Home / Browse projects / Bengaluru Urban, Karnataka / MRG BLISS
MRG BLISS
By MR GROUP
RG-KA-11704 · RERA PRM/KA/RERA/1251/310/PR/210913/004303 · Last updated on RERA Karnataka portal: 18 Dec 2024
Source: official RERA Karnataka filing
Red flags
- 1 complaint at RERA Karnataka
- Completion date moved by 8 months
- 1 extension taken
Clear
- Separate project account declared
Saved.
MRG BLISS is a Residential/Group Housing project by MR GROUP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/210913/004303 on 13 Sep 2021. Possession is promised by 30 Nov 2024. The completion date has moved by 8 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameMRG BLISS
- TypeResidential/Group Housing
- Location
- Bengaluru South
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/310/PR/210913/004303
- ReraGenie IDRG-KA-11704
Builder
- NameMR GROUP
- Entity typePartnership Firm
- Authorized SignatoryA LAKSHMINARAYANA NAIDU
- DirectorM VENKATESHULU
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on13 Sep 2021
- Promised completion30 Nov 2024
- Revised completionRevised to 30 Nov 2024 (originally 31 Mar 2024)
- Buildings8 building records
- Documents filed101 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | - | - | - | 25 | 0 | 25 |
| WING B | - | - | - | 35 | 0 | 35 |
| WING - C | - | - | - | 20 | 0 | 20 |
| WING - D | - | - | - | 20 | 0 | 20 |
| WING - E | - | - | - | 23 | 0 | 23 |
| WING - F | - | - | - | 25 | 0 | 25 |
| WING - G | - | - | - | 25 | 0 | 25 |
| WING - H | - | - | - | 25 | 0 | 25 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 18 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 18 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | No | Not applicable |
| Emergency Evacuation services | Yes | - |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| M R GROUP | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | YUKTHI ARCHITECTS |
| Engineer | YUKTHI CONSULTANTS |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterShortage of Labour
Complaints filed with RERA Karnataka1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| 01461/2025 | - | MR GROUP | 08/12/2025 |
Documents filed101
As listed on the registration, under the names the promoter filed them with; the newest 80 of 101 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/210913/004303 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect certificates Form Ex-1File: Form - Ex1 Architect Certificate.pdf | 18 Dec 2024 |
| Architect certificates Form Ex-2File: Form - Ex2 Architect Certificate.pdf | 18 Dec 2024 |
| Commencement certificateFile: MRG Bliss Commencement Certificate.pdf | 18 Dec 2024 |
| Bank Guarantee for BWSSB FeeFile: Bank Gurantee for BWSSB NOC.pdf | 4 Sep 2021 |
| Affidavit for BWSSB FeeFile: Affidavit for - BWSSB Fee.pdf | 4 Sep 2021 |
| Honourable High Court, Karnataka Order copyFile: BWSSB - STAY ORDER FROM HONARABLEHIGH COURT.pdf | 4 Sep 2021 |
| BWSSB Demand Notice copyFile: BWSSB - DEMAND NOTICE FOR NOC.pdf | 4 Sep 2021 |
| AFFIDAVITFile: AFFIDAVIT.pdf | 24 Aug 2021 |
| BESCOM NOCFile: BESCOM NOC.pdf | 24 Aug 2021 |
| BWSSB NOCFile: BWSSB NOC.pdf | 24 Aug 2021 |
| KSPCB NOCFile: KSPCB NOC.pdf | 24 Aug 2021 |
| RERA Bank Account as per RERA DirectionsFile: M R GROUP MRG BLISS RERA ACCOUNT.pdf | 16 Aug 2021 |
| Form B with Notarized and with Project Completion dateFile: FORM B - RERA.pdf | 16 Aug 2021 |
| Total Area Of Land is matching with Total Open Area and Total Covered Area detailsFile: Land Area details of MRG BLISS.pdf | 16 Aug 2021 |
| Clarification letter regarding water supply NOC without signatureFile: Clarification letter for BWSSB NOC without signature and supporting documents.pdf | 16 Aug 2021 |
| AS PER RERA BANK ACCOUNT OPEN APPLICATION SUBMITTED AND UPLOADED ACKNOWLEDGEMEMNTFile: M R GROUP.pdf | 1 Jul 2021 |
| AS PER RERA FORMAT FORM B SIGNED NOTARIZED AND ATTACHEDFile: Signedform-B.pdf | 1 Jul 2021 |
| BWSSB WILL BE OBTAINEDFile: BWSSB COMPLIANCE.pdf | 1 Jul 2021 |
| MR BLISS EC-01-04-2004 to 19-07-2017 Page1File: MREC01-4-2004to19-07-20171.jpg | 9 Jun 2021 |
| MR BLISS EC-01-04-2004 to 19-07-2017 Page2File: MREC01-4-2004to19-07-20172.jpg | 9 Jun 2021 |
| MR BLISS EC-01-04-2017 to 19-07-2017 Page1File: MRGroupECfrom 01-04-2017totilldate.pdf | 9 Jun 2021 |
| Form B Signed and notarized copyFile: Signedform-B.pdf | 9 Jun 2021 |
| MR GROUP SELF ATTESTED PAN COPYFile: 1 Pan - M R Group attested.pdf | 20 Apr 2021 |
| Project Land EC from 01-04-2017 to till dateFile: 2.MR Group EC from 01-04-2017 to till date.pdf | 20 Apr 2021 |
| Signed and Notarized Form-B ( as per RERA Act)File: 3.signed form B.pdf | 20 Apr 2021 |
| MRG BLISS PROJECT SITE EC UPTO DATEFile: EC MR GROUP.pdf | 7 Apr 2021 |
| MRG BLISS PROJECT BWSSB UNDERTAKINGFile: BWSSB COMPLIANCE.pdf | 7 Apr 2021 |
| CertificateFile: CERTIFICATE OF REGISTRATION OF FIRM MR GROUP.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: Form - Ex1 Architect Certificate.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Form - Ex5 Engineers Certificate.pdf | - |
| CA Certificate for Funds UtilizationFile: Form - Ex3 Chartered Accountant Certificate.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Form - Ex2 Architect Certificate.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Form - Ex6 Engineers Certificate.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: Form - Ex4 Chartered Accountant Certificate.pdf | - |
| AffidavitFile: Form B Affidavit.pdf | - |
| Latest Encumbrance CertificateFile: EC Copy.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx | - |
| cc_BBMP_11689_CH_20-21 | - |
| BBMP PLAN | - |
| BBMP PLAN | - |
| Sale deed -Format | - |
| Sale Agreement format | - |
| SALE DEED - M R GROUP | - |
| BBMP PLAN | - |
| BBMP PLAN | - |
| Sale Agreement format | - |
| BBMP PLAN | - |
| PROJECT SPECIFICATIONS | - |
| EC 2004 | - |
| SALE DEED - M R GROUP | - |
| SALE DEED - M R GROUP | - |
| Khatha | - |
| SALE DEED - M R GROUP | - |
| SALE DEED - M R GROUP | - |
| CONVERSION | - |
| MRG NA | - |
| MRG NA | - |
| MRG NA | - |
| MRG NA | - |
| MRG NA | - |
| MRG NA | - |
| MRG NA | - |
| MRG NA | - |
| KSPCB - Paid | - |
| MRGROUPSEIAA | - |
| MRG NA | - |
| MRG NA | - |
| Unnamed document | - |
| MRG NA | - |
| MRG NA | - |
| MRG NA | - |
| MRG NA | - |
| MRG NA | - |
| MRG NA | - |
| PROJECT SPECIFICATIONS | - |
| BBMP PLAN | - |
| BBMP PLAN | - |
| BBMP PLAN | - |
| CONVERSION | - |
| MR LEGAL SEARCH REPORT | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep MRG BLISS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: MR GROUP
MR GROUP has 1 registration on RERA Karnataka, including MRG BLISS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if MRG BLISS is delayed beyond 30 Nov 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of MRG BLISS?
The registered promoter entity is MR GROUP, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in MRG BLISS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against MRG BLISS?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at MRG BLISS?
The professionals named in the filing: Architect: YUKTHI ARCHITECTS; Engineer: YUKTHI CONSULTANTS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MRG BLISS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.