MALHAR RESIDENCY
RG-MH-16929 · RERA P53100028160 · Last updated on MahaRERA portal: 30 Nov 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 46 months past the filed date
- Completion date moved by 6 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MALHAR RESIDENCY is a Residential / Group Housing project by SAYALI DEVELOPERS in Sangli, Maharashtra, registered with MahaRERA as P53100028160 on 10 Feb 2021. Possession was promised by 31 Dec 2022 and is now 46 months past that date. The completion date has moved by 6 months from the original filing.
At a glance
Project
- NameMALHAR RESIDENCY
- TypeResidential / Group Housing
- Location
- KISAN NAGAR
- Uran Islampur (M Cl)
- Walwa
- Sangli
- 415409
- Pincode415409
- RERA no.P53100028160
- ReraGenie IDRG-MH-16929
Builder
- NameSAYALI DEVELOPERS
- Entity typePartnership
- PartnersSHRINIVAS BHAGWAN ATHAWALE, AMOL APPASO YADAV
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on10 Feb 2021
- Promised completion31 Dec 2022
- Revised completionRevised to 31 Dec 2022 (originally 30 Jun 2022)
- Buildings1 building record
- Documents filed25 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MALHAR RESIDENCY | NA | 2 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
MALHAR RESIDENCY: 64% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 30 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed6
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| PRAVIN TANAJI PATIL | Karve | Sangli |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PARIKSHIT P JOSHI |
| Engineer | AMOL A YADAV |
| Chartered Accountant | AKSHAY JOSHI |
| Chartered Accountant | SHREYAS S SHAH |
| Chartered Accountant | J P N R & ASSO |
| Partner | Role in project |
|---|---|
| SAYALI DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDUE TO COVID 1 ST & 2 ND WAVE LABOUR & MATERIAL IS SHORTAGE & SOME CHANGE IS OUR PLANNING.SO OUR WORK IS SLOWLY PROCESS.SO PLEASE GIVE MI EXTENSION FOR UP TO 31.12.2022
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jan 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jan 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jan 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jan 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 11 Oct 2023
Documents filed25
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: 1 Occupancy Certificate_ Completion Certificate_ Architect's certificate of completion for | 30 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLETION SAYALI.pdf | 11 Oct 2023 |
| Other - LegalFile: Adobe Scan Oct 11, 2023 (3).pdf | 11 Oct 2023 |
| Other - TechnicalFile: COMPLETION CLARIFICATION.pdf | 6 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 21 12 2021.pdf | 4 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 31 12 2022.pdf | 4 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 20 21.pdf | 4 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21 22.pdf | 4 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE 2112.pdf | 14 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE UP 3112.pdf | 14 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE UP 3112.pdf | 14 Feb 2023 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMECMENT.pdf | 5 May 2022 |
| CERSAI detailsFile: CERSAI.pdf | 5 May 2022 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf | 5 May 2022 |
| Declaration in FORM BFile: FORM B PARTNER.pdf | 30 Jan 2021 |
| Layout approvalFile: LAY OUT.pdf | 28 Jan 2021 |
| Building plan approvalFile: SANCTION PLAN.pdf | 28 Jan 2021 |
| PAN CardFile: Sayali Devolper Pan Card.pdf | 28 Jan 2021 |
| Copy of the legal title reportFile: Search Report.pdf | 28 Jan 2021 |
| Details of encumbrancesFile: Encumbrances certificate (1).pdf | 28 Jan 2021 |
| Copy of Layout Approval (in case of layout)File: LAY OUT.pdf | 28 Jan 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: SANCTION PLAN.pdf | 28 Jan 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: PERMISSION.pdf | 28 Jan 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf | 28 Jan 2021 |
| Proforma of Allotment letterFile: DRAFT.pdf | 28 Jan 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sangli
Computed across the 790+ Sangli projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- All 25 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep MALHAR RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KISAN NAGAR790+ in Sangli
SAMRUDDHI RESIDENCY
Shriram Construction
BALAJI HILL CITY B AND C WING
NEW BALAJI DEVELOPERS
VIGHANHARTA COMPLEX
MAHALAXMI CONSTRUCTIONS
GALAXY HEIGHTS
MUNIR MOHAMADHUSEN PATWEKAR
Audumber Residency
Shailesh Prakash Desai
YUSUFIYA DIAMOND TWIN TOWER
MANSOOR SHABBIR MOMIN
See every Sangli project, with the district possession charts
Builder: SAYALI DEVELOPERS
SAYALI DEVELOPERS has 1 registration on MahaRERA, including MALHAR RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sangli district page.
Frequently asked questions
What does it mean that MALHAR RESIDENCY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if MALHAR RESIDENCY is delayed beyond 31 Dec 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MALHAR RESIDENCY?
The registered promoter entity is SAYALI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MALHAR RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for MALHAR RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MALHAR RESIDENCY?
The professionals named in the filing: Architect: PARIKSHIT P JOSHI; Engineer: AMOL A YADAV; Chartered Accountant: AKSHAY JOSHI; Chartered Accountant: SHREYAS S SHAH; Chartered Accountant: J P N R & ASSO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MALHAR RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback