Home / Browse projects / Bengaluru Urban, Karnataka / NCC URBAN MAYFAIR
NCC URBAN MAYFAIR
By NCC URBAN INFRASTRUCTURE LTD
RG-KA-35556 · RERA PRM/KA/RERA/1251/309/PR/180627/001926
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
NCC URBAN MAYFAIR is a Residential/Group Housing project by NCC URBAN INFRASTRUCTURE LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/180627/001926 on 27 Jun 2018. Possession is promised by 31 May 2022. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NameNCC URBAN MAYFAIR
- TypeResidential/Group Housing
- Location
- Bengaluru North
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/309/PR/180627/001926
- ReraGenie IDRG-KA-35556
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on27 Jun 2018
- Promised completion31 May 2022
- Revised completionRevised to 31 May 2022 (originally 31 Aug 2021)
- Buildings5 building records
- Documents filed59 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | - | - | - | 62 | 0 | 62 |
| B | - | - | - | 71 | 0 | 71 |
| C | - | - | - | 70 | 0 | 70 |
| D | - | - | - | 120 | 0 | 120 |
| E | - | - | - | 36 | 0 | 36 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | JAMUNA CHALAM |
| Engineer | K VENKATESH BABU REDDY |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed59
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/180627/001926 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Companny Reg certificate.pdf | - |
| Plan Sanction order -BBMP-1 | - |
| approved plan-2nd time | - |
| Sheet 01 of 06 | - |
| Draft Sale Deed - Blank _corrections_ | - |
| AGREEMENT TO SELL - RERA | - |
| Draft Sale Deed - Blank _corrections_ | - |
| approved plan-2nd time | - |
| Final | - |
| Mayfair Booking form | - |
| brouchure | - |
| Proposed Specifications for Mktg | - |
| EC | - |
| BBMP Khatha | - |
| Meadows-III JDA | - |
| 2 Acres Sale Deed - NCC Urban | - |
| Conversion Order | - |
| BBMP relinquishment deed | - |
| KSPCB NOC | - |
| NOC-Airport and BSNL | - |
| BESCOM NOC | - |
| KSPCB NOC | - |
| BWSSB Letter-Page-1 | - |
| NOC-Airport and BSNL | - |
| Final | - |
| Sheet 06 of 06 | - |
| Sheet 01 of 06 | - |
| Conversion Order | - |
| Balance Sheet 2016 - 2017File: Balance Sheet-16.pdf | - |
| Balance Sheet 2015 - 2016File: Balance Sheet-16.pdf | - |
| Balance Sheet 2014 - 2015File: Balance Sheet.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: Audit Report-16.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: Balance Sheet-16.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: Audiot Report-15.pdf | - |
| Director's Report 2016 - 2017File: director's report-16.pdf | - |
| Director's Report 2015 - 2016File: director's report-16.pdf | - |
| Director's Report 2014 - 2015File: DIR Rep 2015.pdf | - |
| Cash Flow Statement 2016 - 2017File: Cash Flow-16.pdf | - |
| Cash Flow Statement 2015 - 2016File: Cash Flow-16 N.pdf | - |
| Auditor's Report 2016 - 2017File: Audit Report.pdf | - |
| Auditor's Report 2015 - 2016File: Audit Report-16.pdf | - |
| Auditor's Report 2014 - 2015File: Audiot Report-15.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ACK 2015-16WP.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ACK 2015-16WP.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: 14-15 ACK.pdf | - |
| form B | - |
| Prospectus/BrochureFile: Mayfair_Brochure-min..pdf | - |
| Advertisement Copy 1File: ADD - Mayfair_Halfpage_J1.jpg | - |
| Tower Excel SheetFile: Floor Wise Details.xlsx | - |
| Loan raised documentFile: 005051325 Loan details.pdf | - |
| Stability CertificateFile: Stability Certificate Mayfair.pdf | - |
| NOC issued by the Fire Force department after completion of workFile: Fire CC.pdf | - |
| Occupancy CertificateFile: Occupation certificate.pdf | - |
| Consent for operation issued by KSPCBFile: KSPCB CFO.pdf | - |
| Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Lift operation approval.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Power sanction.jpeg | - |
| Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: BWSSB Water connection.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: Form 05 Architect Certificate.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep NCC URBAN MAYFAIR on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: NCC URBAN INFRASTRUCTURE LTD
NCC URBAN INFRASTRUCTURE LTD has 3 registrations on RERA Karnataka, including NCC URBAN GREEN PROVINCE and NCC URBAN MISTY WOODS. Its filings declare 5 earlier projects, 5 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if NCC URBAN MAYFAIR is delayed beyond 31 May 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of NCC URBAN MAYFAIR?
The registered promoter entity is NCC URBAN INFRASTRUCTURE LTD, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in NCC URBAN MAYFAIR?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at NCC URBAN MAYFAIR?
The professionals named in the filing: Architect: JAMUNA CHALAM; Engineer: K VENKATESH BABU REDDY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in NCC URBAN MAYFAIR?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback