Red flags

  • 10 complaints at RERA Karnataka
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • Separate project account declared
Apr 2022Possession promisedmoved 9 months from the original
10Complaints at RERA Karnatakaon this registration
Jump to the 43 documents Report an error

Mantri Centrium is a Residential/Group Housing project by Propcare Developers Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/171016/000485 on 16 Oct 2017. Possession is promised by 1 Apr 2022. The completion date has moved by 9 months from the original filing. 10 complaints are on record with the regulator.

At a glance

Project

  • NameMantri Centrium
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/309/PR/171016/000485
  • ReraGenie IDRG-KA-27255

Builder

  • NamePropcare Developers Private Limited
  • Entity typeCompany
  • CINU70102KA1990PTC027924
  • Authorized SignatoryGirish Gupta HS
  • Other registrations6 more →
  • Declared earlier projects8 →

Key dates

this monthRegisteredOct 2017First promiseJul 2021Revised toApr 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 Oct 2017
  • Promised completion1 Apr 2022
  • Revised completionRevised to 1 Apr 2022 (originally 1 Jul 2021)
  • Buildings2 building records
  • Documents filed43 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---89089
B---89089

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationYes-
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionYes-
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,694 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 474.43 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSpace Matrix Design Consultants Pvt Ltd
EngineerSterling Engineering Consultancy Services Private

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJul 2021 → Apr 2022

No reason recorded in the filing

Complaints filed with RERA Karnataka10

Case no.ComplainantRespondentFiled
CMP/210615/0007998-Mantri Developers Private Limited15/06/2021
CMP/210630/0008079-Mantri Developers Private Limited30/06/2021
CMP/210717/0008139-Mantri Developers Private Limited17/07/2021
CMP/210720/0008145-Mantri Developers Private Limited20/07/2021
CMP/220408/0009331-Mantri Developers Private Limited08/04/2022
CMP/220408/0009332-Mantri Developers Private Limited08/04/2022
CMP/221226/0010534-Mantri Developers Private Limited26/12/2022
CMP/221226/0010535-Mantri Developers Private Limited26/12/2022
00823/2023-Mantri Developers Private Limited25/05/2023
00261/2024-Mantri Developers Private Limited11/03/2024

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/171016/000485 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: COI_MDPL.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Centrium BBMP Sanction Licence-
SITE PLAN-
SITE PLAN-
Centrium - Sale Deed Draft-
Centrium -Agreement of Construction-
Centrium -Agreement to Sell dated 18 03 13 - Part1-
SECTION-
SITE PLAN-
Centrium - Allotment Letter-
MDPL-
MOEF -050513-
Specifications and Amenities - Centrium-
Centrium - EC-
Title Report-
Fire NOC-100511-
AAI- 2015-
BESCOM- 050304-
BWSSB 090204-
KSPCB -160613-
MOEF -050513-
Balance Sheet 2015 - 2016File: MDPL March 2016-BS.pdf-
Balance Sheet 2014 - 2015File: MDPL_2015-BS.pdf-
Balance Sheet 2013 - 2014File: MDPL_financials_FY14-BS.pdf-
Audited Profit and Loss Statement 2015 - 2016File: MDPL March 2016-P&L.pdf-
Audited Profit and Loss Statement 2014 - 2015File: MDPL_2015-PL.pdf-
Audited Profit and Loss Statement 2013 - 2014File: MDPL_financials_FY14-PL.pdf-
Director's Report 2015 - 2016File: MDPL-March 2016-DR (2).pdf-
Director's Report 2014 - 2015File: MDPL_2015-DR.pdf-
Director's Report 2013 - 2014File: MDPL_financials_FY14-DR.pdf-
Cash Flow Statement 2015 - 2016File: MDPL March 2016-Cashflow statement.pdf-
Cash Flow Statement 2014 - 2015File: MDPL_2015-CFS.pdf-
Auditor's Report 2015 - 2016File: MDPL March 2016-Auditor report.pdf-
Auditor's Report 2014 - 2015File: MDPL_2015-AR.pdf-
Auditor's Report 2013 - 2014File: MDPL_financials_FY14-AR.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITRV-AY-2014-15.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITRV-AY-2015-16.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: ITRV-AY-2016-17.pdf-
Mantri Centrium - Form B-
Prospectus/BrochureFile: centrium-brochure.pdf-
Advertisement Copy 1File: Mantri Home Rush - Hindu Jacket copy.pdf-
Tower Excel SheetFile: 1-PRM_KA_RERA_1251_309_PR_171016_000485-Mantri Centrium.xlsx-

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

5 not delivered by the promised date1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Mantri Webcity3C-OngoingJul 2017Not delivered
Mantri Webcity3B-OngoingJul 2017Not delivered
Mantri Webcity3A-OngoingJul 2017Not delivered
Mantri Webcity2B-OngoingJul 2017Not delivered
Mantri Webcity2A-OngoingJul 2017Not delivered
Mantri Webcity1-CompletedJul 2017No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Mantri Centrium on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Propcare Developers Private Limited

Propcare Developers Private Limited has 7 registrations on RERA Karnataka, including Mantri Centrium and Mantri Webcity3C. Its filings declare 8 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Mantri Centrium is delayed beyond 1 Apr 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Mantri Centrium?

The registered promoter entity is Propcare Developers Private Limited, a company as per the filing. Its CIN U70102KA1990PTC027924 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Mantri Centrium?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Mantri Centrium?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Mantri Centrium?

The professionals named in the filing: Architect: Space Matrix Design Consultants Pvt Ltd; Engineer: Sterling Engineering Consultancy Services Private. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mantri Centrium?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mantri Centrium. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mantri Centrium to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.