Home / Browse projects / Bengaluru Urban, Karnataka / MYTHRI STREET

Registration approved No litigation declared Residential/Group Housing project

MYTHRI STREET

By MYTHRI BUILDERS

RG-KA-04051 · RERA PRM/KA/RERA/1251/446/PR/151025/008172 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2029Possession promisedno revision filed
5 of 18Construction stages donefurthest along: RCC or MS Framed structure, 15%
126 of 219Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 162 documents Report an error

MYTHRI STREET is a Residential/Group Housing project by MYTHRI BUILDERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/151025/008172 on 15 Oct 2025. Possession is promised by 30 Dec 2029. 93 of the 219 units on this registration are recorded sold or booked, and 5 of 18 construction stages are filed complete.

At a glance

Project

  • NameMYTHRI STREET
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/151025/008172
  • ReraGenie IDRG-KA-04051

Builder

  • NameMYTHRI BUILDERS
  • Entity typePartnership Firm
  • GSTIN29ABMFM5690D7ZO
  • Authorized SignatoryAINAMPUDI KIRAN KUMAR
  • Other registrations6 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredOct 2025PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Oct 2025
  • Promised completion30 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed162 files

Current status

42%93 of 219 units booked
4.1%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MYTHRI STREET---2190219

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 18 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 15%.

Building: 29% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure15%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes2%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallNoNot applicable
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners4
LandownerVillageDistrict
M/s MYTHRI BUILDERS--
M/s MYTHRI BUILDERS--
M/s MYTHRI BUILDERS--
M/s MYTHRI BUILDERS--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 143.54 cr
Cost incurredRs 5.89 cr
Spent of the estimate4.1%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 135.99 crRs 5.30 cr
Administrative CostRs 5.13 crRs 16.09 lakh
On-site expenditure-Consultants FeesRs 2.14 crRs 4.79 lakh
Payment of taxesRs 28.50 lakhRs 8.07 lakh
On-site expenditure-Site Overhead-Rs 5.40 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectB V Narendranath Reddy
EngineerMADAMANCHI SURENDRA NADH
Chartered AccountantRamesh Babu Lankipalli

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed162

As listed on the registration, under the names the promoter filed them with; the newest 80 of 162 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/151025/008172 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Street_Rera Form 4_Q2.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Street_Form-5_Arch.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6-Sep-2026 Eng.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Q2 2026-27 Airport Authority of India14 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Sankalp_Form-4_Q1.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Sankalp_Form-5_Arch_Q1.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Sankalp_Form-6_Eng_Q1.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q1 2026-27 Fire and Safety14 Jul 2026
Q1 2026-27 Airport Authority of India14 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Mythri Street_RERA Form 4_Q4 2025-26.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: FORM 5.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6-Mar-2026.pdf14 Apr 2026
Q4 2025-26 Water supply and sewage board14 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)14 Apr 2026
Q4 2025-26 KPTCL- BESCOM14 Apr 2026
Q4 2025-26 Fire and Safety14 Apr 2026
Q4 2025-26 Airport Authority of India14 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: dsv (3).jpeg4 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Street_Architect_Form-5_Q3.pdf4 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Street_Engineer_Form-6_Q3.pdf4 Feb 2026
Q3 2025-26 Water supply and sewage board4 Feb 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)4 Feb 2026
Q3 2025-26 KPTCL- BESCOM4 Feb 2026
Q3 2025-26 Fire and Safety4 Feb 2026
Q3 2025-26 Airport Authority of India4 Feb 2026
Q3 2025-26 BSNL/Telecommunication Department4 Feb 2026
STPFile: STP.pdf14 Oct 2025
STPFile: STP.pdf14 Oct 2025
Land Cost calculation sheetFile: Land Cost Calculation Sheet.pdf9 Oct 2025
stpFile: STP_GROUND FLOOR.pdf9 Oct 2025
stpFile: STP_Upper Basement.pdf9 Oct 2025
Reply to NoticeFile: reply to notice.pdf9 Oct 2025
Guidance value certificateFile: Guidence value certificate.pdf9 Oct 2025
RTC, survey 67/3-
Mutation, survey 67/3-
Encumbrance Certificate, survey 67/3-
Conversion/Alienation Order, survey 67/3-
Sale/Title/Gift Deed, survey 67/3-
Khatha, survey 67/3-
RTC, survey 67/11-
Mutation, survey 67/11-
Encumbrance Certificate, survey 67/11-
Conversion/Alienation Order, survey 67/11-
Sale/Title/Gift Deed, survey 67/11-
Khatha, survey 67/11-
RTC, survey 67/12-
Mutation, survey 67/12-
Encumbrance Certificate, survey 67/12-
Conversion/Alienation Order, survey 67/12-
Sale/Title/Gift Deed, survey 67/12-
Khatha, survey 67/12-
RTC, survey 67/13-
Mutation, survey 67/13-
Encumbrance Certificate, survey 67/13-
Conversion/Alienation Order, survey 67/13-
Sale/Title/Gift Deed, survey 67/13-
Khatha, survey 67/13-
Registration CertificateFile: FORM C.pdf-
Partnership DeedFile: PARTNERSHIP DEED.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Mythri Street Form Reg 1.pdf-
Certificate issued by Architect Form 2File: Form 2 Acrhitect Certi.pdf-
Certificate issued by Engineer Form 3File: Form-6.pdf-
Project Chartered Accountant-

How this compares with Bengaluru Urban

42%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep MYTHRI STREET on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: MYTHRI BUILDERS

MYTHRI BUILDERS has 7 registrations on RERA Karnataka, including MYTHRI SQUARE and MYTHRI SANKALP DKM. Its filings declare 4 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if MYTHRI STREET is delayed beyond 30 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of MYTHRI STREET?

The registered promoter entity is MYTHRI BUILDERS, a partnership firm as per the filing. Its GSTIN 29ABMFM5690D7ZO can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in MYTHRI STREET?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at MYTHRI STREET?

The professionals named in the filing: Architect: B V Narendranath Reddy; Engineer: MADAMANCHI SURENDRA NADH; Chartered Accountant: Ramesh Babu Lankipalli. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MYTHRI STREET?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MYTHRI STREET. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MYTHRI STREET to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.