ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Mantri Tranquil

Registration approved Residential/Group Housing project

Mantri Tranquil

By Propcare Developers Private Limited

RG-KA-42872 · RERA PRM/KA/RERA/1251/310/PR/190711/002659

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Apr 2025Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 51 documents Report an error

Mantri Tranquil is a Residential/Group Housing project by Propcare Developers Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/190711/002659 on 11 Jul 2019. Possession is promised by 30 Apr 2025. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameMantri Tranquil
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/190711/002659
  • ReraGenie IDRG-KA-42872

Builder

  • NamePropcare Developers Private Limited
  • Entity typeCompany
  • CINU70102KA1990PTC027924
  • Authorized SignatoryGirish Gupta HS
  • DirectorsSUSHIL PANDURANG MANTRI, Pratik Mantri
  • Other registrations6 more →
  • Declared earlier projects8 →

Key dates

this monthRegisteredJul 2019First promiseJul 2024Revised toApr 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on11 Jul 2019
  • Promised completion30 Apr 2025
  • Revised completionRevised to 30 Apr 2025 (originally 31 Jul 2024)
  • Buildings1 building record
  • Documents filed51 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block L---1040104

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationYes-
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionYes-
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area829 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 71.31 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM/s RSP Design Consultants (I) Private Limited
EngineerM/s Novel-S Design Matrix Private Limited (Earlier M/s Novel Engineering Consultants Private Limited)

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJul 2024 → Apr 2025

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed51

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/190711/002659 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Incorporation Certificate.pdf-
CC-
SITE PLAN-
ALL FLOOR PLANS-
Proforma of Sale Deed-
Proforma of Agreement of Sale-
Sale Deed RTC-
SECTION and ELEVATION-
CDP L Site bounday superimposed-
Tranquil3 Allotment Letter-
MDPL-
ALL NOCs-
Tranquil3 RERA Specifications-
EC up to 12 years-
sec 3(1) affidavit for Tranquil-
RTC KHATHA-
RTC TIPPANY AKARABAND-
Relinquishment Deed-
CONVERSION ORDER-
Relinquishment Deed-
Modified FIRE and Emeregency NOC-
AAI NOC-
BESCOM NOC-
BWSSB-
MOEF SEIAA NOC-
BSNL-
Unnamed document-
Site Plan-
Section & Elevation-
Tranquil Conversion Order for 12 50 Guntas Dtd 31032005-
Legal Reports-
Balance Sheet 2017 - 2018File: Balansheet 2017 18.pdf-
Balance Sheet 2016 - 2017File: Balansheet 2016 17.pdf-
Balance Sheet 2015 - 2016File: Balansheet 2015 16.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Profit Loss 2017 18.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Profit Loss 2016 17.pdf-
Audited Profit and Loss Statement 2015 - 2016File: PL 2015 16.pdf-
Director's Report 2017 - 2018File: Not yet prepared direct reports for 2017.pdf-
Director's Report 2016 - 2017File: Director Repots 2016 17.pdf-
Director's Report 2015 - 2016File: Directors Reports 2015 16.pdf-
Cash Flow Statement 2017 - 2018File: Cashflow statement 2017 18.pdf-
Cash Flow Statement 2016 - 2017File: Cashflow Statement 2016 17.pdf-
Auditor's Report 2017 - 2018File: Auditor Reports 2017 18.pdf-
Auditor's Report 2016 - 2017File: Auditor Reports 2016 17.pdf-
Auditor's Report 2015 - 2016File: Auditor Reports 2015 16.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: ITR 2017 18.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITRV AY17.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR 2015 16.pdf-
FORM B AFFIDAVIT-
Prospectus/BrochureFile: Broucher.jpg-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_190711_002659.xlsx-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Mantri Tranquil on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Propcare Developers Private Limited

Propcare Developers Private Limited has 7 registrations on RERA Karnataka, including Mantri Centrium and Mantri Webcity3C. Its filings declare 8 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Mantri Tranquil is delayed beyond 30 Apr 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Mantri Tranquil?

The registered promoter entity is Propcare Developers Private Limited, a company as per the filing. Its CIN U70102KA1990PTC027924 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Mantri Tranquil?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Mantri Tranquil?

The professionals named in the filing: Architect: M/s RSP Design Consultants (I) Private Limited; Engineer: M/s Novel-S Design Matrix Private Limited (Earlier M/s Novel Engineering Consultants Private Limited). Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mantri Tranquil?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mantri Tranquil. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mantri Tranquil to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.