Home / Browse projects / Bengaluru Urban, Karnataka / Mana Capitol Tower 3,4 & 5

Registration approved No litigation declared Mixed Development project

Mana Capitol Tower 3,4 & 5

By D Kishore Reddy

RG-KA-27161 · RERA PRM/KA/RERA/1251/446/PR/200113/003154 · Last updated on RERA Karnataka portal: 15 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Mar 2027Possession promisedmoved 9 months from the original
9 of 17Construction stages donefurthest along: Basic work of Water supply, 98%
96 of 407Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 89 documents Report an error

Mana Capitol Tower 3,4 & 5 is a Mixed Development project by D Kishore Reddy in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/200113/003154 on 13 Jan 2020. Possession is promised by 30 Mar 2027. The completion date has moved by 9 months from the original filing. 311 of the 407 units on this registration are recorded sold or booked, and 9 of 17 construction stages are filed complete.

At a glance

Project

  • NameMana Capitol Tower 3,4 & 5
  • TypeMixed Development
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/200113/003154
  • ReraGenie IDRG-KA-27161

Builder

  • NameD Kishore Reddy
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredJan 2020First promiseJun 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on13 Jan 2020
  • Promised completion30 Mar 2027
  • Revised completionRevised to 30 Mar 2027 (originally 30 Jun 2026)
  • Buildings3 building records
  • Documents filed89 files

Current status

76%311 of 407 units booked
2.4%Of the estimated cost spent so far

Figures as on 15 Jul 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 3---1420142
Tower 4---1420142
Tower 5---1230123

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 17 construction stages are filed complete. The stage furthest along is Basic work of Water supply, at 98%.

Building: 99% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification98%
Dadoing, Skirting, Flooring, Tiles work (All types)98%
Railing and Grill fixing98%
Electrification, Water supply and Sanitary Finishing98%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)98%
Painting98%
Elevation work98%
Internal and External work including landscapes as per santioned drawings98%

Progress on shared amenities41

As on 15 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsYes98%
Sewage and Drainage SystemYes98%
Parks & Tree plantingYes95%
Street LightingYes95%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes95%
Solid waste management and disposalYes98%
Water conservationYes98%
Energy managementYes-
Fire protection and fire safety requirementsYes100%
Education/Health/Other public amenitiesYes90%
Electricity supply transformer and substationYes100%
Emergency Evacuation servicesYes100%
Storm water drainsYes98%
Use of renewable energyYes98%
Water conservation/rain water harvesting/recharge of ground waterYes98%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseYes95%
Community HallNoNot applicable
Outdoor Sports facilityYes95%
Indoor Sports facilityYes95%
Swimming PoolYes95%
GymYes95%
ParksYes95%
Power BackupYes95%
GasNoNot applicable
Water and SanitationYes100%
Air Conditioning And incerntionNoNot applicable
StaircasesYes98%
LiftsYes100%
Staircases and Lift lobbies, corridor,lobbies, corridorYes98%
Fire escapesYes100%
Common entrance and exit for the building / common portico/foyer/verandahYes98%
BasementYes98%
TerraceYes98%
Outer WallYes98%
Open parking areas and common storage spacesYes98%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,534 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 211.50 cr
Cost incurredRs 5.12 cr
Spent of the estimate2.42%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 202.00 crRs 5.12 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 3.50 cr-
On-site expenditure-Site OverheadRs 2.00 cr-
On-site expenditure-Salaries of workersRs 1.50 cr-
On-site expenditure-Consultants FeesRs 1.50 cr-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 1.00 cr-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectT. GNANVEL
EngineerAMBRISH G

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJun 2026 → not stated

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed89

As listed on the registration, under the names the promoter filed them with; the newest 80 of 89 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/200113/003154 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4 C A MC TOWER 3, 4 & 5 (QU) 31-03-2026.pdf15 Jul 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form -5 Archt MC TOWER 3,4 & 5 (QU) 31-03-2026_Final.pdf15 Jul 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engi MC TOWER 3,4 & 5 (QU) 31-03-2026.pdf15 Jul 2026
Q4 2025-26 Water supply and sewage board15 Jul 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q4 2025-26 KPTCL- BESCOM15 Jul 2026
Q4 2025-26 Fire and Safety15 Jul 2026
Q4 2025-26 Airport Authority of India15 Jul 2026
Q4 2025-26 BSNL/Telecommunication Department15 Jul 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4 C A MC TOWER 3, 4 & 5 (QU) 31-12-2025.pdf19 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form -5 Archt MC TOWER 3,4 & 5 (QU) 31-12-2025.pdf19 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engi MC TOWER 3,4 & 5 (QU) 31-12-2025.pdf19 Feb 2026
Q3 2025-26 Water supply and sewage board19 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)19 Feb 2026
Q3 2025-26 KPTCL- BESCOM19 Feb 2026
Q3 2025-26 Fire and Safety19 Feb 2026
Q3 2025-26 Airport Authority of India19 Feb 2026
Q3 2025-26 BSNL/Telecommunication Department19 Feb 2026
Flat Details of all towersFile: ALL FLAT DETAIL 580.pdf4 Jan 2020
Joint Affidavit cum declarationFile: DECLARATION & AFFIDAVIT.pdf4 Jan 2020
RELINQUISHMENT DEEDFile: Relinquishment Deed.pdf4 Jan 2020
Earmarked Towers on approved planFile: PLAN MARKING TOWER.pdf4 Jan 2020
Company Registration CertificateFile: Certificate of Incoroporation-LLP.pdf4 Jan 2020
Already registered project ongoing detailsFile: Mana Capitol - RERA R C Tower 1 & 2.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: Site Plan.pdf-
Elevation, Sections, Specifications ( If changes are there )File: Elevation Floor Plan.pdf-
List Of AllotteesFile: List of Allottes.pdf-
Consent LetterFile: Consent letter - Scanned_compressed.pdf-
Chartered Accountant CertificateFile: Form -4 C A MC TOWER 3, 4 & 5 (MODFIED PLAN).pdf-
Notarized AffidavitFile: Affidavit cum Declaration - CAPITOL.pdf-
Engineer CertificateFile: Form -6 Engi MC TOWER 3,4 & 5 (MODIFIED PLAN).pdf-
Architect CertificateFile: Form -5 Archt MC TOWER 3,4 & 5 (MODIFIED PLAN).pdf-
Structural Engineer Certificate for stability of structureFile: Form -6 Engi MC TOWER 3,4 & 5 (MODIFIED PLAN).pdf-
Modification of Plan DetailsFile: Site Plan.pdf-
Modification of Plan DetailsFile: Site Plan.pdf-
Modification of Plan DetailsFile: Commencement certificate.pdf-
Modification of Plan DetailsFile: Commencement certificate.pdf-
Modification of Plan DetailsFile: List of Sold & Unsold Existing Plan.pdf-
Modification of Plan DetailsFile: List of Sold & Unsold Modified Plan.pdf-
BDA Approval Letter-
APPROVED PLANS-
sale deed-
sale agreement-
RTC-
Section and Elevation-
DP-
Allotment letter-
Brouchre1-
Specifications-
EC-
Affidavite-
Affidavite Cum Delaration-
E KHATHA-
JDA-
SALE DEEDS-
Unnamed document-
PTCL 3 IN ONE-
Unnamed document-
Unnamed document-
Unnamed document-
FIRE NOC-
AIRPORT NOC (2)-
Bescom NOC-
Unnamed document-
KSPCB CFE_Mana-
SEIAA-
BSNL NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Layout approved-
Section and Elevation-
CONVERSION-

How this compares with Bengaluru Urban

76%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Mana Capitol Tower 3,4 & 5 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmMana Capitol Tower 3,4 &Other 66Dot size: filed unitsN

Filed coordinates, straight-line distance. 66 registered projects within 2 km.

Builder: D Kishore Reddy

D kishore reddy has 2 registrations on RERA Karnataka, including Mana Capitol Tower 1 & 2 and Mana Capitol Tower 3,4 & 5. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Mana Capitol Tower 3,4 & 5 is delayed beyond 30 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Mana Capitol Tower 3,4 & 5?

The registered promoter entity is D Kishore Reddy. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Mana Capitol Tower 3,4 & 5?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Mana Capitol Tower 3,4 & 5?

The professionals named in the filing: Architect: T. GNANVEL; Engineer: AMBRISH G. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mana Capitol Tower 3,4 & 5?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mana Capitol Tower 3,4 & 5. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mana Capitol Tower 3,4 & 5 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.