Navami Funique
RG-KA-26204 · RERA PRM/KA/RERA/1251/310/PR/171102/001532 · Last updated on RERA Karnataka portal: 20 May 2022
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 21 months
- 2 extensions taken
Clear
- No complaints on record
- Separate project account declared
Saved.
Navami Funique is a Mixed Development project by Navami Funique in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/171102/001532 on 2 Nov 2017. Possession is promised by 30 Dec 2022. The completion date has moved by 21 months from the original filing.
At a glance
Project
- NameNavami Funique
- TypeMixed Development
- Location
- Bengaluru South
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/310/PR/171102/001532
- ReraGenie IDRG-KA-26204
Builder
- NameNavami Funique
- Entity typePartnership Firm
- Authorized SignatoryDasappa Raghu
- OthersDasappa Raghu, Suman Raghu.M.A
- Declared earlier projects5 →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on2 Nov 2017
- Promised completion30 Dec 2022
- Revised completionRevised to 30 Dec 2022 (originally 31 Mar 2021)
- Buildings5 building records
- Documents filed103 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TOWER ONE | - | - | - | 40 | 0 | 40 |
| TOWER TWO | - | - | - | 40 | 0 | 40 |
| TOWER THREE | - | - | - | 40 | 0 | 40 |
| TOWER FOUR | - | - | - | 40 | 0 | 40 |
| COMMERCIAL TOWER | - | - | - | 0 | 0 | 0 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 20 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | Not applicable |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 20 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | - |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | Yes | - |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DESIGN FORUM INTERNATIONAL |
| Engineer | MANOHAR CONSULTANTS |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterothers
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed103
As listed on the registration, under the names the promoter filed them with; the newest 80 of 103 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/171102/001532 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| LETTER FOR CHAIRMANFile: Letter for Chairman.pdf | 20 May 2022 |
| AFFIDAVIT UPLOADED THE SAMEFile: Affidavit for Extension-Revised.pdf | 20 May 2022 |
| FORM B AFFIDAVITFile: Form B Affidavit.pdf | 20 May 2022 |
| AOSFile: Agreement of sale.pdf | 20 May 2022 |
| BESCOM SANCTION LETTER COPYFile: Bescom Sanction copy.pdf | 20 May 2022 |
| COMPLETION CERT OF FIRE NOCFile: Comple Certi for FIRE NOC.pdf | 20 May 2022 |
| APPLICATION LETTER FOR OC APPLIEDFile: Applcation Letter for OC Applied.pdf | 20 May 2022 |
| BBMP ENDORSEMENT COPYFile: BBMP Endorsement Copy.pdf | 20 May 2022 |
| CONSENT OPERATION CERTIFICATEFile: Consent Operation Certifcate.pdf | 20 May 2022 |
| DECLARATION LETTERFile: Declartion Letter.pdf | 20 May 2022 |
| PARTIAL OCCUPANCY CERTFile: Partial Occupancy Certificate.pdf | 20 May 2022 |
| Affidavit for Extension-RevisedFile: Affidavit for Extension-Revised.pdf | 16 Apr 2022 |
| CFO (KSPCB)- Navami FuniqueFile: CFO (KSPCB)- Navami Funique.pdf | 16 Apr 2022 |
| Commencement CertificateFile: Commencement Certificate (1).pdf | 16 Apr 2022 |
| Latitude & LongitudeFile: Latitude & Longitude.pdf | 16 Apr 2022 |
| NOC Declaration LetterFile: NOC Declaration Letter.pdf | 16 Apr 2022 |
| PRO SPECIFICATIONFile: PRO SPECIFICATION.pdf | 16 Apr 2022 |
| AOS AFFIDAVITFile: AOS AFFIDAVIT.pdf | 16 Apr 2022 |
| Sold Allotees & Unsold DetailsFile: Sold Allotees & Unsold Details.pdf | 16 Apr 2022 |
| Stability of structureFile: Stability of structure.pdf | 16 Apr 2022 |
| Tower wise Unit & BHK DetailsFile: Tower wise Unit & BHK Details.pdf | 16 Apr 2022 |
| Arc Cert Pending Work as on DateFile: Arc Cert Pending Work as on Date.pdf | 16 Apr 2022 |
| Arc Cert Status Work as on DateFile: Arc Cert Status Work as on Date.pdf | 16 Apr 2022 |
| CertificateFile: Funique - Partnership Deed.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: Arc Cert Pending Work as on Date.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Engg Cert Work as on Date.pdf | - |
| CA Certificate for Funds UtilizationFile: CA Cert Fund Utilization.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Arc Cert Pending Work as on Date.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Engg Cert Pending Work as on Date.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: CA Cert Fund Required.pdf | - |
| AffidavitFile: Extenstion Affidavit Navami Funique.pdf | - |
| Latest Encumbrance CertificateFile: EC 01 12 2020 to 13 02 2022.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: 12 SoldUnsoldDetails.pdf | - |
| Document 1File: 28 Funique - BWSSB NOC.pdf | - |
| Document 2File: 25 Funique - Fire Force NOC.pdf | - |
| Document 3File: 26 Funique - Airport NOC.pdf | - |
| Document 4File: 27 Funique - BESCOM NOC.pdf | - |
| Document 5File: 30 Funique - SEIAAK NOC.pdf | - |
| Document 6File: 31 Funique - BSNL NOC.pdf | - |
| Document 7File: Reason for Dealy.pdf | - |
| Document 8File: 1 EC 2004 TO 2018.pdf | - |
| Document 9File: 2 EC 02 2018 TO 05 2018.pdf | - |
| Document 10File: 3 EC 01 04 2018 TO 31 07 2018.pdf | - |
| Document 11File: 4 EC 08 2018 TO 03 2019.pdf | - |
| Document 12File: 5 EC 03 2019 TO 09 2019.pdf | - |
| Document 13File: 6 EC 04 09 2019 TO 08 03 2020.pdf | - |
| Document 14File: 7 EC 09 08 2019 TO 02 06 2020.pdf | - |
| Document 15File: 8 EC 01 04 2018 TO 15 10 2020.pdf | - |
| Document 16File: 9 EC 01 04 2020 TO 01 12 2020.pdf | - |
| Document 17File: 10 EC 01 12 2020 to 19 03 2021.pdf | - |
| Document 18File: 11 EC 01 12 2020 to 13 02 2022.pdf | - |
| Document 19File: RERA Bank RERA AC.pdf | - |
| 05 Funique - BBMP Licence Sanction Copy Approval of Plan | - |
| 06 Funique - Plan Sanction Drawings or Design Copy 1 | - |
| 15 Funique - Proforma of Sale Deed | - |
| 08 Funique - Proform of Agreement | - |
| 09 Funique - Sale Deed Part | - |
| 08 Funique - Proform of Agreement | - |
| 12 Funique - Brochure | - |
| Funique - Partnership Deed | - |
| 13 Funique - Speci and amenities of Project | - |
| 03 Funique - Encumbrance Certificate | - |
| 16 Funique - Katha | - |
| 17 Funique - JDA | - |
| 18 Funique - Sale Deed Part 3 | - |
| 20 Funique - Conversion Certificate | - |
| 24 Funique - Relinquishment Deed | - |
| 24 Funique - Fire Force NOC | - |
| 25 Funique - Airport NOC | - |
| 26 Funique - BESCOM NOC | - |
| 27 Funique - BWSSB NOC | - |
| 28 Funique - KSPCB Pollution NOC | - |
| 29 Funique - SEIAAK NOC | - |
| 30 Funique - BSNL NOC | - |
| Unnamed document | - |
| Balance Sheet 2015 - 2016File: 01 - BS 16-17.pdf | - |
| Balance Sheet 2014 - 2015File: 01 - BS 15-16.pdf | - |
| Balance Sheet 2013 - 2014File: 01 - BS 14-15.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: 02 - PL 16-17.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: 02 - PL 15-16.pdf | - |
Promoter's earlier projects5
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| NAVAMI VARSHA COMPLEX | - | Completed | - | No date filed |
| NAVAMI VARSHA | - | Completed | - | No date filed |
| NAVAMI SYMPHONY | - | Completed | - | No date filed |
| NAVAMI NAKSHATRA | - | Completed | - | No date filed |
| MN ORCHID | - | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Navami Funique on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Navami Funique
Navami Funique has 1 registration on RERA Karnataka, including Navami Funique. Its filings declare 5 earlier projects, 5 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Navami Funique is delayed beyond 30 Dec 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Navami Funique?
The registered promoter entity is Navami Funique, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Navami Funique?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Navami Funique?
The professionals named in the filing: Architect: DESIGN FORUM INTERNATIONAL; Engineer: MANOHAR CONSULTANTS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Navami Funique?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.