Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Mar 2023Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 70 documents Report an error

NCORP SKYWALK LLP is a Residential/Group Housing project by NCORP SKYWALK LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/200121/003211 on 21 Jan 2020. Possession is promised by 30 Mar 2023. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameNCORP SKYWALK LLP
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/200121/003211
  • ReraGenie IDRG-KA-67277

Builder

  • NameNCORP SKYWALK LLP
  • Entity typeOther
  • Authorized SignatoryNAVEEN C K
  • DirectorYOGESH C K

Key dates

this monthRegisteredJan 2020First promiseJun 2022Revised toMar 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 Jan 2020
  • Promised completion30 Mar 2023
  • Revised completionRevised to 30 Mar 2023 (originally 30 Jun 2022)
  • Buildings1 building record
  • Documents filed70 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Skywalk---35035

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 17 Jan 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 17 Jan 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationYes-
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionYes-
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,199 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 25.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANANTHASWAMY
EngineerS S ASSOCIATES

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJun 2022 → Mar 2023

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed70

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/200121/003211 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
AffidavitFile: Affidavit.pdf17 Jan 2020
BBMP PLAN1File: scan16594bw.pdf10 Jan 2020
BBMP PLAN2File: scan16595.pdf10 Jan 2020
BBMP PLAN3File: scan16598.pdf10 Jan 2020
BBMP PLAN4File: scan16599.pdf10 Jan 2020
BBMP PLAN5File: scan16600.pdf10 Jan 2020
BBMP PLAN6File: scan16601.pdf10 Jan 2020
BBMP PLAN7File: scan16602.pdf10 Jan 2020
BBMP PLAN8File: scan16604.pdf10 Jan 2020
BBMP PLAN9File: scan16605.pdf10 Jan 2020
BBMP PLAN10File: scan16607.pdf10 Jan 2020
BBMP PLAN11File: scan16608.pdf10 Jan 2020
BBMP PLAN12File: scan16609.pdf10 Jan 2020
BBMP PLAN13File: scan16610.pdf10 Jan 2020
BBMP PLAN14File: scan16611.pdf10 Jan 2020
BBMP PLAN15File: scan16613.pdf10 Jan 2020
BBMP PLAN16File: scan16614.pdf10 Jan 2020
BBMP PLAN17File: scan16615.pdf10 Jan 2020
BBMP PLAN18File: scan16616.pdf10 Jan 2020
BALANCE SHEETFile: BalancesheetSWPN.pdf10 Jan 2020
AffidavitFile: Affidavit cum declaration.pdf10 Jan 2020
KSPCB NOCFile: Pollution.pdf10 Jan 2020
Income tax return filed ack copy, Balance Sheet and Profit and Loss AccountFile: FY 1819 - ITRV and FINANCIAL STATEMENTS - NCORP SKYWALK.pdf6 Jan 2020
No Objection Certificates - BWSSB, Pollution and BESCOMFile: BWSSB POLUTION BESCOM NOC.pdf6 Jan 2020
NCORP SKYWALK - BASEMENT FLOOR 1File: NCORP SKYWALK - BASEMENT FLOOR 1.pdf6 Jan 2020
NCORP SKYWALK - BASEMENT FLOOR 2File: NCORP SKYWALK - BASEMENT FLOOR 2.pdf6 Jan 2020
NCORP SKYWALK - FIRST FLOORFile: NCORP SKYWALK - FIRST FLOOR.pdf6 Jan 2020
NCORP SKYWALK - SECOND FLOORFile: NCORP SKYWALK - SECOND FLOOR.pdf6 Jan 2020
NCORP SKYWALK - THIRD FLOORFile: NCORP SKYWALK - THIRD FLOOR.pdf6 Jan 2020
NCORP SKYWALK - TERRACEFile: NCORP SKYWALK - TERRACE.pdf6 Jan 2020
Registration Fee of Rs.32000File: 18-10-19 - Rs 32000 - RERA REGN FEES - NCORP SKYWALK.pdf24 Dec 2019
NOC'sFile: BWSSB,POLUTION&BESCOM.pdf24 Dec 2019
Basement Floor Plan 1File: NCORP SKYWALK - BASEMENT FLOOR 1.pdf24 Dec 2019
Basement Floor Plan 2File: NCORP SKYWALK - BASEMENT FLOOR 2.pdf24 Dec 2019
Plan First FloorFile: NCORP SKYWALK - FIRST FLOOR.pdf24 Dec 2019
Plan Second FloorFile: NCORP SKYWALK - SECOND FLOOR.pdf24 Dec 2019
Plan Third FloorFile: NCORP SKYWALK - THIRD FLOOR.pdf24 Dec 2019
Plan TerraceFile: NCORP SKYWALK - TERRACE.pdf24 Dec 2019
Plan License letterFile: BBMP Plan License Letter.pdf24 Dec 2019
Notarized Joint Affidavit cum declarationFile: Affidavit Cum Declaration.pdf24 Dec 2019
Joint development Agreement as Annexure-1 stated in Joint Affidavit cum DeclarationFile: JDA.pdf24 Dec 2019
Sharing Agreement as Annexure-2 stated in Joint Affidavit cum DeclarationFile: Sharing Agreement_Signed.pdf24 Dec 2019
NOTARISED AFFIDAVITFile: 07-12-19 - AFFIDAVIT - NOTARISED.pdf7 Dec 2019
NOTARISED FORM BFile: 07-12-19 - FORM B - NOTARISED.pdf7 Dec 2019
EC COPY FOR UPTO DATEFile: 2004 TO 2019 - EC COPY.pdf7 Dec 2019
KHATHA CERTIFICATEFile: 20-10-18 - Katha Certificate.pdf7 Dec 2019
RERA PAYMENT DETAILSFile: 18-10-19- Rs.32001.8 - RERA - NCORP SKY WALK - REGN FEES.pdf7 Dec 2019
SITE PLANFile: SITE PLAN 1.pdf7 Dec 2019
NOC - BWSSB, POLLUTION CONTROL BOARD & BESCOMFile: BWSSB,POLUTION&BESCOM.pdf7 Dec 2019
CertificateFile: Certificate of LLP Incorporation.PDF-
Floor Plan-
Floor Plan-
SALE DEED - ITTAMADU-
Floor Plan-
Floor Plan-
MORKS_SKYWALK_BROCHURE-
Amenities and Gen Specs- SKYWALK NCORP- R0-
Skywalk_EC_Till17thJuly-
FORM B-
KATHA CERTIFICATE-
JDA-
BBMP Licence-
BWSSBRECEIPT-
Floor Plan-
Amenities and Gen Specs- SKYWALK NCORP- R0-
FORM B-
Prospectus/BrochureFile: Brochure.pdf-
Advertisement Copy 1File: Flyer Skywalk For RERA_0001.pdf-
Advertisement Copy 2File: Flyer Skywalk For RERA_0001.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_200121_003211.xlsx-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep NCORP SKYWALK LLP on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: NCORP SKYWALK LLP

NCORP SKYWALK LLP has 1 registration on RERA Karnataka, including NCORP SKYWALK LLP. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if NCORP SKYWALK LLP is delayed beyond 30 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of NCORP SKYWALK LLP?

The registered promoter entity is NCORP SKYWALK LLP. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in NCORP SKYWALK LLP?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at NCORP SKYWALK LLP?

The professionals named in the filing: Architect: ANANTHASWAMY; Engineer: S S ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NCORP SKYWALK LLP?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NCORP SKYWALK LLP. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NCORP SKYWALK LLP to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.