Home / Browse projects / Pune, Maharashtra / Mont Vert Kingstown Sector 1 Residential Wings

Registration lapsed No litigation declared Residential / Group Housing project

Mont Vert Kingstown Sector 1 Residential Wings

By Niraj Kumar Associates Pvt Ltd

RG-MH-16582 · RERA P52100026366 · Last updated on MahaRERA portal: 30 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • 4 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
8 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 90%
145 of 316Units unsoldnot recorded sold or booked
4Complaints at MahaRERAon this registration
Jump to the 169 documents Report an error

Mont Vert Kingstown Sector 1 Residential Wings is a Residential / Group Housing project by Niraj Kumar Associates Pvt Ltd in Pune, Maharashtra, registered with MahaRERA as P52100026366 on 11 Sep 2020. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 12 months from the original filing. 171 of the 316 units on this registration are recorded sold or booked, and 8 of 22 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • NameMont Vert Kingstown Sector 1 Residential Wings
  • TypeResidential / Group Housing
  • Location
    • S No 265 p and 268 P
    • Bhugaon
    • Mulshi
    • Pune
    • 411023
  • Pincode411023
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100026366
  • ReraGenie IDRG-MH-16582

Builder

  • NameNiraj Kumar Associates Pvt Ltd
  • Entity typeCompany
  • CINU45209MH1995PTC094283
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Managing DirectorJayant Vallabhdas Kaneria
  • Other registrations6 more →
  • Completed5 of 7
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

4 months past promisethis monthRegisteredSep 2020First promiseJun 2025Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on11 Sep 2020
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2025)
  • Buildings2 building records
  • Documents filed169 files

Current status

54%171 of 316 units booked
65.1%Work done, per cost certificate

Figures as on 30 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Residential Wing ANA20161580158
Residential Wing BNA20161580158

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 30 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 90%.

Residential Wing A60%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)90%
Plinth100%
Stilt Floor100%
Slabs of Super Structure88%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises45%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Residential Wing B63%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)90%
Plinth100%
Stilt Floor100%
Slabs of Super Structure88%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises77%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed60

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots60
Closed/Covered2
Open Space58
BuildingClosed/CoveredOpen SpaceTotal
Residential Wing A12930
Residential Wing B12930

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,870 sq m
Land owned byThe promoter
Named landownersNone
Declared on12 Jun 2025

Approvals and building plan

Sanctioning authorityPMRDA
Permissible FSI25369.06
Proposed, not sanctioned24,286 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAundh, Pune
Estimated costRs 63.86 cr
Cost incurredRs 41.57 cr
Work done65.09%
BuildingWingEstimatedIncurred
Residential Wing ANARs 28.42 crRs 19.90 cr
Residential Wing BNARs 28.42 crRs 21.32 cr
-NARs 7.01 crRs 35.06 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTEAMWORK-Architects & Planners
EngineerNarendra Chaudhary
EngineerSachin Thangat
Chartered AccountantRMR Shah and Co R Shah
Chartered AccountantAmit Satish Shingvi
Chartered AccountantPriyanka Chordiya & Associates
PartnerRole in project
Niraj Kumar Associates Pvt Ltd-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA19062501681Jun 2025 → Jun 2026

Reason as filed by the promoter1. Excavation took at least 6 months more due to unexpectedly hard rock strata. 2. Revision of plan took 1 months more than expected 3. Plinth checking took 16 months more than expected due to non-clarity of applicability of additional development charges (metro Cess) for ongoing projects. 4. We had to let go of a non-performing RCC contractor and hire a new contractor adding to 3 months of transition delays.

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC12503794Niraj Kumar Associates Pvt LtdMangala Shyamrao Patil30/10/2025
CC12503796Niraj Kumar Associates Pvt LtdSiddarth Vijay Aru30/10/2025
CC12503793Niraj Kumar Associates Pvt LtdSumeet Pradeep Nikhare30/10/2025
CC12603884Siddharth Vijay AruNiraj Kumar Associates Pvt Ltd23/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Sep 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Jul 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Mar 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed169

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 169 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 Kingstown Residential June 2026.pdf30 Jul 2026
Withdrawal Update Form 2File: FORM 2 Kingstown Residential June 2026.pdf30 Jul 2026
Withdrawal Update Form 3File: FORM 3 Kingstown Residential Resi March 2026.pdf30 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A MahaRERA 2025 2026 Kingstown Resi.pdf11 May 2026
Withdrawal Update Form 1File: Form 1 KINGSTOWN Resi March 2026 .pdf6 May 2026
Withdrawal Update Form 2File: FORM 2 KINGSTOWN Resi March 2026.pdf6 May 2026
Withdrawal Update Form 3File: FORM 3 Kingstown Residential Resi March 2026.pdf6 May 2026
Withdrawal Update Form 1File: Form 1 Mont Vert Kingstown Resi dec 2025.pdf24 Jan 2026
Withdrawal Update Form 1File: Form 1 Mont Vert Kingstown Resi dec 2025.pdf24 Jan 2026
Withdrawal Update Form 2File: Form 2 Kingstown Resi Dec 2025.pdf24 Jan 2026
Withdrawal Update Form 2File: Form 2 Kingstown Resi Dec 2025.pdf24 Jan 2026
Withdrawal Update Form 3File: Form 3 Kingstown Resi Sept 2025.pdf24 Jan 2026
Withdrawal Update Form 3File: Form 3 Kingstown Resi Sept 2025.pdf24 Jan 2026
Withdrawal Update Form 1File: FORM 1 KINGSTOWN RESI JUNE 25 signed.pdf17 Oct 2025
Withdrawal Update Form 1File: Form 1 Rera Kingstown Resi Sept 2025.pdf17 Oct 2025
Withdrawal Update Form 1File: Form 1 Rera Kingstown Resi Sept 2025.pdf17 Oct 2025
Withdrawal Update Form 2File: FORM-2 KINGSTOWN RESI June 2025.pdf17 Oct 2025
Withdrawal Update Form 2File: FORM-2 KINGSTOWN RESI June 2025.pdf17 Oct 2025
Withdrawal Update Form 2File: FORM-2 KINGSTOWN RESI June 2025.pdf17 Oct 2025
Withdrawal Update Form 3File: Form 3 June 2025 Kingstown Residential Sign.pdf17 Oct 2025
Withdrawal Update Form 3File: Form 3 June 2025 Kingstown Residential Sign.pdf17 Oct 2025
Withdrawal Update Form 3File: Form 3 Kingstown Resi Sept 2025.pdf17 Oct 2025
Building plan approvalFile: Kingstown CC for MahaRERA 2025.pdf23 Jul 2025
Building plan approvalFile: R Binder1 1.pdf22 Jul 2025
Building plan approvalFile: R Binder1 2.pdf22 Jul 2025
Building plan approvalFile: R Binder1 3.pdf22 Jul 2025
Building plan approvalFile: R Binder1 4.pdf22 Jul 2025
Building plan approvalFile: R Binder1 5.pdf22 Jul 2025
Building plan approvalFile: R Binder1 6.pdf22 Jul 2025
Building plan approvalFile: R Binder1 7.pdf22 Jul 2025
Building plan approvalFile: R Binder1 8.pdf22 Jul 2025
Building plan approvalFile: R Binder1 9.pdf22 Jul 2025
Building plan approvalFile: R Binder1 10.pdf22 Jul 2025
Building plan approvalFile: R Binder1 11.pdf22 Jul 2025
Building plan approvalFile: R Binder1 12.pdf22 Jul 2025
Building plan approvalFile: R Binder1 13.pdf22 Jul 2025
Building plan approvalFile: R Binder1 14.pdf22 Jul 2025
Building plan approvalFile: R Binder1 15.pdf22 Jul 2025
Building plan approvalFile: R Binder1 16.pdf22 Jul 2025
Building plan approvalFile: R Binder1 17.pdf22 Jul 2025
Building plan approvalFile: R Binder1 18.pdf22 Jul 2025
Building plan approvalFile: R Binder1 19.pdf22 Jul 2025
Building plan approvalFile: HPSC0213.pdf11 Jul 2025
Building plan approvalFile: HPSC0214.pdf11 Jul 2025
Building plan approvalFile: HPSC0215.pdf11 Jul 2025
Building plan approvalFile: HPSC0216.pdf11 Jul 2025
Building plan approvalFile: HPSC0217.pdf11 Jul 2025
Building plan approvalFile: HPSC0218.pdf11 Jul 2025
Building plan approvalFile: HPSC0219.pdf11 Jul 2025
Building plan approvalFile: HPSC0220.pdf11 Jul 2025
Building plan approvalFile: HPSC0221.pdf11 Jul 2025
Building plan approvalFile: HPSC0222.pdf11 Jul 2025
Building plan approvalFile: HPSC0223.pdf11 Jul 2025
Building plan approvalFile: HPSC0224.pdf11 Jul 2025
Building plan approvalFile: HPSC0225.pdf11 Jul 2025
Building plan approvalFile: HPSC0226.pdf11 Jul 2025
Building plan approvalFile: HPSC0227.pdf11 Jul 2025
Building plan approvalFile: HPSC0228.pdf11 Jul 2025
Building plan approvalFile: HPSC0229.pdf11 Jul 2025
Building plan approvalFile: HPSC0230.pdf11 Jul 2025
Building plan approvalFile: HPSC0231.pdf11 Jul 2025
Form 5 (FY 2024-2025)File: Form 5 Kingstown Resi 2024 2025.pdf30 Jun 2025
Form 2A (FY 2024-2025)File: Form 2A singed 2024 2025 Kingstown Resi.pdf26 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Kingstown Residential March 2025.pdf11 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 NKAPL KINGSTOWN R MARCH 2025 (1).pdf11 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 KINGSTOWN RESI MARCH 2025.pdf11 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold and Unsold Mont Vert Kingstown March 2025.pdf11 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD KINGSTOWN RESIDEN DEC 2024.pdf9 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Mont Vert Kingstown Sector 1 Residential Wings Dec 2024.pdf8 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA RESIDENTIAL.pdf6 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Kingstown Resi Dec 2024.pdf4 Jan 2025
Details of encumbrances concerned to FinanceFile: RERA No legal pendency Bhugaon Kingstown.pdf13 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Kingstown Resident Sept 2023.pdf13 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Kingstown Residential March 2024 (2).pdf13 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 KINGSTOWN RESIDENTIAL 30-6-21.pdf13 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 M V Kingstown Residential bldg Dec 2021.pdf13 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 M V Kingstown Resi June 21 Qtr.pdf13 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: explanation form 5 kingstown Residential.pdf13 Nov 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration society formation Kingstown.pdf13 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: explanation form 5 kingstown Residential.pdf13 Nov 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Avion1401A Pashan-Sus Rd Pashan93CompletedDec 2017Late, Jul 2018

How this compares with Pune

54%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mont Vert Kingstown Sector 1 Residential Win on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bhugaon13,700+ in Pune

2 kmMont Vert Kingstown SectCompleted 45Lapsed / revoked 28Other 50Dot size: filed unitsN

Filed coordinates, straight-line distance. 123 registered projects within 2 km.

Builder: Niraj Kumar Associates Pvt Ltd

Niraj Kumar Associates Pvt Ltd has 7 registrations on MahaRERA, including Mont Vert Avion and Mont Vert Velocity. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Mont Vert Kingstown Sector 1 Residential Wings shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Mont Vert Kingstown Sector 1 Residential Wings is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mont Vert Kingstown Sector 1 Residential Wings?

The registered promoter entity is Niraj Kumar Associates Pvt Ltd, a company as per the filing. Its CIN U45209MH1995PTC094283 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mont Vert Kingstown Sector 1 Residential Wings?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Mont Vert Kingstown Sector 1 Residential Wings?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Mont Vert Kingstown Sector 1 Residential Wings?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mont Vert Kingstown Sector 1 Residential Wings?

The professionals named in the filing: Architect: TEAMWORK-Architects & Planners; Engineer: Narendra Chaudhary; Engineer: Sachin Thangat; Chartered Accountant: RMR Shah and Co R Shah; Chartered Accountant: Amit Satish Shingvi; Chartered Accountant: Priyanka Chordiya & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mont Vert Kingstown Sector 1 Residential Wings?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mont Vert Kingstown Sector 1 Residential Wings. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mont Vert Kingstown Sector 1 Residential Win to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.