ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / NAVKAR CITY

Registration lapsed No litigation declared Residential / Group Housing project

NAVKAR CITY

By NAVKAR DEVELOPERS

RG-MH-12241 · RERA P99000009015 · Last updated on MahaRERA portal: 2 Mar 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 58 months past the filed date
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2021Possession promised58 months past this date
10 of 66Construction stages doneacross 6 buildings; furthest along: Staircases, 80%
65 of 90Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 26 documents Report an error

NAVKAR CITY is a Residential / Group Housing project by NAVKAR DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000009015 on 19 Aug 2017. Possession was promised by 30 Dec 2021 and is now 58 months past that date. The completion date has moved by 24 months from the original filing. 25 of the 90 units on this registration are recorded sold or booked, and 10 of 66 construction stages are filed complete.

At a glance

Project

  • NameNAVKAR CITY
  • TypeResidential / Group Housing
  • Location
    • road
    • Malyan
    • Dahanu (M Cl)
    • Dahanu
    • Palghar
    • 401602
  • Pincode401602
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000009015
  • ReraGenie IDRG-MH-12241

Builder

  • NameNAVKAR DEVELOPERS
  • Entity typePartnership
  • PartnersSANJAY MANSHUKHLAL BAPHNA, NIRMAL KALYANMAL MEHTA, CHANDRAKANT HIRJI CHHEDA, HARESH NAGJI VORA, DILESH CHUNILAL CHHEDA, BIPIN LAXMICHAND DEDHIA, VIPUL RATILAL BAPHNA
  • Other registrations10 more →
  • Completed3 of 11
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

58 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toDec 2021

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on19 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings6 building records
  • Documents filed26 files

Current status

28%25 of 90 units booked

Figures as on 2 Mar 2023, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GIRNARNA5346046
PAVAPURINA5340040
ROW HOUSE C1NA22101
ROW HOUSE C2NA22101
ROW HOUSE C3NA22101
ROW HOUSE C4NA22101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 2 Mar 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Staircases, at 80%.

GIRNAR53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
PAVAPURI61%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE C10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE C20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE C30%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE C40%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 2 Mar 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes15%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed30

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots30
Closed/Covered30
BuildingClosed/CoveredTotal
GIRNAR1717
PAVAPURI1313

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area6,738 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 Jul 2025

Approvals and building plan

Sanctioning authorityDahanu Nagarparishad
Permissible FSI6692.14
Proposed, not sanctioned6,692 sq m
Buildings approved6
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMATRU ASHISH, IRANI ROAD, DAHANU ROAD 401602

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNISHANT PRABHAKAR PATIL
ArchitectVastushilp Assocaites
EngineerYOGESH VAJA
EngineerDarsh Consult
Chartered AccountantMavani Santoki & Co.
Chartered AccountantKakaria and Associates LLP
PartnerRole in project
NAVKAR DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000005343Dec 2019 → Dec 2020

Reason as filed by the promoterPROJECT IS ALMOST COMPLETE AND PROMOTER IS COMMITTED TO COMPLETE THE PROJECT AND OBTAIN THE COMPLETION FROM THE COMPETENT AUTHORITY

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed26

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf2 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Navkar Developers.pdf26 Mar 2022
Certificates of CA (Form 5)File: Form-05.pdf30 Jan 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form-05.pdf30 Jan 2021
Certificates of CA (Form 5)File: Form 5.pdf19 Oct 2019
Certificates of CA (Form 5)File: Navkar-FORM 5.PDF13 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certi-ilovepdf-compressed.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Girnar Structure Cert-ilovepdf-compressed.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Pawapuri Structure Cert-ilovepdf-compressed.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Structure Row House.pdf29 Jul 2017
Certificates of CA (Form 3)File: Certificate RERA1.pdf29 Jul 2017
Proforma of Allotment letterFile: Agreement for sale draft final.pdf27 Jul 2017
Building plan approvalFile: Final for upload.pdf23 Jul 2017
Building plan approvalFile: Final for Upload.pdf23 Jul 2017
Layout approvalFile: Plot B Layout-ilovepdf-compressed.pdf23 Jul 2017
Layout approvalFile: Layout plan-ilovepdf-compressed.pdf23 Jul 2017
PAN CardFile: ND Pan.pdf23 Jul 2017
Copy of the legal title reportFile: SERCH REPORT CUM TITLE CERTIFICATE-ilovepdf-compressed-ilovepdf-compressed.pdf23 Jul 2017
Details of encumbrancesFile: SERCH REPORT CUM TITLE CERTIFICATE-ilovepdf-compressed-ilovepdf-compressed.pdf23 Jul 2017
Copy of Layout Approval (in case of layout)File: Plot B Layout-ilovepdf-compressed.pdf23 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout plan-ilovepdf-compressed.pdf23 Jul 2017
Building Plan Approval (IOD)File: Final for upload.pdf23 Jul 2017
Building Plan Approval (IOD)File: Final for Upload.pdf23 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Navkar City CC-ilovepdf-compressed.pdf23 Jul 2017
Declaration in FORM BFile: STAMP PAPER FORM B.pdf23 Jul 2017
Proforma of Allotment letterFile: NAVKAR ALLOTMENT LETTER.pdf23 Jul 2017

How this compares with Palghar

28%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 24 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NAVKAR CITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Malyan3,200+ in Palghar

2 kmNAVKAR CITYCompleted 2Lapsed / revoked 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: NAVKAR DEVELOPERS

Navkar developers has 11 registrations on MahaRERA, including Tulsi Centre Point and NAVKAR CITY. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that NAVKAR CITY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if NAVKAR CITY is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NAVKAR CITY?

The registered promoter entity is NAVKAR DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NAVKAR CITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NAVKAR CITY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NAVKAR CITY?

The professionals named in the filing: Architect: NISHANT PRABHAKAR PATIL; Architect: Vastushilp Assocaites; Engineer: YOGESH VAJA; Engineer: Darsh Consult; Chartered Accountant: Mavani Santoki & Co.; Chartered Accountant: Kakaria and Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NAVKAR CITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NAVKAR CITY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NAVKAR CITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.