ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / MAHINDRA BLOSSOM

Registration approved No litigation declared Mixed Development project

MAHINDRA BLOSSOM

By MAHINDRA BLOSSOM DEVELOPERS LIMITED

RG-KA-18420 · RERA TOR/PRM/KA/RERA/1251/446/PR/260615/008348 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 17 complaints at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Oct 2030Possession promisedno revision filed
1 of 18Construction stages donefurthest along: Foundation footing work, 75%
190 of 735Units unsoldnot recorded sold or booked
17Complaints at RERA Karnatakaon this registration
Jump to the 110 documents Report an error

MAHINDRA BLOSSOM is a Mixed Development project by MAHINDRA BLOSSOM DEVELOPERS LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as TOR/PRM/KA/RERA/1251/446/PR/260615/008348 on 15 Jun 2026. Possession is promised by 31 Oct 2030. 545 of the 735 units on this registration are recorded sold or booked, and 1 of 18 construction stages are filed complete. 17 complaints are on record with the regulator.

At a glance

Project

  • NameMAHINDRA BLOSSOM
  • TypeMixed Development
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.TOR/PRM/KA/RERA/1251/446/PR/260615/008348
  • ReraGenie IDRG-KA-18420

Builder

  • NameMAHINDRA BLOSSOM DEVELOPERS LIMITED
  • Entity typeCompany
  • CINU41000MH2026PLC464693
  • Authorized SignatoryNandan V Mallya
  • DirectorsMs. Amrita Chowdhury, Mr. Hisashi Yoshimura, Mr. Vimalendra Singh, Mr. Amit Kumar Sinha, Mr. Yoshitsugu Homma, Mr. Vikram Goel

Key dates

this monthRegisteredJun 2026PromisedOct 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Jun 2026
  • Promised completion31 Oct 2030
  • Revised completionNone
  • Buildings7 building records
  • Documents filed110 files

Current status

74%545 of 735 units booked
11.9%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing A---1120112
Wing B---1630163
Wing C---1100110
Wing D---1080108
Wing E---1330133
Wing F---1070107
RETAIL---022

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 18 construction stages are filed complete. The stage furthest along is Foundation footing work, at 75%.

Building: 10% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work75%
Retaining wall (All types)2%
Plinth level Beam0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
RCC or MS Framed structure0%
Masonry construction: Bricks, Concrete blocks etc0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Painting0%
Elevation work0%
Internal and External work including landscapes as per santioned drawings0%

Progress on shared amenities41

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes0%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservationYes0%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes0%
Emergency Evacuation servicesYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
GasYes0%
Water and SanitationYes0%
Air Conditioning And incerntionNoNot applicable
StaircasesYes0%
LiftsYes0%
Staircases and Lift lobbies, corridor,lobbies, corridorYes0%
Fire escapesYes0%
Common entrance and exit for the building / common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallNoNot applicable
Open parking areas and common storage spacesYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area37,911 sq m
Named landowners1
LandownerVillageDistrict
Mahindra Blossom Developers Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 752.35 cr
Cost incurredRs 89.24 cr
Spent of the estimate11.86%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 599.94 crRs 11.46 cr
On-site expenditure-Consultants FeesRs 87.68 crRs 18.60 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 64.73 crRs 20.04 cr
Payment of taxes-Rs 39.14 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSrimathi J Adiga
EngineerB E Pruthviraja

Complaints filed with RERA Karnataka17

Case no.ComplainantRespondentFiled
00830/2026-MAHINDRA BLOSSOM DEVELOPERS LIMITED17/07/2026
00868/2026-MAHINDRA BLOSSOM DEVELOPERS LIMITED27/07/2026
00903/2026-MAHINDRA BLOSSOM DEVELOPERS LIMITED28/07/2026
00914/2026-MAHINDRA BLOSSOM DEVELOPERS LIMITED29/07/2026
00954/2026-MAHINDRA BLOSSOM DEVELOPERS LIMITED04/08/2026
00970/2026-MAHINDRA BLOSSOM DEVELOPERS LIMITED06/08/2026
00974/2026-MAHINDRA BLOSSOM DEVELOPERS LIMITED07/08/2026
00995/2026-MAHINDRA BLOSSOM DEVELOPERS LIMITED12/08/2026
01001/2026-MAHINDRA BLOSSOM DEVELOPERS LIMITED13/08/2026
01007/2026-MAHINDRA BLOSSOM DEVELOPERS LIMITED14/08/2026
01015/2026-MAHINDRA BLOSSOM DEVELOPERS LIMITED18/08/2026
01038/2026-MAHINDRA BLOSSOM DEVELOPERS LIMITED24/08/2026
01054/2026-MAHINDRA BLOSSOM DEVELOPERS LIMITED25/08/2026
01086/2026-MAHINDRA BLOSSOM DEVELOPERS LIMITED01/09/2026
01100/2026-MAHINDRA BLOSSOM DEVELOPERS LIMITED03/09/2026
01204/2026-MAHINDRA BLOSSOM DEVELOPERS LIMITED07/10/2026
01231/2026-MAHINDRA BLOSSOM DEVELOPERS LIMITED14/10/2026

Documents filed110

As listed on the registration, under the names the promoter filed them with; the newest 80 of 110 are shown. The files themselves are available at source: search the registration number TOR/PRM/KA/RERA/1251/446/PR/260615/008348 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Mahindra Blossom Q2 26-27.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Mahindra Blossom Q2 26-27.pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Mahindra Blossom Q2 26-27.pdf13 Oct 2026
Q2 2026-27 Water supply and sewage board13 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)13 Oct 2026
Q2 2026-27 KPTCL- BESCOM13 Oct 2026
Q2 2026-27 Fire and Safety13 Oct 2026
Q2 2026-27 Airport Authority of India13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - Mahindra Blossom - June 26 signed.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate_JUNE 2026 Blossom.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM-6 MAHINDRA BLOSSOM 30-06-2026.pdf14 Jul 2026
Bank Account Affidavit - Mahindra BlossomFile: 1 Bank Account Affidavit - Mahindra Blossom.pdf9 Jun 2026
RERA Bank AccountsFile: 2 RERA Bank Accounts.pdf9 Jun 2026
RERA Bank AccountsFile: 1 RERA Bank Accounts.pdf29 May 2026
Bank Account AffidavitFile: 2 Bank Account Affidavit.pdf29 May 2026
AFS_Mahindra Blossom_MBLDL (RERA version final) V3File: 3 AFS_Mahindra Blossom_MBLDL (RERA version final) V3.pdf29 May 2026
SEIAA NOC Clear copy latestFile: 4 SEIAA NOC Clear copy latest.pdf29 May 2026
Declaration Affidavit for NOCsFile: 5 Declaration Affidavit for NOCs.pdf29 May 2026
MBLDL - Sold & Unsold unit detailsFile: 6 MBLDL - Sold & Unsold unit details.pdf29 May 2026
Incoming Promoter - AffidavitFile: 7 Incoming Promoter - Affidavit.pdf29 May 2026
CertificateFile: MBLDL_COI.pdf-
BDA Work Order-
Development Plan-
AFS_Mahindra Blossom_30042026 (RERA)-
Allotment Letter_Mahindra Blossom 30042026 (RERA)-
Project Specification V1-
ECC-30032026-11811564-
Sec 3(1) Affidavit-
Mahindra Blossom _ E-Khata-
Fire - NOC-
AAI NOC-
BESCOM NOC-
BWSSB- NOC-
KSPCB CFE NOC_c-
SEIAA NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Stability certificate-
Title Certificate_B9Hope-
Balance Sheet 2024 - 2025File: Clarifications on Financial _ MBLDL.pdf-
Balance Sheet 2023 - 2024File: Clarifications on Financial _ MBLDL.pdf-
Balance Sheet 2022 - 2023File: Clarifications on Financial _ MBLDL.pdf-
Audited Profit and Loss Statement 2024 - 2025File: Clarifications on Financial _ MBLDL.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Clarifications on Financial _ MBLDL.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Clarifications on Financial _ MBLDL.pdf-
Director's Report 2024 - 2025File: Clarifications on Financial _ MBLDL.pdf-
Director's Report 2023 - 2024File: Clarifications on Financial _ MBLDL.pdf-
Director's Report 2022 - 2023File: Clarifications on Financial _ MBLDL.pdf-
Cash Flow Statement 2024 - 2025File: Clarifications on Financial _ MBLDL.pdf-
Cash Flow Statement 2023 - 2024File: Clarifications on Financial _ MBLDL.pdf-
Auditor's Report 2024 - 2025File: Clarifications on Financial _ MBLDL.pdf-
Auditor's Report 2023 - 2024File: Clarifications on Financial _ MBLDL.pdf-
Auditor's Report 2022 - 2023File: Clarifications on Financial _ MBLDL.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: Clarifications on Financial _ MBLDL.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: Clarifications on Financial _ MBLDL.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: Clarifications on Financial _ MBLDL.pdf-
Form-B Affidavit-
MBDL - Sale deed-
Title Report-Mahindra Blossom-
Form-2 Mahindra Blossom-
Form-3 Mahindra Blossom-
A Block Consent Letters 1-
A Block Consent Letters 2-
B Block Consent Letters 1-
B Block Consent Letters 2-
B Block Consent Letters 3-
B Block Consent Letters 4-
B Block Consent Letters 5-
B Block Consent Letters 6-
C Block Consent Letters 1-
C Block Consent Letters 2-
C Block Consent Letters 3-
C Block Consent Letters 4-
C Block Consent Letters 5-

How this compares with Bengaluru Urban

74%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep MAHINDRA BLOSSOM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmMAHINDRA BLOSSOMOther 35Dot size: filed unitsN

Filed coordinates, straight-line distance. 35 registered projects within 2 km.

Builder: MAHINDRA BLOSSOM DEVELOPERS LIMITED

MAHINDRA BLOSSOM DEVELOPERS LIMITED has 1 registration on RERA Karnataka, including MAHINDRA BLOSSOM. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if MAHINDRA BLOSSOM is delayed beyond 31 Oct 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of MAHINDRA BLOSSOM?

The registered promoter entity is MAHINDRA BLOSSOM DEVELOPERS LIMITED, a company as per the filing. Its CIN U41000MH2026PLC464693 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in MAHINDRA BLOSSOM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MAHINDRA BLOSSOM?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at MAHINDRA BLOSSOM?

The professionals named in the filing: Architect: Srimathi J Adiga; Engineer: B E Pruthviraja. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAHINDRA BLOSSOM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAHINDRA BLOSSOM. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAHINDRA BLOSSOM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.