza Akbarull & NHDPL.pdf3 Dec 2020
Total number of units and Proposed cover under this phase demarcation - Mirza 2File: 2013.07.10 - Allocation Agreement Munaf & other and NHDPL.pdf3 Dec 2020
Total number of units and Proposed cover under this phase demarcation - Kailashnath 1File: 2014.02.21 - Agreement - Kailashnath Patil.pdf3 Dec 2020
Total number of units and Proposed cover under this phase demarcation - Kailashnath 2File: 2014.02.21 - Allocation Agreement Kailashnath Patil & NHDPL.pdf3 Dec 2020
Total number of units and Proposed cover under this phase demarcationFile: 2019.02.01 - Addendum Allocation Agreement.pdf3 Dec 2020
JDA between outgoing promoter and landowners 1File: JDA - Kailashnath 2010.pdf3 Dec 2020
JDA between outgoing promoter and landowners 2File: JDA - Mirza - 2010 complete.pdf3 Dec 2020
Business Transfer Agreement between outgoing promoter, incoming promoter and landownersFile: BTA final_compressed.pdf3 Dec 2020
Project head details - TBRPL Certificate of incorporationFile: 4A. True-Blue_COI.pdf3 Dec 2020
CertificateFile: True-Blue_Certificate of Incorporation.pdf-
Project Details-
Certificate form Architect,Engineer,CA etc.File: Napa Physical and Cost Certification - CA Engineer Architects.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Architect Certificate Works As on Date.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Eng Certificate Works pending As on Date.pdf-
CA Certificate for Funds UtilizationFile: CA certificate - fund utilized.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect Certificate Works pending As on Date.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Eng Certificate Works pending As on Date.pdf-
CA Certificate for Funds required for Project CompletionFile: CA certificate - funds required.pdf-
AffidavitFile: Affidavit cum dclaration.pdf-
Latest Encumbrance CertificateFile: ECform.pdf-
Consent letter from 2/3rd of AllotteesFile: Consent Letter from Allotees.pdf-
Details Of Sold/ Un-sold UnitsFile: LIST OF SOLD AND UNSOLD VILLAS.pdf-
Document 1File: LETTER FOR EXTENTION -RERA.pdf-
sanction letter-
a plan-
site plan 14mb-
Napa Valley - Sale Deed-
Napa Valley - Sale Agreement-
sale deed & RTC-
AB plan-
RERA - NNV - Services-
NNV_Specifications-
NNV-EC-
Affidavit-
MOU - TBRPL-
Katha Certificate & Extract - 2013 (Sy No 24 & 26)-
MOU - TBRPL-
title report-
conversion order-
Mutation report-
SD_merged-compressed-
height NA-
AAI-
BESCOM-

How this compares with Bengaluru Urban

97%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 57 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Nitesh Napa Valley on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmNitesh Napa ValleyOther 13Dot size: filed unitsN

Filed coordinates, straight-line distance. 13 registered projects within 2 km.

Builder: True-Blue Realty Private Limited

True-Blue Realty Private Limited has 1 registration on RERA Karnataka, including Nitesh Napa Valley. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Nitesh Napa Valley is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Nitesh Napa Valley?

The registered promoter entity is True-Blue Realty Private Limited, a company as per the filing. Its CIN U45202KA2020PTC132034 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Nitesh Napa Valley?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Nitesh Napa Valley?

The professionals named in the filing: Architect: Design Front Architects; Engineer: Base Engineering Services. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Nitesh Napa Valley?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Nitesh Napa Valley. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Nitesh Napa Valley to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.