ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Metro Urbano

Registration approved Residential/Group Housing project

Metro Urbano

By NYK Homes

RG-KA-54170 · RERA PRM/KA/RERA/1251/310/PR/180924/002015

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Sep 2021Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 78 documents Report an error

Metro Urbano is a Residential/Group Housing project by NYK Homes in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/180924/002015 on 24 Sep 2018. Possession is promised by 30 Sep 2021. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameMetro Urbano
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/180924/002015
  • ReraGenie IDRG-KA-54170

Builder

  • NameNYK Homes
  • Entity typePartnership Firm
  • Authorized SignatoryY.Kumaraswamy
  • OthersC.Vishwanath, Y.Hemanth Kumar, N.Nalini, Y.Naveen Kumar

Key dates

this monthRegisteredSep 2018First promiseDec 2020Revised toSep 2021

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on24 Sep 2018
  • Promised completion30 Sep 2021
  • Revised completionRevised to 30 Sep 2021 (originally 31 Dec 2020)
  • Buildings1 building record
  • Documents filed78 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ABC---87087

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,717 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 22.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAslam Architects (Ani Sambyal Singh)
EngineerBhaskar Y

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2020 → Sep 2021

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed78

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/180924/002015 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: NYK Partnership firm Certificate.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Architect OC Form.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer OC.pdf-
CA Certificate for Funds UtilizationFile: Form-4, CA FUNDS.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architect OC Form.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineer OC.pdf-
CA Certificate for Funds required for Project CompletionFile: Form-4, CA FUNDS.pdf-
AffidavitFile: RERA Extension Affidavit.pdf-
Latest Encumbrance CertificateFile: NYK Metro Urbano Latest EC.jpeg-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails (1).xlsx-
Document 1File: NYK BESCOM Application.pdf-
NA To The Project-
compressed_Sanction Plan Full -
NA To The Project-
Proforma Agreement of Sale-
Proforma Agreement of Sale-
Saledeed combine-
NA To The Project-
NA To The Project-
Allotment Letter-
Metro Urbano Brochure-
Apartment specification-
NYK EC April 2017 to May 2018-
Khatha Extract-
Joint Development Agreement-
Court Settlement -
Conversion-
NA To The Project-
NA To The Project-
NA To The Project-
NA To The Project-
NYK Hosur Rd -Fire NOC-3-
NYK Hosur Rd - Airport NOC-
NYK Hosur Rd -BESCOM NOC-
NYK BWSSB demand note-
NYK Hosur Rd - Pollution NOC-4-
NA To The Project-
NYK Hosur Rd - BSNL NOC-
NA To The Project-
Unnamed document-
NA To The Project-
NYK Homes - BMRCL NOC-
NA To The Project-
NA To The Project-
NA To The Project-
NA To The Project-
NA To The Project-
NA To The Project-
NA To The Project-
NA To The Project-
NA To The Project-
NYK Legal Opinion 2-
Balance Sheet 2016 - 2017File: Balance Sheet 2017-18.pdf-
Balance Sheet 2015 - 2016File: Balance Sheet 2016-17.pdf-
Balance Sheet 2014 - 2015File: Balance Sheet 2015-16.pdf-
Audited Profit and Loss Statement 2016 - 2017File: NA To First Project.pdf-
Audited Profit and Loss Statement 2015 - 2016File: NA To First Project.pdf-
Audited Profit and Loss Statement 2014 - 2015File: NA To First Project.pdf-
Director's Report 2016 - 2017File: NA To First Project.pdf-
Director's Report 2015 - 2016File: NA To First Project.pdf-
Director's Report 2014 - 2015File: NA To First Project.pdf-
Cash Flow Statement 2016 - 2017File: NA To First Project.pdf-
Cash Flow Statement 2015 - 2016File: NA To First Project.pdf-
Auditor's Report 2016 - 2017File: Auditor Letter for RERA.pdf-
Auditor's Report 2015 - 2016File: NA To First Project.pdf-
Auditor's Report 2014 - 2015File: NA To First Project.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: NYK Homes AY 2017.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: NYK Homes AY 2016.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: NYK Homes AY 2015.pdf-
Form B -
Prospectus/BrochureFile: Metro Urbano Brochure Latest.pdf-
Advertisement Copy 1File: No Advertisement So Far.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_180924_002015.xlsx-
Occupancy CertificateFile: OC.pdf-
Completion certificate issued by the competent authorityFile: OC.pdf-
Registered Agreement of SaleFile: Saleagreement (1).pdf-
Registered conveyance deed for an individual unitFile: Saleagreement (1).pdf-
InsuranceFile: NYK HDFCERGO.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Metro Urbano on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmMetro UrbanoOther 20Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: NYK Homes

NYK Homes has 1 registration on RERA Karnataka, including Metro Urbano. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Metro Urbano is delayed beyond 30 Sep 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Metro Urbano?

The registered promoter entity is NYK Homes, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Metro Urbano?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Metro Urbano?

The professionals named in the filing: Architect: Aslam Architects (Ani Sambyal Singh); Engineer: Bhaskar Y. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Metro Urbano?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Metro Urbano. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Metro Urbano to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.