MSR CROWN IMPERIALS

By MSR DEVELOPERS

RG-KA-54225 · RERA PRM/KA/RERA/1251/446/PR/180420/001522

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Oct 2020Possession promisedmoved 12 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 78 documents Report an error

MSR CROWN IMPERIALS is a Residential/Group Housing project by MSR DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/180420/001522 on 20 Apr 2018. Possession is promised by 9 Oct 2020. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameMSR CROWN IMPERIALS
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/180420/001522
  • ReraGenie IDRG-KA-54225

Builder

  • NameMSR DEVELOPERS
  • Entity typePartnership Firm
  • Authorized SignatoryM SRIMANNARAYAN REDDY
  • Board MembersR Anji Reddy, R Nagarjuna Reddy, Mandadi Yadava Reddy, R SUDHAKARA REDDY, Musku Naresh Kumar Reddy, A KRISHNA REDDY, P Thirumal Reddy, M MANOHARA

Key dates

this monthRegisteredApr 2018First promiseOct 2019Revised toOct 2020

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on20 Apr 2018
  • Promised completion9 Oct 2020
  • Revised completionRevised to 9 Oct 2020 (originally 9 Oct 2019)
  • Buildings2 building records
  • Documents filed78 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---60060
B---60060

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & CeilingNot applicable
Joinery: Doors, Windows, Ventilators etcNot applicable
Basic work of Water supply, Sanitary and ElectrificationNot applicable
Dadoing, Skirting, Flooring, Tiles work (All types)Not applicable
Railing and Grill fixingNot applicable
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
PaintingNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,000 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 25.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectN GANESH
EngineerPB SRINIVAS

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionOct 2019 → Jul 2021

No reason recorded in the filing

EX/PRM/KA/RERA/1251/446/PR/200526/001522Jul 2021 → Oct 2020

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed78

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/180420/001522 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: MSR Developers Partnership Firm.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Arc status of wok.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engg status of work Completed Certificate.pdf-
CA Certificate for Funds UtilizationFile: Ca funds utilization certificate-min.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Arc pending work letter.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engg pending of work.pdf-
CA Certificate for Funds required for Project CompletionFile: Ca funds required -min.pdf-
AffidavitFile: Affidavit for extension of project registration.pdf-
Latest Encumbrance CertificateFile: Latest Ec Min.pdf-
Details Of Sold/ Un-sold UnitsFile: Sold & unsold flats.pdf-
Document 1File: Bank Statement_compressed.pdf-
Document 2File: Rera Extension Affidavit_compressed.pdf-
Document 3File: Commencement Certificate.pdf-
Document 4File: 54324258_1578892171472.pdf-
Document 5File: Rera Extension Affidavit.pdf-
Document 7File: A-207 Consent Letter - 10-Feb-2020 - 10-40 am.pdf-
Document 8File: A-208 Consent Letter - 10-Feb-2020 - 10-38 am.pdf-
Document 9File: A-302 Consent Letter - 10-Feb-2020 - 10-41 am.pdf-
Document 10File: A-406 Consent letter - 10-Feb-2020 - 10-39 am.pdf-
Document 11File: B-201 Consent Letter - 10-Feb-2020 - 10-43 am.pdf-
Document 12File: B-205 Consent letter - 10-Feb-2020 - 10-39 am.pdf-
Document 13File: B-209 Consent letter - 10-Feb-2020 - 10-42 am.pdf-
Document 14File: B-212 Consent letter - 10-Feb-2020 - 10-37 am.pdf-
Document 15File: B-309 Consent letter - 10-Feb-2020 - 10-44 am.pdf-
Document 16File: B-409 Consent letter - 10-Feb-2020 - 10-42 am.pdf-
Document 17File: Sec 18(I) Affidavit.pdf-
New Project Launching-
21-2 & 21-3 Plan 3-
21-2 & 21-3 Plan 2-
MSR KURUDUSONNEHALALI SALE DEED DRAFT 21-3 21-2-
KURUSUSONNENAHALLI AGREEMENT Draft-
Sale Deed & RTC-
BDA Plan Licence-
21-2 & 21-3 Plan 1-
allotment_letter-
Brochure Crown Imperials-min-
SPECIFICATION-
EC-
21-3 Conversion Order-ilovepdf-compressed-
JDA & GPA-
Village Map-
Survey Sketch-
21-3 Conversion Order-ilovepdf-compressed-
Balance Sheet 2016 - 2017File: MSR Developers Balance Sheet 2016-17.pdf-
Balance Sheet 2015 - 2016File: MSR Dev Balance Sheet 2015-16.pdf-
Balance Sheet 2014 - 2015File: MSR Dev Balance Sheet 14-15.pdf-
Audited Profit and Loss Statement 2016 - 2017File: MSR Developers Profit & Loss 2016-17.pdf-
Audited Profit and Loss Statement 2015 - 2016File: MSR Dev Profit & Loss 2015-16.pdf-
Audited Profit and Loss Statement 2014 - 2015File: MSR Dev Profit & Loss 14-15.pdf-
Director's Report 2016 - 2017File: MSR Developers Director 2016-17.pdf-
Director's Report 2015 - 2016File: MSR Dev Capital 2015-16.pdf-
Director's Report 2014 - 2015File: MSR Dev Capital 14-15.pdf-
Cash Flow Statement 2016 - 2017File: MSR Developers Cash Flow 2016-17.pdf-
Cash Flow Statement 2015 - 2016File: MSR Deve Cash Flow 2015-16.pdf-
Auditor's Report 2016 - 2017File: MSR Developers ITR 2016-17 (2).pdf-
Auditor's Report 2015 - 2016File: MSR DEVELOPERS ITR 2015-16.pdf-
Auditor's Report 2014 - 2015File: MSR DEVELOPERS ITR 2014-15.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: MSR Developers ITR 2016-17.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: MSR Dev ITR 2015-16.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: MSR Dev ITR Aknolgement 14-15.pdf-
Form B3-
Prospectus/BrochureFile: Brochure Crown Imperials-min.pdf-
Advertisement Copy 1File: Brochure Crown Imperials-min.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_446_PR_180420_001522.xlsx-
Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: Road & Water Permission Letter of 21-2 & 3.pdf-
NOC issued by the Fire Force department after completion of workFile: msr developers PCB_compressed.pdf-
Occupancy CertificateFile: oc copy.pdf-
Consent for operation issued by KSPCBFile: msr developers PCB_compressed.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Lift Electrical Approval.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Lift Electrical Approval.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: Road & Water Permission Letter of 21-2 & 3.pdf-
Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: STP Work order - 29-Mar-2026 - 12-08 pm.pdf-
Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: Doc - 29-Mar-2026 - 11-59 am.pdf-
Details of undivided share of land handed over to the association of allotteesFile: Doc - 29-Mar-2026 - 11-59 am.pdf-
Architect certificate for having completed the work(in format no 5)File: Architect Certificate.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: Form -4 CA.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit.pdf-
we are attaching the oc certificate and affidavit for the project completion kindly do the needful.File: oc copy_Affidavit_merged_compressed.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep MSR CROWN IMPERIALS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmMSR CROWN IMPERIALSOther 51Dot size: filed unitsN

Filed coordinates, straight-line distance. 51 registered projects within 2 km.

Builder: MSR DEVELOPERS

MSR DEVELOPERS has 1 registration on RERA Karnataka, including MSR CROWN IMPERIALS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if MSR CROWN IMPERIALS is delayed beyond 9 Oct 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of MSR CROWN IMPERIALS?

The registered promoter entity is MSR DEVELOPERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in MSR CROWN IMPERIALS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at MSR CROWN IMPERIALS?

The professionals named in the filing: Architect: N GANESH; Engineer: PB SRINIVAS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MSR CROWN IMPERIALS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MSR CROWN IMPERIALS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MSR CROWN IMPERIALS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.