ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Miraya Brunton by UKN

Registration approved No litigation declared Residential/Group Housing project

Miraya Brunton by UKN

By UKN Properties Private Limited

RG-KA-33318 · RERA PRM/KA/RERA/1251/310/PR/210810/004250 · Last updated on RERA Karnataka portal: 14 Apr 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Jun 2026Possession promisedmoved 18 months from the original
16 of 16Construction stages doneevery applicable stage filed complete
5 of 10Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 129 documents Report an error

Miraya Brunton by UKN is a Residential/Group Housing project by UKN Properties Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/210810/004250 on 10 Aug 2021. Possession is promised by 30 Jun 2026. The completion date has moved by 18 months from the original filing. 5 of the 10 units on this registration are recorded sold or booked, and 16 of 16 construction stages are filed complete.

At a glance

Project

  • NameMiraya Brunton by UKN
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/210810/004250
  • ReraGenie IDRG-KA-33318

Builder

  • NameUKN Properties Private Limited
  • Entity typeCompany
  • CINU70102KA1997PTC022387
  • Authorized SignatoryMr. Gautam U Nambisan
  • OthersMr. Sudhir Kumar Mishra
  • Declared earlier projects4 →

Key dates

this monthRegisteredAug 2021First promiseDec 2024Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on10 Aug 2021
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed129 files

Current status

50%5 of 10 units booked
88.3%Of the estimated cost spent so far

Figures as on 14 Apr 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Miraya Brunton by ukn---10010

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 16 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)100%
Painting100%
Elevation work100%
Internal and External work including landscapes as per santioned drawings100%

Progress on shared amenities41

As on 14 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsYes0%
Sewage and Drainage SystemYes100%
Parks & Tree plantingYes100%
Street LightingYes100%
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes100%
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes100%
Use of renewable energyYes0%
Water conservation/rain water harvesting/recharge of ground waterYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes100%
GymYes0%
ParksYes0%
Power BackupYes100%
GasNoNot applicable
Water and SanitationYes100%
Air Conditioning And incerntionNoNot applicable
StaircasesYes100%
LiftsYes100%
Staircases and Lift lobbies, corridor,lobbies, corridorYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areas and common storage spacesYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,239 sq m
Named landowners1
LandownerVillageDistrict
V R Rajesh--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 25.20 cr
Cost incurredRs 22.24 cr
Spent of the estimate88.27%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 22.30 crRs 19.45 cr
On-site expenditure-Salaries of workersRs 2.90 crRs 2.79 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKabir Hira
EngineerRajesh M H

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/310/PR/250123/004250Dec 2024 → Dec 2025

Reason as filed by the promoterApplied for modification

ExtensionDec 2025 → Jun 2026

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed129

As listed on the registration, under the names the promoter filed them with; the newest 80 of 129 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/210810/004250 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Brunton_Format_Form -4, Chartered Accountant (QU).pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect_Brunton_Q4-2025-26.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Brunton_Engineer Certificate_Q-4-25-26.pdf14 Apr 2026
Q4 2025-26 Water supply and sewage board14 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Brunton_Format_Form -4, Chartered Accountant Q3 25-26.pdf12 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 05 Architect_Brunton_Q3-2025-26.pdf12 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Brunton_Engineer Certificate_Q-3-25-26.pdf12 Jan 2026
Q3 2025-26 Water supply and sewage board12 Jan 2026
Q3 2025-26 KPTCL- BESCOM12 Jan 2026
CONSENT LETTER -MIRAYA BRUNTON BY UKNFile: CONSENT LETTER -MIRAYA BRUNTON BY UKN.pdf5 Feb 2025
KSPCB CFE dated 24.11.2020File: KSPCB CFE dated 24112020.pdf5 Feb 2025
BWSSB -NOC -05.03.2024File: BWSSB -NOC -05032024.pdf5 Feb 2025
BUILDING LICENSE dated 03.09.2024File: BUILDING LICENSE dated 03092024.pdf5 Feb 2025
Demand Notice for Modified Plan Sanction -Miraya BruntonFile: Demand Notice for Modified Plan Sanction -Miraya Brunton.pdf5 Feb 2025
Approved planFile: Approved plan (7).pdf5 Feb 2025
SOLD & UNSOLD UNITS -MIRAYA BRUNTONFile: SOLD & UNSOLD UNITS -MIRAYA BRUNTON.pdf5 Feb 2025
Quarterly Updates Q3 2024 25File: Quarterly Update Details Miraya Brunton q3 2024-25.pdf20 Jan 2025
Commencement certificateFile: Commencement Certificate dated 27 07 2022.pdf20 Jan 2025
RERA Bank accountFile: RERA Bank Account.pdf28 Jul 2021
Development details units break upFile: Development details units break up.pdf28 Jul 2021
Directors Report 2019-20File: Directors Report -2019-20.pdf3 Mar 2021
Bank Statement for the ProjectFile: Bank account for Brunton.pdf3 Mar 2021
Balance sheetFile: 1875_210216171842_001_compressed(1).pdf17 Feb 2021
P and LFile: 1875_210216171842_001_compressed(1).pdf17 Feb 2021
Director Report 2016-17File: Directors Report - 2016-17.pdf17 Feb 2021
Director Report 2017-18File: Directors Report - 2017-18.pdf17 Feb 2021
Director Report 2018-19File: Directors Report -2018-19.pdf17 Feb 2021
ECFile: EC from 01.04.2004 to 10.12.2020 (1).pdf17 Feb 2021
Building LicenseFile: Building Liscense.pdf17 Feb 2021
Bank StatementFile: NOV-2020.pdf17 Feb 2021
CertificateFile: Certificate of Incorporation.pdf-
Project Details-
Already registered project ongoing detailsFile: Ongoing project Belvedere phase 2.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: Building License.pdf-
Elevation, Sections, Specifications ( If changes are there )File: Project Specification.pdf-
List Of AllotteesFile: List of Allotees -MIRAYA BRUNTON BY UKN.pdf-
Consent LetterFile: Consent Letter.pdf-
Chartered Accountant CertificateFile: modification_form4 CA CERTIFICATE.pdf-
Notarized AffidavitFile: Notarized Affidavit cum declaration.pdf-
Engineer CertificateFile: modification_form6 ENG CERTIFICATE.pdf-
Architect CertificateFile: Modification Form 5 ARCHITECT CERTIFICATE.pdf-
Structural Engineer Certificate for stability of structureFile: Structural Stability Certificate.pdf-
Modification of Plan DetailsFile: Plan Brunton Road.pdf-
Modification of Plan DetailsFile: Approved Sanction Plan.pdf-
Modification of Plan DetailsFile: Commencement Certificate dated 27 07 2022.pdf-
Modification of Plan DetailsFile: Commencement Certificate dated 27 07 2022.pdf-
Modification of Plan DetailsFile: Sold and unsold unit details.pdf-
Modification of Plan DetailsFile: Sold and unsold unit details.pdf-
Document 1File: BWSSB -NOC -05 03 2024.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Form-Ex1 Architect Certificate For Status of Work As On Date.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Form-Ex5 Engineers Certificate for Status of Work as on date.pdf-
CA Certificate for Funds UtilizationFile: Form-Ex3 Chartered Accountant Certificate For Fund Utilization.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Form-Ex2 Architect Certificate For Pending Work As On Date.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Form-Ex6 Engineers Certifictae for Pending work as on date.pdf-
CA Certificate for Funds required for Project CompletionFile: Form-Ex4 Chartered Accountant Certificate For Fund Required.pdf-
AffidavitFile: Form-Ex7 Affidavit for seeking extension of registered project.pdf-
Latest Encumbrance CertificateFile: EC FROM 25 05 2023 TO 16 11 2024(6568042).pdf-
Consent letter from 2/3rd of AllotteesFile: Consent Letter.pdf-
Details Of Sold/ Un-sold UnitsFile: Sold and unsold unit details.pdf-
Document2-
Plan Brunton Road-
Document2-
Document2-
Sale deed-
Building License-
Sanction Plan-
Document2-
Document2-
Specifications-
EC-
Document2-
Affidavit Cum Declaration-
Khata-
JDA-
Document2-
Document2-
Document2-
Unnamed document-
Unnamed document-

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Miraya Rose by UKN-Completed-No date filed
Garden of Eden by UKN-Completed-No date filed
Esperanza by UKN-Completed-No date filed
Belvista by UKN-Completed-No date filed

How this compares with Bengaluru Urban

50%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 18 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Miraya Brunton by UKN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: UKN Properties Private Limited

UKN Properties Private Limited has 1 registration on RERA Karnataka, including Miraya Brunton by UKN. Its filings declare 4 earlier projects, 4 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Miraya Brunton by UKN is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Miraya Brunton by UKN?

The registered promoter entity is UKN Properties Private Limited, a company as per the filing. Its CIN U70102KA1997PTC022387 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Miraya Brunton by UKN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Miraya Brunton by UKN?

The professionals named in the filing: Architect: Kabir Hira; Engineer: Rajesh M H. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Miraya Brunton by UKN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Miraya Brunton by UKN. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Miraya Brunton by UKN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.