Home / Browse projects / Bengaluru Urban, Karnataka / MJR Clique - Hydra
MJR Clique - Hydra
By MJR BUILDERS PRIVATE LIMITED
RG-KA-31072 · RERA PRM/KA/RERA/1251/310/PR/171028/000684
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
MJR Clique - Hydra is a Residential/Group Housing project by MJR BUILDERS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/171028/000684 on 28 Oct 2017. Possession is promised by 31 Dec 2018.
At a glance
Project
- NameMJR Clique - Hydra
- TypeResidential/Group Housing
- Location
- Bengaluru South
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/310/PR/171028/000684
- ReraGenie IDRG-KA-31072
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on28 Oct 2017
- Promised completion31 Dec 2018
- Revised completionNone
- Buildings5 building records
- Documents filed40 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | - | - | - | 70 | 0 | 70 |
| B | - | - | - | 56 | 0 | 56 |
| C | - | - | - | 52 | 0 | 52 |
| D | - | - | - | 56 | 0 | 56 |
| E | - | - | - | 70 | 0 | 70 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | Not applicable |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | Yes | - |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DSP Design Architects Pvt Ltd |
| Engineer | Anagha Engineering Consultants |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed40
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/171028/000684 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Incorporation certificate.jpg | - |
| CC Hydra | - |
| Hydra- Approved Plan | - |
| MJR | - |
| Sale deed draft- Hydra | - |
| Sale Agreement_hydra | - |
| Land Documents1 | - |
| Approved Section Plan -Hydra | - |
| Area Development Hydra | - |
| MJR Clique Hydra - Allotment Letter | - |
| MJR Clique - Hydra -E-Brochure | - |
| NOC hydra | - |
| MJR Clique -Hydra Specifications | - |
| EC-Hydra- April 2017 to August 2017 | - |
| katha-Hydra | - |
| Balance Sheet 2015 - 2016File: Balancesheet 15-16.pdf | - |
| Balance Sheet 2014 - 2015File: Balance sheet 14-15.pdf | - |
| Balance Sheet 2013 - 2014File: Balancesheet 13-14.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: P & L Account 15-16.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: P & L Account 14-15.pdf | - |
| Audited Profit and Loss Statement 2013 - 2014File: P & L 13-14.pdf | - |
| Director's Report 2015 - 2016File: Directors report 15-16.pdf | - |
| Director's Report 2014 - 2015File: Directors Report 14 -15.pdf | - |
| Director's Report 2013 - 2014File: Director Report 13-14.pdf | - |
| Cash Flow Statement 2015 - 2016File: CASH FLOW 15-16.pdf | - |
| Cash Flow Statement 2014 - 2015File: CASHFLOW 14-15.pdf | - |
| Auditor's Report 2015 - 2016File: Auditor Report 15-16.pdf | - |
| Auditor's Report 2014 - 2015File: Audit Report 14-15.pdf | - |
| Auditor's Report 2013 - 2014File: Audit Report 13-14.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: Income Tax Return - 15-16.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: Income Tax Return 14-15.pdf | - |
| Income Tax Return Acknowledgement 2013 - 2014File: Incometax return 13-14.pdf | - |
| Form B Decleration | - |
| Prospectus/BrochureFile: MJR Clique - Hydra -E-Brochure.pdf | - |
| Advertisement Copy 1File: MJR Clique - Hydra -E-Brochure.pdf | - |
| Tower Excel SheetFile: Copy of PRM_KA_RERA_1251_310_PR_171028_000684-3.xlsx | - |
| Occupancy CertificateFile: OC - Hydra.pdf | - |
| Completion certificateFile: COMPLETATION CERTIFICATE- HYDRA.pdf | - |
| Registered Agreement of SaleFile: Sale Agreement.pdf | - |
| Registered conveyance deed for an individual unitFile: Sale Deed.pdf | - |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| MJR Platina | - | Completed | Aug 2017 | No date filed |
| MJR Pearl | - | Completed | Aug 2017 | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep MJR Clique - Hydra on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: MJR BUILDERS PRIVATE LIMITED
MJR Builders Private Limited has 2 registrations on RERA Karnataka, including MJR Opus and MJR Clique - Hydra. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if MJR Clique - Hydra is delayed beyond 31 Dec 2018?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of MJR Clique - Hydra?
The registered promoter entity is MJR BUILDERS PRIVATE LIMITED, a company as per the filing. Its CIN U45209KA2011PTC057125 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in MJR Clique - Hydra?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at MJR Clique - Hydra?
The professionals named in the filing: Architect: DSP Design Architects Pvt Ltd; Engineer: Anagha Engineering Consultants. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MJR Clique - Hydra?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback