ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / MYTHRI SIKHARAM

Registration approved No litigation declared Residential/Group Housing project

MYTHRI SIKHARAM

By MYTHRI BUILDERS

RG-KA-57279 · RERA PRM/KA/RERA/1251/446/PR/280525/007790 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Mar 2029Possession promisedno revision filed
1 of 18Construction stages donefurthest along: Earth work and other leveling..., 78%
74 of 182Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 175 documents Report an error

MYTHRI SIKHARAM is a Residential/Group Housing project by MYTHRI BUILDERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/280525/007790 on 28 May 2025. Possession is promised by 31 Mar 2029. 108 of the 182 units on this registration are recorded sold or booked, and 1 of 18 construction stages are filed complete.

At a glance

Project

  • NameMYTHRI SIKHARAM
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/280525/007790
  • ReraGenie IDRG-KA-57279

Builder

  • NameMYTHRI BUILDERS
  • Entity typePartnership Firm
  • GSTIN29ABMFM5690D5ZQ
  • Authorized SignatoryS.ANIL KUMAR REDDY
  • Other registrations6 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredMay 2025PromisedMar 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on28 May 2025
  • Promised completion31 Mar 2029
  • Revised completionNone
  • Buildings2 building records
  • Documents filed175 files

Current status

59%108 of 182 units booked
6.1%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MYTHRI SIKHARAM TOWER A---84084
MYTHRI SIKHARAM TOWER B---98098

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 18 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 78%.

Building: 26% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work78%
Foundation footing work78%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)60%
Retaining wall (All types)65%
RCC or MS Framed structure38%
Masonry Construction28%
Plastering inside , outside & Ceiling10%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing10%
Electrification, Water supply and Sanitary Finishing3%
Painting5%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes30%
LiftsYes30%
Corridor/LobbiesYes35%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes70%
TerraceYes0%
Outer WallYes50%
Open parking areasYes30%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership15

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners15
LandownerVillageDistrict
MYTHRI BUILDERS--
MYTHRI BUILDERS--
Nitesh kumar Hruthik--
Chandramma--
Nitesh kumar Hruthik--
Chandramma--
AINAMPUDI KIRANKUMAR--
S.ANIL KUMAR REDDY--
T.KISHORE BABU--
AINAMPUDI KIRANKUMAR--
S.ANIL KUMAR REDDY--
T.KISHORE BABU--
AINAMPUDI KIRANKUMAR--
S.ANIL KUMAR REDDY--
T.KISHORE BABU--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 111.82 cr
Cost incurredRs 6.86 cr
Spent of the estimate6.13%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 106.92 crRs 5.55 cr
Administrative CostRs 3.20 crRs 25.38 lakh
Architect, Engineer, Consultant FeesRs 1.50 crRs 4.68 lakh
Payment of taxesRs 20.00 lakhRs 48.97 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGnanavel Thirumaran
EngineerAmbrish G
Chartered AccountantRamesh Babu Lankipalli

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed175

As listed on the registration, under the names the promoter filed them with; the newest 80 of 175 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/280525/007790 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Mythri Sikharam_Rera Form 4_Q2 FY 26-27 (2).pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Mythri sikharam-Form-5 rera cer-Q2-26-27.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Mythri sikharam-Form-6 rera cer-Q2-26-27.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Q2 2026-27 Airport Authority of India14 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Mythri Sikharam_Form-4.pdf13 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: mythri rera certficate-sikaram- Form-5.pdf13 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: RERA Engineer Certificate Form-6.pdf13 Jul 2026
Q1 2026-27 Water supply and sewage board13 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)13 Jul 2026
Q1 2026-27 KPTCL- BESCOM13 Jul 2026
Q1 2026-27 Fire and Safety13 Jul 2026
Q1 2026-27 Airport Authority of India13 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department13 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Mythri Sikharam_RERA From 4 Q4 2025-26.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: SIKHARAM_Architect_Form_5_Q4.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: RERA SIKHARAM form 6.pdf14 Apr 2026
Q4 2025-26 Water supply and sewage board14 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)14 Apr 2026
Q4 2025-26 KPTCL- BESCOM14 Apr 2026
Q4 2025-26 Fire and Safety14 Apr 2026
Q4 2025-26 Airport Authority of India14 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Mythri Sikharam RERA Form-4 Q3.pdf26 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: SIKHARAM_Architect_Form_5_Q3.pdf26 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: SIKHARAM_Engineer_Form 6_Q3.pdf26 Jan 2026
Q3 2025-26 Water supply and sewage board26 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)26 Jan 2026
Q3 2025-26 KPTCL- BESCOM26 Jan 2026
Q3 2025-26 Fire and Safety26 Jan 2026
Q3 2025-26 Airport Authority of India26 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department26 Jan 2026
Section 3-1 AffidavitFile: Section 3(1) Affidavit with notary.pdf23 May 2025
structural safety certificate by EngFile: Certificate for structural safety of building by Eng.pdf23 May 2025
Bank Affidavit with NotaryFile: Bank Affidavit.pdf23 May 2025
Sale - operation clarification affidavitFile: Sale-Operation clarification Affidavit.pdf23 May 2025
declaration for Sale - operationFile: Declaration for Sale - Operation letter.pdf23 May 2025
source of fund detailsFile: Source of Funds.pdf23 May 2025
BS 2021-22File: BS 2021-22.pdf23 May 2025
BS 2022-23File: BS -2022-23.pdf23 May 2025
BS 2023-24File: BS -2023-24.pdf23 May 2025
PL 2021-22File: PL -2021-22.pdf23 May 2025
PL 2022-23File: PL-2022-23.pdf23 May 2025
PL 2023-24File: PL-2023-24.pdf23 May 2025
Bank Account DetailsFile: Mythri Sikharam Bank Details.pdf23 May 2025
EC 48-10File: EC 48-10.pdf23 May 2025
EC Khaneshumari No 39File: EC Khaneshumari No-39.pdf23 May 2025
EC Khaneshumari No 230-35-36-37File: EC Khaneshumari No-230 - 35 - 36 - and 37.pdf23 May 2025
EC Khaneshumari No 233-AFile: EC Khaneshumari No-233-A.pdf23 May 2025
EC Sy No 48-4File: EC sy no 48-4.pdf23 May 2025
EC Sy No 48-9File: EC sy no 48-9.pdf23 May 2025
EC Sy No 48-10File: EC Sy No 48-10.pdf23 May 2025
EC Sy No 48-8File: EC_48-8.pdf23 May 2025
Form -B Affidavit with notaryFile: Form-B with notary.pdf23 May 2025
JD Affidavit with NotaryFile: JOINT AFFIDAVIT CUM DECLARATION with notary.pdf23 May 2025
MR All sy no with all pagesFile: MR All Sy No.pdf23 May 2025
Non litigation affidavi with notaryFile: Non litigation Affidavit with notary.pdf23 May 2025
RTC Sy No 48-1File: RTC Sy No 48-1.pdf23 May 2025
RTC Sy No 48-8File: RTC Sy No 48-8.pdf23 May 2025
RTC 48-9File: RTC Sy No 48-9.pdf23 May 2025
RTC sy no 48-10File: RTC Sy No 48-10.pdf23 May 2025
Section 3(1) affidavit with notaryFile: Section 3(1) Affidavit with notary.pdf23 May 2025
Clarification of MR and RTC Khaneshumari Nos by AdvocateFile: Clarification of MR and RTC.pdf23 May 2025
EC Khaneshumari No 230-35-36-37 from 2010 to till dateFile: EC Khaneshumari No 230-035-36 and 37 from 2010 to till date.pdf23 May 2025
RTC, survey 48-4-
Mutation, survey 48-4-
Encumbrance Certificate, survey 48-4-
Conversion/Alienation Order, survey 48-4-
Sale/Title/Gift Deed, survey 48-4-
Khatha, survey 48-4-
RTC, survey 48-8-
Mutation, survey 48-8-
Encumbrance Certificate, survey 48-8-
Conversion/Alienation Order, survey 48-8-
Sale/Title/Gift Deed, survey 48-8-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationStatusPromisedDelivered
MYTHRI SANKALP DKMSurvey 59/5, 59/6, and 59/7 , Halehalli Village, Bidarahalli Hobli, Bangalore East Taluk , Bengaluru EastOngoingDec 2027Not due yet

How this compares with Bengaluru Urban

59%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep MYTHRI SIKHARAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: MYTHRI BUILDERS

MYTHRI BUILDERS has 7 registrations on RERA Karnataka, including MYTHRI SQUARE and MYTHRI SANKALP DKM. Its filings declare 4 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if MYTHRI SIKHARAM is delayed beyond 31 Mar 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of MYTHRI SIKHARAM?

The registered promoter entity is MYTHRI BUILDERS, a partnership firm as per the filing. Its GSTIN 29ABMFM5690D5ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in MYTHRI SIKHARAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at MYTHRI SIKHARAM?

The professionals named in the filing: Architect: Gnanavel Thirumaran; Engineer: Ambrish G; Chartered Accountant: Ramesh Babu Lankipalli. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MYTHRI SIKHARAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MYTHRI SIKHARAM. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MYTHRI SIKHARAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.