Mukul Palms

By Faizunnisa Farooque Sayed

RG-MH-48895 · RERA P51700013500 · Last updated on MahaRERA portal: 13 Aug 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 58 months past the filed date
  • Litigation declared, 1 case
  • 12 complaints at MahaRERA

Clear

  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2021Possession promised58 months past this date
22 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 24%
12Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

Mukul Palms is a Residential / Group Housing project by Faizunnisa Farooque Sayed in Thane, Maharashtra, registered with MahaRERA as P51700013500 on 9 Oct 2017. Possession was promised by 30 Dec 2021 and is now 58 months past that date. 12 complaints are on record with the regulator.

At a glance

Project

  • NameMukul Palms
  • TypeResidential / Group Housing
  • Location
    • Kamlakar Nagar
    • Khoj Gaon
    • Ambarnath (R)
    • Ambarnath
    • Thane
    • 421505
  • Pincode421505
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700013500
  • ReraGenie IDRG-MH-48895

Builder

  • NameFaizunnisa Farooque Sayed
  • Entity typeIndividual

Key dates

58 months past promisethis monthRegisteredOct 2017PromisedDec 2021

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Oct 2017
  • Promised completion30 Dec 2021
  • Revised completionNone
  • Buildings3 building records
  • Documents filed73 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CoralNA270000
EmeraldNA170000
SapphireNA280000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 13 Aug 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 24%.

Coral84%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure24%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Emerald39%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure13%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Sapphire84%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure24%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 13 Aug 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes20%
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes10%
Landscaping & Tree PlantingYes10%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes20%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes20%

Parking filed468

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots468
Closed/Covered82
Open Space386
BuildingClosed/CoveredOpen SpaceTotal
Coral206585
Emerald44256300
Sapphire186583

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area20,506 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Jamiyat co-op Housing Society LtdAmbarnath (R)Thane

Approvals and building plan

Permissible FSI1695.0
Proposed, not sanctioned1,695 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAxis Bank Ambernath East Dist Thane Maharashtra

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSatish Dattatray Ook
EngineerAtul Vijay Kudtarkar
Chartered AccountantRR Anekar & Co
PartnerRole in project
Faizunnisa Farooque Sayed-

Litigation declared1

CaseCourtStatus
56/2015KalyanInjunction Operative Next date Six August Two Thousand Eighteen

Complaints filed with MahaRERA12

Case no.ComplainantRespondentFiled
CC006000000054622Jamiyat Co-op. Housing Society through chairman Mohd. Arif AnsariFaizunnisa N sayed15/06/2018
CC006000000120939Kirthi KumarAminMukul Developers16/09/2019
CC006000000198173Mrs. Varsha Vijay MandaveSmt. Fazunnisan Sayyad14/10/2021
CC006000000198612Sheena RajanM/s. Mukul Developers14/10/2021
CC006000000198613Ashish TabhaneM/s. Mukul Developers14/10/2021
CC006000000198616Wasiullah AnsariM/s. Mukul Developers14/10/2021
CC006000000198618Mrs. Bharati Venkatesh NaiduM/s. Mukul Developers14/10/2021
CC006000000198623Dr. Natwar Brahmdev DwivediM/s. Mukul Developers14/10/2021
CC006000000198624Dr. Natwar Bramhdev DwivediM/s. Mukul Developers14/10/2021
CC006000000220849Faizunnisa Farooque SayedKirthi Kumar Amin17/04/2022
CC006000000395963Jamiyat Co-operative Housing Society LimitedM/s Mukul Developers through its Proprietor Mrs Faizunnisa M Sayyad02/06/2023
CC006000000591537Mukul Palms Emeral Allottiees Welfare AssociationM/s Mukul Developers14/08/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Sep 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Sep 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Sep 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Sep 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 14 Nov 2019

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: FORM 3- JAN 18 - DEC 21_compressed.pdf13 Aug 2024
Certificates of CA (Form 3)File: FORM 3- JAN 22 TO MAR 22_compressed.pdf13 Aug 2024
Certificates of CA (Form 3)File: FORM 3- APRIL 22 TO JUNE 22_compressed.pdf13 Aug 2024
Certificates of CA (Form 3)File: FORM 3- JULY 22 TO SEPT 22_compressed.pdf13 Aug 2024
Certificates of CA (Form 3)File: FORM 3- OCT 22 TO DEC 22_compressed.pdf13 Aug 2024
Certificates of CA (Form 3)File: FORM 3- JAN 23 TO MAR 23_compressed.pdf13 Aug 2024
Certificates of CA (Form 3)File: FORM 3- APRIL 23 TO JUNE 23_compressed.pdf13 Aug 2024
Certificates of CA (Form 3)File: FORM 3- JULY 23 TO SEPT 23_compressed.pdf13 Aug 2024
Certificates of CA (Form 3)File: FORM 3- OCT 23 TO DEC 23_compressed.pdf13 Aug 2024
Certificates of CA (Form 3)File: FORM 3- JAN 24 TO MAR 24_compressed.pdf13 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 - APRIL 17 TO MAR 18.pdf13 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5- APRL 18 TO MAR 19.pdf13 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 - APRIL 19 TO MAR 20.pdf13 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5- APRIL 20 TO MAR 21.pdf13 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5- APRIL 21 TO MAR 22.pdf13 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM -5 APRIL 22 TO MAR 23.pdf13 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1- JAN 18 TO DEC 21.pdf31 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1-1ST JAN 22 TO 31ST MAR 22.pdf31 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1- 1ST APRIL 22 TO 30TH JUNE 22.pdf31 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1- 1ST JULY 22 TO 30TH SEPT 22.pdf31 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1- 1ST OCT 22 TO 31ST DEC 22.pdf31 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1- 1ST JAN 23 TO 31ST MAR 23.pdf31 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1- 1ST APRIL 23 TO 30TH JUNE 23.pdf31 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - 1ST JULY 23 TO 30TH SEPT 23.pdf31 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1ST OCT 23 TO 31 ST DEC 23.pdf31 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 JAN 24 TO MAR 24.pdf31 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 JAN 18- DEC 21.pdf31 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - OCT 21 TO DEC 21.pdf31 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 JAN 22- MAR 22.pdf31 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 APRIL 22 - JUNE 22.pdf31 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 JULY 22- SEPT 22.pdf31 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 OCT 22 - DEC 22.pdf31 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 JAN 23- MAR 23.pdf31 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 APRIL 23 - JUNE 23.pdf31 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 JULY 23- SEPT 23.pdf31 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 OCT 23- DEC 23.pdf31 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 JAN 24 - MAR 24.pdf31 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FY 19-20.pdf31 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FY 20-21.pdf31 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FY 21-22.pdf31 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FY 22-23.pdf31 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FY 23-24.pdf31 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FY 23-24.pdf31 Jul 2024
Disclosure of sold/ booked inventoryFile: SOLD INVENTORY .pdf31 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Disclosure of interest in other real estate organizations.pdf31 Jul 2024
Details of encumbrances concerned to FinanceFile: Encumbrance related to Legal.pdf27 Jul 2024
Details of encumbrances concerned to LegalFile: Encumbrance related to Legal.pdf27 Jul 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMATE A.pdf27 Jul 2024
Deviation Report with respect to Allotment letterFile: Deviation Report Allotment letter.pdf27 Jul 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report AFS.pdf27 Jul 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Coral OC-1.pdf14 Nov 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Sapphire OC-1.pdf14 Nov 2019
OtherFile: completion certificate.pdf28 Apr 2018
OtherFile: fire noc of Coral.pdf28 Apr 2018
OtherFile: drainage certificate_.pdf28 Apr 2018
OtherFile: Sapphire Fire NOC.pdf24 Apr 2018
OtherFile: Stability certificate_2016.pdf24 Apr 2018
OtherFile: Lift Licence_sapphire.pdf24 Apr 2018
OtherFile: Lift Licence of coral.pdf24 Apr 2018
OtherFile: STABILITY CERTIFICATE_ CORAL.pdf24 Apr 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf19 Sep 2017
Copy of the legal title reportFile: Title _certificate1.pdf16 Sep 2017
Building plan approvalFile: 2015_Master.pdf15 Sep 2017
Layout approvalFile: 2015_Master.pdf15 Sep 2017
PAN CardFile: IMG.pdf15 Sep 2017
Details of encumbrancesFile: Encumbrances -.pdf15 Sep 2017
Copy of Layout Approval (in case of layout)File: 2015_Master.pdf15 Sep 2017
Building Plan Approval (IOD)File: 2015_Master.pdf15 Sep 2017
Commencement Certificates / NA Order for plotted developmentFile: CC_Doc.pdf15 Sep 2017
Declaration in FORM BFile: Form_B.pdf15 Sep 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf15 Sep 2017
Certificates of CA (Form 3)File: Form 3.pdf15 Sep 2017
Proforma of Allotment letterFile: Sale_agreement.pdf15 Sep 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mukul Palms on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Khoj Gaon7,600+ in Thane

2 kmMukul PalmsCompleted 27Lapsed / revoked 9Other 29Dot size: filed unitsN

Filed coordinates, straight-line distance. 65 registered projects within 2 km.

Builder: Faizunnisa Farooque Sayed

Faizunnisa Farooque Sayed has 1 registration on MahaRERA, including Mukul Palms. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Mukul Palms shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Mukul Palms is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mukul Palms?

The registered promoter entity is Faizunnisa Farooque Sayed, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mukul Palms?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Mukul Palms?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Mukul Palms?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mukul Palms?

The professionals named in the filing: Architect: Satish Dattatray Ook; Engineer: Atul Vijay Kudtarkar; Chartered Accountant: RR Anekar & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mukul Palms?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mukul Palms. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mukul Palms to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.