ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Mantri Serenity3

Registration approved Residential/Group Housing project

Mantri Serenity3

By CASTLES VISTA PRIVATE LIMITED

RG-KA-14592 · RERA PRM/KA/RERA/1251/310/PR/171016/000500 · Last updated on RERA Karnataka portal: 7 Mar 2022

Source: official RERA Karnataka filing

Red flags

  • 11 complaints at RERA Karnataka
  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • Separate project account declared
Sep 2022Possession promisedmoved 21 months from the original
11Complaints at RERA Karnatakaon this registration
Jump to the 93 documents Report an error

Mantri Serenity3 is a Residential/Group Housing project by CASTLES VISTA PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/171016/000500 on 16 Oct 2017. Possession is promised by 29 Sep 2022. The completion date has moved by 21 months from the original filing. 11 complaints are on record with the regulator.

At a glance

Project

  • NameMantri Serenity3
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/171016/000500
  • ReraGenie IDRG-KA-14592

Builder

  • NameCASTLES VISTA PRIVATE LIMITED
  • Entity typeCompany
  • Authorized SignatoryGirish Gupta HS
  • Other registrations3 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredOct 2017First promiseDec 2020Revised toSep 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 Oct 2017
  • Promised completion29 Sep 2022
  • Revised completionRevised to 29 Sep 2022 (originally 29 Dec 2020)
  • Buildings4 building records
  • Documents filed93 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
E---96096
F---96096
G---96096
H---96096

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 7 Mar 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 7 Mar 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area79,287 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 151.27 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAshok Design Build Pvt Ltd.,
EngineerNAGESH CONSULTANTS

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2020 → Sep 2021

No reason recorded in the filing

EX/PRM/KA/RERA/1251/310/PR/230515/000500Sep 2021 → Sep 2022

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka11

Case no.ComplainantRespondentFiled
CMP/190327/0002525-Mantri Castles Pvt Ltd27/03/2019
CMP/200924/0006607-Mantri Castles Pvt Ltd24/09/2020
CMP/200927/0006666-Mantri Castles Pvt Ltd27/09/2020
CMP/201013/0006791-Mantri Castles Pvt Ltd13/10/2020
CMP/201022/0006736-Mantri Castles Pvt Ltd22/10/2020
CMP/201112/0007052-Mantri Castles Pvt Ltd12/11/2020
CMP/201112/0007053-Mantri Castles Pvt Ltd12/11/2020
CMP/210107/0007403-Mantri Castles Pvt Ltd07/01/2021
CMP/220905/0009978-Mantri Castles Pvt Ltd05/09/2022
01106/2023-Mantri Castles Pvt Ltd17/07/2023
00239/2024-Mantri Castles Pvt Ltd28/02/2024

Documents filed93

As listed on the registration, under the names the promoter filed them with; the newest 80 of 93 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/171016/000500 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
NOC AAIFile: AAI NOC.pdf7 Mar 2022
BESCOM NOCFile: BESCOM NOC.pdf7 Mar 2022
BSNL NOCFile: BSNL NOC.pdf7 Mar 2022
BWSSB NOCFile: BWSSB NOC.pdf7 Mar 2022
FIRE NOCFile: Fire NOC.pdf7 Mar 2022
KSPCB NOCFile: Serenity KSPCB.pdf7 Mar 2022
AFFIDAVIT SEEKING EXTENSIONFile: 1 AFFIDAVIT SEEKING EXTENSION.pdf7 Mar 2022
COMMENCEMENT CERTIFICATEFile: 4 Commencement Cert.pdf7 Mar 2022
PROJECT MEMBER DETAILSFile: 5 Project Member details.pdf7 Mar 2022
DEVELOPMENT WORK DETAILSFile: 6 Development work details.pdf7 Mar 2022
ALLOTMENT LETTERFile: 7 Application of Allotment.pdf7 Mar 2022
E BROCHUREFile: 8 Serenity ebrochure.pdf7 Mar 2022
FIRST FLOOR PLANFile: FIRST FLOOR PLAN TOWER 3.pdf7 Mar 2022
GROUND FLOOR PLANFile: GROUND FLOOR PLAN TOWER 3.pdf7 Mar 2022
SECTION PLANFile: SECTION A A ELEVATION 1 TOWER 3.pdf7 Mar 2022
TERRACE FLOOR PLANFile: TERRACE FLOOR PLAN TOWER 3.pdf7 Mar 2022
REPLY TO QUERYFile: REPLY TO QUERY.pdf10 Jan 2022
CertificateFile: COI_Castles.pdf-
Architect Certificate for Work Completion Schedule till DateFile: WORK COMPLETED ARCHITECT CERT SERENITY 3.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: WORK COMPLETED ENGINEER SERENITY 3.pdf-
CA Certificate for Funds UtilizationFile: CA FUND UTILISED.pdf-
Architect Certificate for Pending Work Completion Schedule.File: WORK PENDING ARCHITECT CERT SERENITY 3.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: WORK PENDING ENGINEER SERENITY 3.pdf-
CA Certificate for Funds required for Project CompletionFile: CA FUNDS REQUIRED.pdf-
AffidavitFile: AFFIDAVIT SEEKING EXTENSION.pdf-
Latest Encumbrance CertificateFile: EC.pdf-
Details Of Sold/ Un-sold UnitsFile: BWSSB NOC.pdf-
NOC DetailsFile: Mantri Serenity AAI NOC dated on 22 02 2021.pdf-
Document 1File: EC1 1-300 PAGES.pdf-
Document 2File: EC2 SERENITY 1-301-400.pdf-
Document 3File: EC3 SERENITY 1-401-527.pdf-
Document 4File: AFFIDAVIT CONSENT LETTERS SERENITY 3.pdf-
Document 5File: FORM B.pdf-
Document 6File: BANK STATEMENT SERENITY 3.pdf-
Commencement Certificate 150911-
Approved Building Plan-
Approved Layout Plan-
Customer Sale Deed-
Construction Agreement-
Serenity 3 RTCs-
Approved Section of Building-
Approved Layout Plan-
Letter of Allotment - Mantri Castles-
MCPL-
All NOCs from Authority-
Specifications and Amenities - Serenity-
Tower 3 Commencement Certificate 150911-
Serenity 3 - Khata Extract-
Serenity 3 JDA and GPA-
Any other document-
Conversion Certificate-
Section 14 of KTCP ACT-
Utilization Certificaate NA-
TDR NA-
Reliquinshment Deed NA-
Revised Fire NOC-281112-
AAI 051113-
BESCOM -070709-
BWSSB 121109-
KSPCB (CFE) dtd-170113-
Modified MOEF -220613-
BSNL - Serenity-
Noc in case of building proposals abutting to neighbouring properties-
Unnamed document-
Urban Land Ceiling-
BMRCL-
Bangalore Urban Arts Commission-
Inspector of Factories Controller of explosives-
Dist Magistrate-
Coastal Regulation Zone Authority-
Certificate from Registered Engineer-
Approved Section of Building-
Balance Sheet 2015 - 2016File: Mantri Castles- 2016-BS.pdf-
Balance Sheet 2014 - 2015File: Mantri castles- 2015-BS.pdf-
Balance Sheet 2013 - 2014File: Mantri Castles-Bal-2014-BS.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Mantri Castles- 2016-P&L.pdf-
Audited Profit and Loss Statement 2014 - 2015File: Mantri castles- 2015-PL.pdf-
Audited Profit and Loss Statement 2013 - 2014File: Mantri Castles-Bal-2014-PL.pdf-
Director's Report 2015 - 2016File: Mantri Castles- 2016-DR.pdf-
Director's Report 2014 - 2015File: Mantri castles- 2015-DR.pdf-

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
Mantri Serenity5-OngoingJul 2017Not delivered
Mantri Serenity4-OngoingJul 2017Not delivered
Mantri Serenity1-OngoingJul 2017Not delivered

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 21 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Mantri Serenity3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: CASTLES VISTA PRIVATE LIMITED

CASTLES VISTA PRIVATE LIMITED has 4 registrations on RERA Karnataka, including Mantri Serenity3 and Mantri Serenity4. Its filings declare 4 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Mantri Serenity3 is delayed beyond 29 Sep 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Mantri Serenity3?

The registered promoter entity is CASTLES VISTA PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Mantri Serenity3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Mantri Serenity3?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Mantri Serenity3?

The professionals named in the filing: Architect: Ashok Design Build Pvt Ltd.,; Engineer: NAGESH CONSULTANTS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mantri Serenity3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mantri Serenity3. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mantri Serenity3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.