Home / Browse projects / Bengaluru Urban, Karnataka / MILLENIA MUTHANALLUR

Registration approved No litigation declared Residential/Group Housing project

MILLENIA MUTHANALLUR

By Nambiar Enterprises LLP

RG-KA-04021 · RERA PRM/KA/RERA/1251/308/PR/220202/004665 · Last updated on RERA Karnataka portal: 15 Apr 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Nov 2026Possession promisedno revision filed
18 of 18Construction stages doneevery applicable stage filed complete
81 of 604Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 136 documents Report an error

MILLENIA MUTHANALLUR is a Residential/Group Housing project by Nambiar Enterprises LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/220202/004665 on 2 Feb 2022. Possession is promised by 30 Nov 2026. 523 of the 604 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.

At a glance

Project

  • NameMILLENIA MUTHANALLUR
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/220202/004665
  • ReraGenie IDRG-KA-04021

Builder

  • NameNambiar Enterprises LLP
  • Entity typePartnership Firm
  • Authorized SignatoryPavan Kumar Reddy Kovvuri
  • OthersRajesh P K, K S Satyanarayana Reddy, Pavan Kumar Reddy Kovvuri, Ratheesh Nambiar, Ramesh Nambiar

Key dates

this monthRegisteredFeb 2022PromisedNov 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on2 Feb 2022
  • Promised completion30 Nov 2026
  • Revised completionNone
  • Buildings4 building records
  • Documents filed136 files

Current status

87%523 of 604 units booked
6.1%Of the estimated cost spent so far

Figures as on 15 Apr 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower A---1900190
Tower B---1200120
Tower C---1540154
Tower D---1400140

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Painting100%
Elevation work100%
Internal and External work including landscapes as per santioned drawings100%

Progress on shared amenities41

As on 15 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsYes100%
Sewage and Drainage SystemYes100%
Parks & Tree plantingYes0%
Street LightingYes0%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservationYes100%
Energy managementYes0%
Fire protection and fire safety requirementsYes100%
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes100%
Emergency Evacuation servicesYes100%
Storm water drainsYes100%
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseYes100%
Community HallYes100%
Outdoor Sports facilityYes100%
Indoor Sports facilityYes100%
Swimming PoolYes100%
GymYes100%
ParksYes100%
Power BackupYes100%
GasYes0%
Water and SanitationYes100%
Air Conditioning And incerntionYes100%
StaircasesYes100%
LiftsYes100%
Staircases and Lift lobbies, corridor,lobbies, corridorYes100%
Fire escapesYes100%
Common entrance and exit for the building / common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areas and common storage spacesYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area15,530 sq m
Named landowners1
LandownerVillageDistrict
Nambiar Enterprises LLP--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 232.00 cr
Cost incurredRs 14.24 cr
Spent of the estimate6.14%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 192.75 crRs 8.60 cr
Interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 25.20 crRs 50.85 lakh
On-site expenditure-Site OverheadRs 5.34 crRs 1.24 cr
On-site expenditure-Salaries of workersRs 2.95 crRs 79.75 lakh
On-site expenditure-Consultants FeesRs 2.39 crRs 33.10 lakh
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 2.37 crRs 1.76 cr
Payment of chargesRs 1.00 crRs 1.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGnanavel. T
EngineerAmbrish G

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed136

As listed on the registration, under the names the promoter filed them with; the newest 80 of 136 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/220202/004665 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4-Q4 25-26 Nambiar Millennia.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5-Architect-Nambiar Millennia _Q4 25-26.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6-Q4 25-26 Nambiar Millennia.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4-CA-Nambiar Millennia _Q3 25-26.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5-Architect-Nambiar Millennia _Q3 25-26.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 - Q3 FY 25-25 Millenia.pdf15 Jan 2026
Q3 2025-26 Water supply and sewage board15 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Jan 2026
Q3 2025-26 KPTCL- BESCOM15 Jan 2026
Q3 2025-26 Fire and Safety15 Jan 2026
Q3 2025-26 Airport Authority of India15 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department15 Jan 2026
Proforma of Agreement for Sale in conformity with the GOK notified Agreement for SaleFile: Proforma AOS-Project Nambiar Millenia I.pdf26 Jan 2022
Declaration Letter of Promoters of Nambiar Enterprises LLPFile: Declaration of Promoter of Nambiar Enterprises LLP.pdf10 Jan 2022
Proforma of Agreement for Sale in conformity with the GOK notified Agreement for SaleFile: Proforma Agreement For Sale - Project Nambiar Millenia I.pdf10 Jan 2022
Bellezea Phase V-Quarterly update Details-Q-2-21-22File: Bellezea Phase V-Quarterly update Details-Q-2-21-22.pdf19 Dec 2021
Ellegenza Phase -I-Quarterly update Details-Q-2-21-22File: Ellegenza Phase -I-Quarterly update Details-Q-2-21-22.pdf19 Dec 2021
Bellezea- Phase IV-Quarterly update Details-Q-2-21-22File: Bellezea- Phase IV-Quarterly update Details-Q-2-21-22.pdf19 Dec 2021
Bellezea -Annex-Quarterly update Details-Q-2-21-22File: Bellezea -Annex-Quarterly update Details-Q-2-21-22.pdf19 Dec 2021
Audited P & L Account of Nambiar Enterprises LLP For the FY - 2020-21File: Audited P&L Account FY - 2020-21.pdf19 Dec 2021
Audited Balance Sheet of Nambiar Enterprises LLP For the FY - 2020-21File: Audited Balance Sheet FY - 2020-21.pdf19 Dec 2021
Proforma Allotment LetterFile: Proforma Allotment Letter.pdf19 Dec 2021
Proforma Agreement to SellFile: Nambiar Millenia I - Agreement to Sell.pdf19 Dec 2021
Proforma Sale DeedFile: Nambiar Millenia I - Sale Deed.pdf19 Dec 2021
Project SpecificationsFile: Project Specification-NELLP.pdf19 Dec 2021
Form B in RERA prescribed formFile: Declaration Form B.pdf8 Oct 2021
Site PlanFile: Site Plan.pdf8 Oct 2021
Basement PlanFile: Basement Plan_compressed.pdf8 Oct 2021
Ground Floor PlanFile: Ground Floor Plan_compressed.pdf8 Oct 2021
Elevation 1 & Section AAFile: Elevation-1 & Section - AA.pdf8 Oct 2021
First Floor Plan Building 1File: First Floor Plan Building - 1.pdf8 Oct 2021
First Floor Plan Building 2File: First Floor Plan Building - 2.pdf8 Oct 2021
Terrace Plan Building 1File: Terrace Plan Building - 1.pdf8 Oct 2021
Terrace Plan Building 2File: Terrace Plan Building - 2.pdf8 Oct 2021
Typical Floor Plan (2nd to 13th Floor) Building 2File: Typical Floor Plan (2nd to 13th Floor)-Building-2.pdf8 Oct 2021
14th Floor Plan Building 1File: 14th Floor Plan- Building - 1.pdf8 Oct 2021
14th Floor Plan Building 2File: 14th Floor Plan- Building - 2.pdf8 Oct 2021
Relinquishment DeedFile: Relinquishment Deed.pdf8 Oct 2021
Project SpecificationFile: Project Specification-NELLP.pdf8 Oct 2021
Section 3 (1) Notarized AffidavitFile: Notarized Affidavit for 3(1) Voliation.pdf8 Oct 2021
NOC issued by Airport AuthorityFile: Airport Authority - NOC.pdf8 Oct 2021
Approved Building Plan with STP demarcationFile: Approved Building Plan with STP demarcation.pdf8 Oct 2021
CertificateFile: Registration Certificate.pdf-
Already registered project ongoing detailsFile: Ongoing Project Details.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: Floor Plans and Others.pdf-
List Of AllotteesFile: List of Allottes.xlsx-
Consent LetterFile: Consent Letter.pdf-
Chartered Accountant CertificateFile: Form 4 CA Certificate.pdf-
Notarized AffidavitFile: Affidavit.pdf-
Engineer CertificateFile: Form 6 - Millenia - Modification.pdf-
Architect CertificateFile: Form-5-Architect-Nambiar Millennia - Modification.pdf-
Structural Engineer Certificate for stability of structureFile: Stability Certificate - Structural Engineer.pdf-
Modification of Plan DetailsFile: Approved Building Plan-Merged_Compressed.pdf-
Modification of Plan DetailsFile: DP Plan.pdf-
Modification of Plan DetailsFile: Commencement Certificate -Old.pdf-
Modification of Plan DetailsFile: Commenecement Certficiate New.pdf-
Modification of Plan DetailsFile: Tower Details - Sold & Unsold New.xlsx-
Modification of Plan DetailsFile: Tower Details - Sold & Unsold Old.xlsx-
Document 1File: Fire NOC.pdf-
Document 2File: Nambiar Enterprises Airport NOC.pdf-
Document 3File: Millenia BESCOM NOC Full Project.pdf-
Document 4File: MILLENIA WATER NOC.pdf-
Document 5File: PCB.pdf-
Document 6File: Nambiar ECxpn SEIAA.pdf-
Document 7File: BSNL NOC OF MILLENIA-.pdf-
Exchange Deed Sy No. 128/4, 131/4, 131/7File: Exchange Deed 128 bar 4, 131 bar 4 and 131 bar 7.pdf-
Exchange Deed Sy No. 128/5File: Exchange Deed 128 bar 5.pdf-
Exchange Deed Sy. No. 131/3File: Exchange Deed 131 bar 3.pdf-
Sale Deed Sy No. 128/1File: SY NO 128-1 sale deed doc 3806 2021 compressed.pdf-
Commencement Certificate_Compressed-
MUTHANALURU- DP PLAN_Compressed-
RERA Document -1-
RERA Document -1-
Sale Deed & RTC_Compressed-

How this compares with Bengaluru Urban

87%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep MILLENIA MUTHANALLUR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Nambiar Enterprises LLP

Nambiar Enterprises LLP has 1 registration on RERA Karnataka, including MILLENIA MUTHANALLUR. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if MILLENIA MUTHANALLUR is delayed beyond 30 Nov 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of MILLENIA MUTHANALLUR?

The registered promoter entity is Nambiar Enterprises LLP, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in MILLENIA MUTHANALLUR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at MILLENIA MUTHANALLUR?

The professionals named in the filing: Architect: Gnanavel. T; Engineer: Ambrish G. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MILLENIA MUTHANALLUR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MILLENIA MUTHANALLUR. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MILLENIA MUTHANALLUR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.