Miraya Brunton by UKN
By UKN Properties Private Limited
RG-KA-33318 · RERA PRM/KA/RERA/1251/310/PR/210810/004250 · Last updated on RERA Karnataka portal: 14 Apr 2026
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 18 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
Saved.
Miraya Brunton by UKN is a Residential/Group Housing project by UKN Properties Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/210810/004250 on 10 Aug 2021. Possession is promised by 30 Jun 2026. The completion date has moved by 18 months from the original filing. 5 of the 10 units on this registration are recorded sold or booked, and 16 of 16 construction stages are filed complete.
At a glance
Project
- NameMiraya Brunton by UKN
- TypeResidential/Group Housing
- Location
- Bengaluru South
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/310/PR/210810/004250
- ReraGenie IDRG-KA-33318
Builder
- NameUKN Properties Private Limited
- Entity typeCompany
- CINU70102KA1997PTC022387
- Authorized SignatoryMr. Gautam U Nambisan
- OthersMr. Sudhir Kumar Mishra
- Declared earlier projects4 →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on10 Aug 2021
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2024)
- Buildings1 building record
- Documents filed129 files
Current status
Figures as on 14 Apr 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Miraya Brunton by ukn | - | - | - | 10 | 0 | 10 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 16 construction stages are filed complete.
Building: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Retaining wall (All types) | 100% |
| Plinth level Beam | Not applicable |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| RCC or MS Framed structure | 100% |
| Masonry construction: Bricks, Concrete blocks etc | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 100% |
| Basic work of Water supply, Sanitary and Electrification | 100% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 100% |
| Railing and Grill fixing | 100% |
| Electrification, Water supply and Sanitary Finishing | 100% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | 100% |
| Painting | 100% |
| Elevation work | 100% |
| Internal and External work including landscapes as per santioned drawings | 100% |
Progress on shared amenities41
As on 14 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 100% |
| Internal Roads & Footpaths | Yes | 0% |
| Sewage and Drainage System | Yes | 100% |
| Parks & Tree planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | Yes | 100% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | 0% |
| Electricity supply transformer and substation | Yes | 100% |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | 100% |
| Use of renewable energy | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 100% |
| Electricity | Yes | 100% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | Yes | 100% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 100% |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | 100% |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | 100% |
| Lifts | Yes | 100% |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | 100% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | 100% |
| Basement | Yes | 100% |
| Terrace | Yes | 100% |
| Outer Wall | Yes | 100% |
| Open parking areas and common storage spaces | Yes | 0% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| V R Rajesh | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 22.30 cr | Rs 19.45 cr |
| On-site expenditure-Salaries of workers | Rs 2.90 cr | Rs 2.79 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Kabir Hira |
| Engineer | Rajesh M H |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterApplied for modification
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed129
As listed on the registration, under the names the promoter filed them with; the newest 80 of 129 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/210810/004250 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Brunton_Format_Form -4, Chartered Accountant (QU).pdf | 14 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect_Brunton_Q4-2025-26.pdf | 14 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Brunton_Engineer Certificate_Q-4-25-26.pdf | 14 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 14 Apr 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 14 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Brunton_Format_Form -4, Chartered Accountant Q3 25-26.pdf | 12 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 05 Architect_Brunton_Q3-2025-26.pdf | 12 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Brunton_Engineer Certificate_Q-3-25-26.pdf | 12 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 12 Jan 2026 |
| Q3 2025-26 KPTCL- BESCOM | 12 Jan 2026 |
| CONSENT LETTER -MIRAYA BRUNTON BY UKNFile: CONSENT LETTER -MIRAYA BRUNTON BY UKN.pdf | 5 Feb 2025 |
| KSPCB CFE dated 24.11.2020File: KSPCB CFE dated 24112020.pdf | 5 Feb 2025 |
| BWSSB -NOC -05.03.2024File: BWSSB -NOC -05032024.pdf | 5 Feb 2025 |
| BUILDING LICENSE dated 03.09.2024File: BUILDING LICENSE dated 03092024.pdf | 5 Feb 2025 |
| Demand Notice for Modified Plan Sanction -Miraya BruntonFile: Demand Notice for Modified Plan Sanction -Miraya Brunton.pdf | 5 Feb 2025 |
| Approved planFile: Approved plan (7).pdf | 5 Feb 2025 |
| SOLD & UNSOLD UNITS -MIRAYA BRUNTONFile: SOLD & UNSOLD UNITS -MIRAYA BRUNTON.pdf | 5 Feb 2025 |
| Quarterly Updates Q3 2024 25File: Quarterly Update Details Miraya Brunton q3 2024-25.pdf | 20 Jan 2025 |
| Commencement certificateFile: Commencement Certificate dated 27 07 2022.pdf | 20 Jan 2025 |
| RERA Bank accountFile: RERA Bank Account.pdf | 28 Jul 2021 |
| Development details units break upFile: Development details units break up.pdf | 28 Jul 2021 |
| Directors Report 2019-20File: Directors Report -2019-20.pdf | 3 Mar 2021 |
| Bank Statement for the ProjectFile: Bank account for Brunton.pdf | 3 Mar 2021 |
| Balance sheetFile: 1875_210216171842_001_compressed(1).pdf | 17 Feb 2021 |
| P and LFile: 1875_210216171842_001_compressed(1).pdf | 17 Feb 2021 |
| Director Report 2016-17File: Directors Report - 2016-17.pdf | 17 Feb 2021 |
| Director Report 2017-18File: Directors Report - 2017-18.pdf | 17 Feb 2021 |
| Director Report 2018-19File: Directors Report -2018-19.pdf | 17 Feb 2021 |
| ECFile: EC from 01.04.2004 to 10.12.2020 (1).pdf | 17 Feb 2021 |
| Building LicenseFile: Building Liscense.pdf | 17 Feb 2021 |
| Bank StatementFile: NOV-2020.pdf | 17 Feb 2021 |
| CertificateFile: Certificate of Incorporation.pdf | - |
| Project Details | - |
| Already registered project ongoing detailsFile: Ongoing project Belvedere phase 2.pdf | - |
| Modified plan details site plan, floor plans, Plan Licence LetterFile: Building License.pdf | - |
| Elevation, Sections, Specifications ( If changes are there )File: Project Specification.pdf | - |
| List Of AllotteesFile: List of Allotees -MIRAYA BRUNTON BY UKN.pdf | - |
| Consent LetterFile: Consent Letter.pdf | - |
| Chartered Accountant CertificateFile: modification_form4 CA CERTIFICATE.pdf | - |
| Notarized AffidavitFile: Notarized Affidavit cum declaration.pdf | - |
| Engineer CertificateFile: modification_form6 ENG CERTIFICATE.pdf | - |
| Architect CertificateFile: Modification Form 5 ARCHITECT CERTIFICATE.pdf | - |
| Structural Engineer Certificate for stability of structureFile: Structural Stability Certificate.pdf | - |
| Modification of Plan DetailsFile: Plan Brunton Road.pdf | - |
| Modification of Plan DetailsFile: Approved Sanction Plan.pdf | - |
| Modification of Plan DetailsFile: Commencement Certificate dated 27 07 2022.pdf | - |
| Modification of Plan DetailsFile: Commencement Certificate dated 27 07 2022.pdf | - |
| Modification of Plan DetailsFile: Sold and unsold unit details.pdf | - |
| Modification of Plan DetailsFile: Sold and unsold unit details.pdf | - |
| Document 1File: BWSSB -NOC -05 03 2024.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: Form-Ex1 Architect Certificate For Status of Work As On Date.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Form-Ex5 Engineers Certificate for Status of Work as on date.pdf | - |
| CA Certificate for Funds UtilizationFile: Form-Ex3 Chartered Accountant Certificate For Fund Utilization.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Form-Ex2 Architect Certificate For Pending Work As On Date.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Form-Ex6 Engineers Certifictae for Pending work as on date.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: Form-Ex4 Chartered Accountant Certificate For Fund Required.pdf | - |
| AffidavitFile: Form-Ex7 Affidavit for seeking extension of registered project.pdf | - |
| Latest Encumbrance CertificateFile: EC FROM 25 05 2023 TO 16 11 2024(6568042).pdf | - |
| Consent letter from 2/3rd of AllotteesFile: Consent Letter.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: Sold and unsold unit details.pdf | - |
| Document2 | - |
| Plan Brunton Road | - |
| Document2 | - |
| Document2 | - |
| Sale deed | - |
| Building License | - |
| Sanction Plan | - |
| Document2 | - |
| Document2 | - |
| Specifications | - |
| EC | - |
| Document2 | - |
| Affidavit Cum Declaration | - |
| Khata | - |
| JDA | - |
| Document2 | - |
| Document2 | - |
| Document2 | - |
| Unnamed document | - |
| Unnamed document | - |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Miraya Rose by UKN | - | Completed | - | No date filed |
| Garden of Eden by UKN | - | Completed | - | No date filed |
| Esperanza by UKN | - | Completed | - | No date filed |
| Belvista by UKN | - | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Miraya Brunton by UKN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: UKN Properties Private Limited
UKN Properties Private Limited has 1 registration on RERA Karnataka, including Miraya Brunton by UKN. Its filings declare 4 earlier projects, 4 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Miraya Brunton by UKN is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Miraya Brunton by UKN?
The registered promoter entity is UKN Properties Private Limited, a company as per the filing. Its CIN U70102KA1997PTC022387 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Miraya Brunton by UKN?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Miraya Brunton by UKN?
The professionals named in the filing: Architect: Kabir Hira; Engineer: Rajesh M H. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Miraya Brunton by UKN?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback