Home / Browse projects / Bengaluru Urban, Karnataka / MAHAVEER SITARA
MAHAVEER SITARA
By SITARA DEVELOPERS PRIVATE LIMITED
RG-KA-74812 · RERA PRM/KA/RERA/1251/310/PR/171019/000671 · Last updated on RERA Karnataka portal: 8 Sep 2021
Source: official RERA Karnataka filing
Red flags
- 2 complaints at RERA Karnataka
- Completion date moved by 59 months
- 3 extensions taken
Clear
- Separate project account declared
Saved.
MAHAVEER SITARA is a Residential/Group Housing project by SITARA DEVELOPERS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/171019/000671 on 19 Oct 2017. Possession is promised by 31 Mar 2025. The completion date has moved by 59 months from the original filing. 2 complaints are on record with the regulator.
At a glance
Project
- NameMAHAVEER SITARA
- TypeResidential/Group Housing
- Location
- Bengaluru South
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/310/PR/171019/000671
- ReraGenie IDRG-KA-74812
Builder
- NameSITARA DEVELOPERS PRIVATE LIMITED
- Entity typeCompany
- CINU70109KA2012PTC065353
- Authorized SignatoryKUMBALA PRAVEEN
- DirectorsKUMBALA PRAVEEN, KUMBALA BHAGYA LAXMI
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on19 Oct 2017
- Promised completion31 Mar 2025
- Revised completionRevised to 31 Mar 2025 (originally 30 Apr 2020)
- Buildings4 building records
- Documents filed65 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BLOCK - A | - | - | - | 54 | 0 | 54 |
| BLOCK - B | - | - | - | 52 | 0 | 52 |
| BLOCK - C | - | - | - | 52 | 0 | 52 |
| BLOCK - D | - | - | - | 59 | 0 | 59 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 8 Sep 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | Not applicable |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
As on 8 Sep 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | Yes | - |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | Yes | - |
| Community Hall | Yes | - |
| Outdoor Sports facility | Yes | - |
| Indoor Sports facility | Yes | - |
| Swimming Pool | Yes | - |
| Gym | Yes | - |
| Parks | Yes | - |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | THOMAS TILAK |
| Engineer | RENUKA PRASAD H N |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterothers
No reason recorded in the filing
Complaints filed with RERA Karnataka2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| 00872/2024 | - | SITARA DEVELOPERS PRIVATE LIMITED | 10/09/2024 |
| 00901/2025 | - | SITARA DEVELOPERS PRIVATE LIMITED | 03/07/2025 |
Documents filed65
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/171019/000671 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| 1. In the CA certificate designated bank account number not matchedFile: Accounts approval sitara.pdf | 8 Sep 2021 |
| 2.This projects previous end date was 30-04-2020 project extension registration certificate from 30-File: Sitara RERA Covid certficate.pdf | 8 Sep 2021 |
| Affidavit template 6File: Template -6 Affidavit.pdf | 8 Sep 2021 |
| Bank StatementFile: ICICI - 7122.pdf | 17 Jun 2021 |
| Affidavit Tamplet 6File: Template -6 Affidavit.pdf | 17 Jun 2021 |
| Sitara extension Covid certificateFile: Sitara RERA Covid certficate.pdf | 17 Jun 2021 |
| CCFile: 23.COMMENCEMENT CERTIFICATE Sitara.pdf | 17 Jun 2021 |
| Affidavit section 18(1)File: Form B affidavit -declaration.pdf | 17 Jun 2021 |
| change of bank requestFile: Screen Shot bank change request.pdf | 17 Jun 2021 |
| CertificateFile: Sitara-Incorp Certificate.pdf | - |
| Project Details | - |
| Architect Certificate for Work Completion Schedule till DateFile: Status of work Architectcertifcate.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Work status engineer.pdf | - |
| CA Certificate for Funds UtilizationFile: Funds Utilized Signed Certificate.PDF | - |
| Architect Certificate for Pending Work Completion Schedule.File: Pending of work Archtitect certificate.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Pending work engineer.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: Funds Required Signed Certificate.PDF | - |
| AffidavitFile: Template -6 Affidavit.pdf | - |
| Latest Encumbrance CertificateFile: EC.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx | - |
| SITE PLAN | - |
| FLOOR PLAN | - |
| SITE PLAN | - |
| proforma Sale Deed | - |
| proforma SALE AGREEMENT | - |
| location | - |
| SECTION ELEVATION | - |
| DP PLAN | - |
| BOOKING FORM - ALLOTMENT | - |
| Sitara brochures | - |
| NOC_Compressed_Compressed_Compressed | - |
| Specifications | - |
| encumberance certificate | - |
| RTC | - |
| sale deed 1350 | - |
| Conversion Copy | - |
| 01-06 08 00 FIRE | - |
| 06 03 00 AAI | - |
| 01-06 04 00 BESCOM | - |
| 06 06 00 BWSSB | - |
| 01-06 09 00 KSPCB | - |
| 01-06 07 00 EC | - |
| 06 05 00 BSNL | - |
| SECTION ELEVATION | - |
| Balance Sheet 2015 - 2016File: balance Sheet.pdf | - |
| Balance Sheet 2014 - 2015File: Balance Sheet.pdf | - |
| Balance Sheet 2013 - 2014File: Balance Sheet.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: Profit and Loss Account.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: Profit and loss account.pdf | - |
| Audited Profit and Loss Statement 2013 - 2014File: Profit and loss account.pdf | - |
| Director's Report 2015 - 2016File: Directors Report.pdf | - |
| Director's Report 2014 - 2015File: Directors Report.pdf | - |
| Director's Report 2013 - 2014File: Directors Report.pdf | - |
| Cash Flow Statement 2015 - 2016File: Cash Flow Statement.pdf | - |
| Cash Flow Statement 2014 - 2015File: Cash Flow Statement.pdf | - |
| Auditor's Report 2015 - 2016File: Auditors Report.pdf | - |
| Auditor's Report 2014 - 2015File: Auditors Report.pdf | - |
| Auditor's Report 2013 - 2014File: Auditors Report.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR copy.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: ITR Copy.pdf | - |
| Income Tax Return Acknowledgement 2013 - 2014File: ITR copy.pdf | - |
| Sitara-Affidavit | - |
| Prospectus/BrochureFile: Sitara_Leaflet-2.jpg | - |
| Advertisement Copy 1File: Sitara_Leaflet-2.jpg | - |
| Tower Excel SheetFile: 6_Sitara - PRM_KA_RERA_1251_310_PR_171019_000671.xlsx | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep MAHAVEER SITARA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: SITARA DEVELOPERS PRIVATE LIMITED
SITARA DEVELOPERS PRIVATE LIMITED has 1 registration on RERA Karnataka, including MAHAVEER SITARA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if MAHAVEER SITARA is delayed beyond 31 Mar 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of MAHAVEER SITARA?
The registered promoter entity is SITARA DEVELOPERS PRIVATE LIMITED, a company as per the filing. Its CIN U70109KA2012PTC065353 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in MAHAVEER SITARA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against MAHAVEER SITARA?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at MAHAVEER SITARA?
The professionals named in the filing: Architect: THOMAS TILAK; Engineer: RENUKA PRASAD H N. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MAHAVEER SITARA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback