MAHAVEER TRIDENT
By REDDY STRUCTURES PRIVATE LIMITED
RG-KA-13650 · RERA PRM/KA/RERA/1251/310/PR/190219/002385
Source: official RERA Karnataka filing
Red flags
- 14 complaints at RERA Karnataka
- Completion date moved by 39 months
- 3 extensions taken
Clear
- Separate project account declared
Saved.
MAHAVEER TRIDENT is a Residential/Group Housing project by REDDY STRUCTURES PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/190219/002385 on 19 Feb 2019. Possession is promised by 31 Mar 2025. The completion date has moved by 39 months from the original filing. 14 complaints are on record with the regulator.
At a glance
Project
- NameMAHAVEER TRIDENT
- TypeResidential/Group Housing
- Location
- Bengaluru South
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/310/PR/190219/002385
- ReraGenie IDRG-KA-13650
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on19 Feb 2019
- Promised completion31 Mar 2025
- Revised completionRevised to 31 Mar 2025 (originally 31 Dec 2021)
- Buildings4 building records
- Documents filed58 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BLOCK A | - | - | - | 36 | 0 | 36 |
| BLOCK B | - | - | - | 28 | 0 | 28 |
| BLOCK C | - | - | - | 56 | 0 | 56 |
| BLOCK D | - | - | - | 20 | 0 | 20 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | Yes | - |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | No | Not applicable |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ANI SAMBYAL SINGH |
| Engineer | DR. R JAGADISH |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterothers
No reason recorded in the filing
Complaints filed with RERA Karnataka14
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CMP/221208/0010438 | - | REDDY STRUCTURES PRIVATE LIMITED | 08/12/2022 |
| 00009/2023 | - | REDDY STRUCTURES PRIVATE LIMITED | 04/01/2023 |
| 00254/2023 | - | REDDY STRUCTURES PRIVATE LIMITED | 27/02/2023 |
| 00257/2023 | - | REDDY STRUCTURES PRIVATE LIMITED | 27/02/2023 |
| 00269/2023 | - | REDDY STRUCTURES PRIVATE LIMITED | 28/02/2023 |
| 00270/2023 | - | REDDY STRUCTURES PRIVATE LIMITED | 28/02/2023 |
| 00278/2023 | - | REDDY STRUCTURES PRIVATE LIMITED | 02/03/2023 |
| 00297/2023 | - | REDDY STRUCTURES PRIVATE LIMITED | 06/03/2023 |
| 00509/2023 | - | REDDY STRUCTURES PRIVATE LIMITED | 18/04/2023 |
| 00681/2023 | - | REDDY STRUCTURES PRIVATE LIMITED | 05/05/2023 |
| 00803/2023 | - | REDDY STRUCTURES PRIVATE LIMITED | 22/05/2023 |
| 01298/2023 | - | REDDY STRUCTURES PRIVATE LIMITED | 30/08/2023 |
| 01711/2023 | - | REDDY STRUCTURES PRIVATE LIMITED | 16/11/2023 |
| 00433/2024 | - | REDDY STRUCTURES PRIVATE LIMITED | 13/05/2024 |
Documents filed58
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/190219/002385 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Certificate of Incorporation RSPL.pdf | - |
| Project Details | - |
| Architect Certificate for Work Completion Schedule till DateFile: AR work as on date.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Engineercertificate for status of work.pdf | - |
| CA Certificate for Funds UtilizationFile: CA Fund utilized_compressed.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Ar work Pending.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Engineer work pending.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: CA funds Required_compressed.pdf | - |
| AffidavitFile: Affidavit B_compressed.pdf | - |
| Latest Encumbrance CertificateFile: EC.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: Trident Sold and unsold -1.xlsx | - |
| Document 1File: NOC request letter.pdf | - |
| Document 2File: Affidavit 2.pdf | - |
| Document 3File: Affidavit 3.pdf | - |
| BUILDING LICENCE | - |
| Trident-old SITE PLAN | - |
| site plan | - |
| proforma Sale Deed | - |
| proforma SALE AGREEMENT | - |
| RTC and sale deeds | - |
| Sanction plan | - |
| Trident-old GROUND FLOOR | - |
| BOOKING FORM - ALLOTMENT | - |
| Trident-Leaflet_1 | - |
| Specification | - |
| EC-12 years till date | - |
| KHATA AND EXTRACT | - |
| JDA | - |
| JDA | - |
| CONVERSION copy | - |
| BESCOM-13022013-final | - |
| BWSSB-30082012-final | - |
| KSPCB-09072013-final | - |
| EC-29072013-final | - |
| Typical floor plan | - |
| site plan | - |
| CONVERSION copy | - |
| Balance Sheet 2016 - 2017File: balance sheet.pdf | - |
| Balance Sheet 2015 - 2016File: Balance Sheet.pdf | - |
| Balance Sheet 2014 - 2015File: Balance Sheet.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: profit and loss account.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: Profit and loss account.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: Profit and Loss account.pdf | - |
| Director's Report 2016 - 2017File: Director's Report.pdf | - |
| Director's Report 2015 - 2016File: Directors Report.pdf | - |
| Director's Report 2014 - 2015File: Directors Report.pdf | - |
| Cash Flow Statement 2016 - 2017File: cash flow statement.pdf | - |
| Cash Flow Statement 2015 - 2016File: cash flow statement.pdf | - |
| Auditor's Report 2016 - 2017File: Auditors report.pdf | - |
| Auditor's Report 2015 - 2016File: Audit Report.pdf | - |
| Auditor's Report 2014 - 2015File: Audit Report.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ITR Acknowledgement.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR copy.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: Tax Filing Ackn.pdf | - |
| Declaration Form B | - |
| Prospectus/BrochureFile: Trident Leaflet_Whatsapp.pdf | - |
| Advertisement Copy 1File: Hindu_Trident_Lauching-Ad.jpg | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_190219_002385.xlsx | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep MAHAVEER TRIDENT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: REDDY STRUCTURES PRIVATE LIMITED
REDDY STRUCTURES PRIVATE LIMITED has 11 registrations on RERA Karnataka, including MAHAVEER PALATIUM and Mahaveer Palatium Sy No 41. Its filings declare 25 earlier projects, 8 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if MAHAVEER TRIDENT is delayed beyond 31 Mar 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of MAHAVEER TRIDENT?
The registered promoter entity is REDDY STRUCTURES PRIVATE LIMITED, a company as per the filing. Its CIN U07010KA2002PTC031181 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in MAHAVEER TRIDENT?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against MAHAVEER TRIDENT?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at MAHAVEER TRIDENT?
The professionals named in the filing: Architect: ANI SAMBYAL SINGH; Engineer: DR. R JAGADISH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MAHAVEER TRIDENT?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.