Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
MEDA EAST WINDS is a Residential/Group Housing project by MEDA PROJECTS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/261224/007320 on 26 Dec 2024. Possession is promised by 30 Dec 2028. 247 of the 542 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete.
At a glance
Project
- NameMEDA EAST WINDS
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/446/PR/261224/007320
- ReraGenie IDRG-KA-51653
Builder
- NameMEDA PROJECTS
- Entity typeProprietorship
- GSTIN29ABRFM9235F1ZO
- Authorized SignatoryMEDA ROHIT REDDY
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on26 Dec 2024
- Promised completion30 Dec 2028
- Revised completionNone
- Buildings11 building records
- Documents filed167 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TOWER 1 | - | - | - | 44 | 0 | 44 |
| TOWER 2 | - | - | - | 44 | 0 | 44 |
| TOWER 3 | - | - | - | 44 | 0 | 44 |
| TOWER 4 | - | - | - | 44 | 0 | 44 |
| TOWER 5 | - | - | - | 44 | 0 | 44 |
| TOWER 6 | - | - | - | 50 | 0 | 50 |
| TOWER 7 | - | - | - | 70 | 0 | 70 |
| TOWER 8 | - | - | - | 70 | 0 | 70 |
| TOWER 9 | - | - | - | 44 | 0 | 44 |
| TOWER 10 | - | - | - | 44 | 0 | 44 |
| TOWER 11 | - | - | - | 44 | 0 | 44 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 18 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 90%.
Building: 39% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 90% |
| Foundation footing work | 90% |
| Upto Plinth Level | 90% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 70% |
| Retaining wall (All types) | 90% |
| RCC or MS Framed structure | 70% |
| Masonry Construction | 65% |
| Plastering inside , outside & Ceiling | 65% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 20% |
| Painting | 10% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | 10% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 20% |
| Internal and External work including landscapes as per sanctioned drawings | 20% |
Progress on shared amenities40
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | Yes | 20% |
| Community Hall | Yes | 20% |
| Outdoor Sports facility | Yes | 0% |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 70% |
| Lifts | Yes | 70% |
| Corridor/Lobbies | Yes | 50% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 40% |
| Basement | Yes | 80% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 40% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | Yes | 40% |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership6
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MEDA PROJECTS REP. bY ITS PARTNER Mr. Meda Sai Krishna Reddy | - | - |
| MEDA PROJECTS REP. bY ITS PARTNER Mr. Meda Sai Krishna Reddy | - | - |
| MEDA PROJECTS REP. bY ITS PARTNER Mr. Meda Sai Krishna Reddy | - | - |
| MEDA PROJECTS REP. bY ITS PARTNER Mr. Meda Sai Krishna Reddy | - | - |
| MEDA PROJECTS REP. bY ITS PARTNER Mr. Meda Sai Krishna Reddy | - | - |
| MEDA PROJECTS REP. bY ITS PARTNER Mr. Meda Sai Krishna Reddy | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 339.87 cr | Rs 170.29 cr |
| ADMINISTRATIVE COST | Rs 55.28 cr | - |
| On-site expenditure-Consultants Fees | Rs 2.06 cr | Rs 7.13 cr |
| Plan Approval | Rs 83.90 lakh | - |
| BETTERMENT CHARGES | Rs 82.74 lakh | - |
| DEVELOPMANT PLAN | Rs 61.82 lakh | - |
| Water / bwssb | Rs 52.14 lakh | - |
| Fire NOC | Rs 47.72 lakh | - |
| property Taxees | Rs 44.88 lakh | - |
| Katha | Rs 35.90 lakh | - |
| WELFARE BOARD | Rs 25.00 lakh | - |
| OTHER | Rs 11.12 lakh | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mr. Yash Dayama |
| Engineer | Mr. KAMI REDDY SURESH REDDY |
| Chartered Accountant | Mr. K Ravi Kumar |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed167
As listed on the registration, under the names the promoter filed them with; the newest 80 of 167 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/261224/007320 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4_CA_Q2_2026-2027_Signed.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5, Architect (Q2 2026-2027).pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: MEDA ENGINEERS CERTIFICATE.PDF | 15 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 15 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 15 Oct 2026 |
| Q2 2026-27 Fire and Safety | 15 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 15 Oct 2026 |
| Q2 2026-27 BSNL/Telecommunication Department | 15 Oct 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA.pdf | 15 Jul 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: ARCH.pdf | 15 Jul 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: EN.pdf | 15 Jul 2026 |
| Q4 2025-26 Water supply and sewage board | 15 Jul 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q4 2025-26 KPTCL- BESCOM | 15 Jul 2026 |
| Q4 2025-26 Fire and Safety | 15 Jul 2026 |
| Q4 2025-26 Airport Authority of India | 15 Jul 2026 |
| Q4 2025-26 BSNL/Telecommunication Department | 15 Jul 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Form 4_Q1_2026-2027_compressed.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: BALCONY AREA SRI SAI SAMRUDDHI itangur.xlsx | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, (Q1 2026-2027 ) sent to Engg.PDF | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| Q1 2026-27 Fire and Safety | 15 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 15 Jul 2026 |
| Q1 2026-27 BSNL/Telecommunication Department | 15 Jul 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Q3.pdf | 1 Feb 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Q3.pdf | 1 Feb 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: ENGINEER Q3 (1) (1).PDF | 1 Feb 2026 |
| Q3 2025-26 Water supply and sewage board | 1 Feb 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 1 Feb 2026 |
| Q3 2025-26 KPTCL- BESCOM | 1 Feb 2026 |
| Q3 2025-26 Fire and Safety | 1 Feb 2026 |
| Q3 2025-26 Airport Authority of India | 1 Feb 2026 |
| Q3 2025-26 BSNL/Telecommunication Department | 1 Feb 2026 |
| net-worth details and capital contribution details form -01 CA certificateFile: CA Cost Estimation Cetificate.pdf | 2 Nov 2024 |
| sources of fundFile: affidavit 2.pdf | 2 Nov 2024 |
| Proprietorship registration certificateFile: Meda Properties Partnership Deed.pdf | 2 Nov 2024 |
| GST registration certificateFile: COMPANY GST - CERTIFICATEAA2907220574334_RC29072022.pdf | 2 Nov 2024 |
| Bank AffidavitFile: Bank Affidavite_page-0001.pdf | 2 Nov 2024 |
| CA CERTIFICATE ON FY QUEIRSFile: CA CERTIFICATE FOR FY 2024 FILLING.pdf | 2 Nov 2024 |
| ITR FOR FY 2023-24File: ITR5 for Fy2324.pdf | 2 Nov 2024 |
| ITR FOR 2024-25File: ITR 2022-23.pdf | 2 Nov 2024 |
| Non litigation AffidavitFile: Non Litigation Certification.pdf | 2 Nov 2024 |
| self attested copy of the Engineer license certificateFile: LICENSE.PDF | 2 Nov 2024 |
| cost details - Engineer certificateFile: CERTIFICATE BY Cost Estimation.PDF | 2 Nov 2024 |
| original copy of the Form-6, Engineer certificateFile: FORM-6.PDF | 2 Nov 2024 |
| Annexure-A and upload the proforma of the Allotment letter.File: Allotment Letter anex.pdf | 2 Nov 2024 |
| proforma of Agreement for SaleFile: AGREEMENT FOR SALE.pdf | 2 Nov 2024 |
| ITR FOR FY 2023-24File: fy 23-24.pdf | 2 Nov 2024 |
| capital contribution details form -01 CA certificateFile: capital contribution details form -01 CA certificate.pdf | 24 Oct 2024 |
| Proprietorship registration certificateFile: Meda Properties Partnership Deed.pdf | 24 Oct 2024 |
| GST registration certificateFile: COMPANY GST - CERTIFICATEAA2907220574334_RC29072022.pdf | 24 Oct 2024 |
| Bank AffidaviteFile: Bank Affidavite.pdf | 24 Oct 2024 |
| Assessment Year 2024-25File: ITR5 for Fy2324.pdf | 24 Oct 2024 |
| Assessment Year 2022-23File: fy2223.jpeg | 24 Oct 2024 |
| Assessment Year 2023-24File: fy 2324.jpeg | 24 Oct 2024 |
| Notarized Non litigation AffidavitFile: Non Litigation Certification.pdf | 24 Oct 2024 |
| self attested copy of the BBMP Engineer license certificateFile: LICENSE.PDF | 24 Oct 2024 |
| cost details Engineer certificate.File: CERTIFICATE BY Cost Estimation.PDF | 24 Oct 2024 |
| Allotment letterFile: Allotment Letter_merged.pdf | 24 Oct 2024 |
| SALE AGREEMENTFile: MEDA EAST WINDS AGREEMENT FOR SALE formatted .pdf | 24 Oct 2024 |
| CA CERTIFICATE MEDA PROJECTSFile: CA CERTIFICATE MEDA PROJECTS.pdf | 30 Sep 2024 |
| COMPANY GST - CERTIFICATEFile: COMPANY GST - CERTIFICATEAA2907220574334_RC29072022.pdf | 30 Sep 2024 |
| Meda Properties Partnership DeedFile: Meda Properties Partnership Deed.pdf | 30 Sep 2024 |
| POINT nO. 6 CA CERTIFICATEFile: POINT NO 6 CA CERTIFICATE.pdf | 30 Sep 2024 |
| affidavit 3File: affidavit 3.pdf | 30 Sep 2024 |
| Title deed 12.1 saledeedFile: 121 saledeed.pdf | 30 Sep 2024 |
| Title deed SALES DEEDFile: 153 sale deed.pdf | 30 Sep 2024 |
| EC from 01.04.2008 to 31.03.2022File: BANK AFFIDAVIT.pdf | 30 Sep 2024 |
| Building licenceFile: Building licence.pdf | 30 Sep 2024 |
| Ec 12.1 12.2 12.3 01.04.2008 to 31.03.2022File: Ec 121 122 123.pdf | 30 Sep 2024 |
| Ec 15/2, 15/3 01.04.2008 to 31.03.2022File: Ec 152 153.pdf | 30 Sep 2024 |
| AFFIDAVITEFile: AFFIDAVITE.pdf | 30 Sep 2024 |
| GUIDLINE VALUEFile: GUIDLINE VALUE.pdf | 30 Sep 2024 |
| SALE AGREEMENT FORMATFile: Meda East Winds Agreement.pdf | 30 Sep 2024 |
| BECOSM NOCFile: BESCOM NOC.pdf | 30 Sep 2024 |
| BESCOM PAID RECEIPTFile: BESCOM PAID RECEIPT.pdf | 30 Sep 2024 |
| BWSSB NOCFile: BWSSB NOC.pdf | 30 Sep 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep MEDA EAST WINDS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: MEDA PROJECTS
MEDA PROJECTS has 1 registration on RERA Karnataka, including MEDA EAST WINDS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if MEDA EAST WINDS is delayed beyond 30 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of MEDA EAST WINDS?
The registered promoter entity is MEDA PROJECTS, a proprietorship as per the filing. Its GSTIN 29ABRFM9235F1ZO can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in MEDA EAST WINDS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at MEDA EAST WINDS?
The professionals named in the filing: Architect: Mr. Yash Dayama; Engineer: Mr. KAMI REDDY SURESH REDDY; Chartered Accountant: Mr. K Ravi Kumar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MEDA EAST WINDS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback