Registration approved Residential/Group Housing project

Neeladri Kota Hills

By Neeladri Properties

RG-KA-94099 · RERA PRM/KA/RERA/1251/310/PR/180120/002173

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2018Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 54 documents Report an error

Neeladri Kota Hills is a Residential/Group Housing project by Neeladri Properties in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/180120/002173 on 20 Jan 2018. Possession is promised by 5 Dec 2018.

At a glance

Project

  • NameNeeladri Kota Hills
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/180120/002173
  • ReraGenie IDRG-KA-94099

Builder

  • NameNeeladri Properties
  • Entity typePartnership Firm
  • Authorized SignatoryT.BHDARACHALAM
  • OthersP.Sreelakshmi, M.Madhava Naidu, Pradeep P B, M.Devendra Naidu, V.Niranjan Kumar
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredJan 2018PromisedDec 2018

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on20 Jan 2018
  • Promised completion5 Dec 2018
  • Revised completionNone
  • Buildings1 building record
  • Documents filed54 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK---80080

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing workNot applicable
Retaining wall (All types)Not applicable
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etcNot applicable
Plastering inside , outside & CeilingNot applicable
Joinery: Doors, Windows, Ventilators etcNot applicable
Basic work of Water supply, Sanitary and ElectrificationNot applicable
Dadoing, Skirting, Flooring, Tiles work (All types)Not applicable
Railing and Grill fixingNot applicable
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
PaintingNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,938 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 25.30 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectV.SIVA KUMAR
EngineerSRINIVAS RAO BOLIMUNTA.

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed54

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/180120/002173 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Neeladri GST NO.pdf-
cc-
Plan G F S T Terrece + parking -
Plan G F S T Terrece + parking -
Sale Deed Kota HIlls-
Sale Agreement Draft Kota Hills-
partition Deed 1 -
Plan G F S T Terrece + parking -
Project Area Statement-
allotment Letter PDF-
Broucher of KotaHills -
KSPCB FINA-
Specification PDF-
EC Thurahalli 001-
Katha FINAL -
JD & GPA -
conversion order-
KSPCB FINA-
Plan G F S T -
Plan & Specification-
conversion Final-
Search Report 2 -
Balance Sheet 2016 - 2017File: bs 16-17 PDF.pdf-
Balance Sheet 2015 - 2016File: BS 14-15.pdf-
Balance Sheet 2014 - 2015File: BS 14-15.pdf-
Audited Profit and Loss Statement 2016 - 2017File: P& L 16.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P& L 14-15.pdf-
Audited Profit and Loss Statement 2014 - 2015File: P& L 14-15.pdf-
Director's Report 2016 - 2017File: 2016 001.jpg-
Director's Report 2015 - 2016File: 2015 001.jpg-
Director's Report 2014 - 2015File: 2014 001.jpg-
Cash Flow Statement 2016 - 2017File: Cash Flow Statement.pdf-
Cash Flow Statement 2015 - 2016File: Cash Flow Statement.pdf-
Auditor's Report 2016 - 2017File: Audit report 2016 .pdf-
Auditor's Report 2015 - 2016File: Neeladri 3CB & 3CD (2).pdf-
Auditor's Report 2014 - 2015File: Audit Report 14.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: Acknowledgement 16.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: Acknowledgement.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: acknowledgement receipt 14-15.pdf-
Declaration Form B-
Prospectus/BrochureFile: Broucher of KotaHills .pdf-
Advertisement Copy 1File: Neeladri Kota Hills in Subramanyapura, Bangalore - Price, Reviews & Floor Plan.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_180120_002173 (2).xlsx-
Loan raised documentFile: kotahills loan closing letter.pdf-
Stability CertificateFile: Structural Stability .pdf-
Occupancy CertificateFile: OC .pdf-
Consent for operation issued by KSPCBFile: Neeladri Properties CFO .pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: lift licence.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Bescom Sanction NOC.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: Kotahills BWSSB Deposit Receipt .pdf-
Details of undivided share of land handed over to the association of allotteesFile: UDS Kotahills Reg flats.pdf-
Architect certificate for having completed the work(in format no 5)File: Architect Certificate Completion.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: CA Certificate for completion.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit Declaration kotahills 2 .pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Neeladri Kota Hills on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmNeeladri Kota HillsOther 27Dot size: filed unitsN

Filed coordinates, straight-line distance. 27 registered projects within 2 km.

Builder: Neeladri Properties

Neeladri Properties has 2 registrations on RERA Karnataka, including Neeladri Kota Hills and NEELADRI SAROVARAM. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Neeladri Kota Hills is delayed beyond 5 Dec 2018?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Neeladri Kota Hills?

The registered promoter entity is Neeladri Properties, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Neeladri Kota Hills?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Neeladri Kota Hills?

The professionals named in the filing: Architect: V.SIVA KUMAR; Engineer: SRINIVAS RAO BOLIMUNTA.. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Neeladri Kota Hills?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Neeladri Kota Hills. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Neeladri Kota Hills to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.