Registration approved Residential/Group Housing project

MITTAL PALMS

By TRISHUL DEVELOPERS

RG-KA-94562 · RERA PRM/KA/RERA/1251/309/PR/180328/000585

Source: official RERA Karnataka filing

Red flags

  • 11 complaints at RERA Karnataka
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Aug 2020Possession promisedmoved 12 months from the original
11Complaints at RERA Karnatakaon this registration
Jump to the 33 documents Report an error

MITTAL PALMS is a Residential/Group Housing project by TRISHUL DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/180328/000585 on 28 Mar 2018. Possession is promised by 1 Aug 2020. The completion date has moved by 12 months from the original filing. 11 complaints are on record with the regulator.

At a glance

Project

  • NameMITTAL PALMS
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/309/PR/180328/000585
  • ReraGenie IDRG-KA-94562

Builder

  • NameTRISHUL DEVELOPERS
  • Entity typePartnership Firm
  • Authorized SignatoryNIRAJ OMPRAKASH MITTAL

Key dates

this monthRegisteredMar 2018First promiseAug 2019Revised toAug 2020

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on28 Mar 2018
  • Promised completion1 Aug 2020
  • Revised completionRevised to 1 Aug 2020 (originally 1 Aug 2019)
  • Buildings7 building records
  • Documents filed33 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---32032
B---32032
C---32032
D---28028
E---28028
F---32032
G---40040

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,460 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 80.00 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/309/PR/220620/000585Aug 2019 → Aug 2020

Reason as filed by the promoterActivities undertaken by BMRDA, BBPM, BESCOM etc. leading to delay in construction

Complaints filed with RERA Karnataka11

Case no.ComplainantRespondentFiled
CMP/200103/0005130-TRISHUL DEVELOPERS03/01/2020
CMP/200106/0005150-TRISHUL DEVELOPERS06/01/2020
CMP/210119/0007420-TRISHUL DEVELOPERS19/01/2021
CMP/220420/0009371-TRISHUL DEVELOPERS20/04/2022
CMP/220711/0009738-TRISHUL DEVELOPERS11/07/2022
CMP/220822/0009926-TRISHUL DEVELOPERS22/08/2022
CMP/220921/0010035-TRISHUL DEVELOPERS21/09/2022
CMP/221007/0010058-TRISHUL DEVELOPERS07/10/2022
01359/2023-TRISHUL DEVELOPERS05/09/2023
01360/2023-TRISHUL DEVELOPERS05/09/2023
01361/2023-TRISHUL DEVELOPERS05/09/2023

Documents filed33

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/180328/000585 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Partnership REGN.pdf-
Latest Encumbrance CertificateFile: EC.pdf-
COMMECEMENT-
SITE PLAN-
Siteplan-
Agreement_to_sell-
Village Map of Shivanhalli-
SITE PLAN-
ALL NOC'S-
SPECS-
EC-
Katha Certificate & Extract-
JD-
Balance Sheet 2015 - 2016File: BALANCE SHEET 15-16.pdf-
Balance Sheet 2014 - 2015File: BALANCE SHEET 14-15.pdf-
Balance Sheet 2013 - 2014File: BALANCE SHEET 13-14.pdf-
Audited Profit and Loss Statement 2015 - 2016File: PROFIT LOSS 15-16.pdf-
Audited Profit and Loss Statement 2014 - 2015File: PROFIT LOSS 14-15.pdf-
Audited Profit and Loss Statement 2013 - 2014File: PROFIT LOSS 13-14.pdf-
Director's Report 2015 - 2016File: DIRECTORS REPORT.pdf-
Director's Report 2014 - 2015File: DIRECTORS REPORT.pdf-
Director's Report 2013 - 2014File: DIRECTORS REPORT.pdf-
Cash Flow Statement 2015 - 2016File: CASH FLOW.pdf-
Cash Flow Statement 2014 - 2015File: CASH FLOW.pdf-
Auditor's Report 2015 - 2016File: AUDITORS REPORT 15-16.pdf-
Auditor's Report 2014 - 2015File: AUDIT REPORT 14-15.pdf-
Auditor's Report 2013 - 2014File: AUDITORS REPORT 13-14.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: IT ACKNO 15-16.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: IT ACKNO 14-15.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: IT ACNO 13-14.pdf-
Prospectus/BrochureFile: Mittal brochure Page 01.pdf-
Advertisement Copy 1File: Mittal Palms ebrochure.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR_180328_000585.xlsx-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep MITTAL PALMS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: TRISHUL DEVELOPERS

TRISHUL DEVELOPERS has 1 registration on RERA Karnataka, including MITTAL PALMS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if MITTAL PALMS is delayed beyond 1 Aug 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of MITTAL PALMS?

The registered promoter entity is TRISHUL DEVELOPERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in MITTAL PALMS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MITTAL PALMS?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

What should I check before booking in MITTAL PALMS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MITTAL PALMS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MITTAL PALMS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.