ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / NAKSHA HYDEPARK

Registration approved Residential/Group Housing project

NAKSHA HYDEPARK

By NAKSHA PROJECT PVT LTD

RG-KA-60360 · RERA PRM/KA/RERA/1251/310/PR/171214/001461

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka
  • Completion date moved by 11 months
  • 1 extension taken

Clear

  • Separate project account declared
May 2019Possession promisedmoved 11 months from the original
1Complaints at RERA Karnatakaon this registration
Jump to the 44 documents Report an error

NAKSHA HYDEPARK is a Residential/Group Housing project by NAKSHA PROJECT PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/171214/001461 on 14 Dec 2017. Possession is promised by 30 May 2019. The completion date has moved by 11 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameNAKSHA HYDEPARK
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/171214/001461
  • ReraGenie IDRG-KA-60360

Builder

  • NameNAKSHA PROJECT PVT LTD
  • Entity typeCompany
  • CINU45201KA2011PTC058520
  • Authorized SignatoryRAVICHANDRAN K

Key dates

this monthRegisteredDec 2017First promiseJun 2018Revised toMay 2019

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on14 Dec 2017
  • Promised completion30 May 2019
  • Revised completionRevised to 30 May 2019 (originally 1 Jun 2018)
  • Buildings1 building record
  • Documents filed44 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NA---60060

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes-
Swimming PoolNoNot applicable
GymYes-
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,311 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 13.41 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM/s Secant architects LLP
EngineerBhadya Enginering Services Pvt Ltd.

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/310/PR/190719/001461Jun 2018 → May 2019

Reason as filed by the promoterCustomers want modification in interiors

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
CMP/210419/0007909-NAKSHA PROJECT PVT LTD19/04/2021

Documents filed44

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/171214/001461 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: certificate.pdf-
Architect Certificate for Work Completion Schedule till DateFile: ARC2 Work Completion.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Eng1 work Completion.pdf-
CA Certificate for Funds UtilizationFile: CA Certificate_utilisation-.pdf-
Architect Certificate for Pending Work Completion Schedule.File: ARC1 Pending Works.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Eng2 pending works.pdf-
CA Certificate for Funds required for Project CompletionFile: Certificate_1 funds required.pdf-
AffidavitFile: RERA Affidavit Cum Declaration.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Commencement c-
Temp00340-
Temp00340-
SD-HYDEPARK DRAFT-
HYDE-PARK SALE- AGREEMENT-
RTC-
Temp00338-
Temp00338-
HYDEPARK_Flat_booking_form-
Naksha-HydePark-Ver5 Lite (1)-
Hydepark Conversion-
Specification deed-
Hydepark EC-
hydepark Katha & Extract-
New Doc 2017-08-23-ilovepdf-compressed-
Balance Sheet 2015 - 2016File: Balance sheet 1516.pdf-
Balance Sheet 2014 - 2015File: BS FY1415-min.pdf-
Balance Sheet 2013 - 2014File: Balance Sheet13-14.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P&L 1516.pdf-
Audited Profit and Loss Statement 2014 - 2015File: P & L Fy 1415.pdf-
Audited Profit and Loss Statement 2013 - 2014File: P & L ac13-14.pdf-
Director's Report 2015 - 2016File: Directors Report1516.pdf-
Director's Report 2014 - 2015File: Directors Report1415.pdf-
Director's Report 2013 - 2014File: Directors Report1314.pdf-
Cash Flow Statement 2015 - 2016File: Cash Flow.pdf-
Cash Flow Statement 2014 - 2015File: Cash Flow.pdf-
Auditor's Report 2015 - 2016File: Audit Report fy1516 (2).pdf-
Auditor's Report 2014 - 2015File: Audit Report FY 1415.pdf-
Auditor's Report 2013 - 2014File: audit report13-14.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR ACK Fy1516.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR ACK FY 1415.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: ITR ACK13-14.pdf-
affidavit-
Prospectus/BrochureFile: Naksha-HydePark-Ver3 Lite.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_171214_001461 (1) (1).xlsx-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 11 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep NAKSHA HYDEPARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: NAKSHA PROJECT PVT LTD

NAKSHA PROJECT PVT LTD has 1 registration on RERA Karnataka, including NAKSHA HYDEPARK. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if NAKSHA HYDEPARK is delayed beyond 30 May 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of NAKSHA HYDEPARK?

The registered promoter entity is NAKSHA PROJECT PVT LTD, a company as per the filing. Its CIN U45201KA2011PTC058520 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in NAKSHA HYDEPARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against NAKSHA HYDEPARK?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at NAKSHA HYDEPARK?

The professionals named in the filing: Architect: M/s Secant architects LLP; Engineer: Bhadya Enginering Services Pvt Ltd.. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NAKSHA HYDEPARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NAKSHA HYDEPARK. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NAKSHA HYDEPARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.