Home / Browse projects / Bengaluru Urban, Karnataka / MAHAVEER CREST

Registration approved No litigation declared Residential/Group Housing project

MAHAVEER CREST

By REDDY STRUCTURES PRIVATE LIMITED

RG-KA-19255 · RERA PRM/KA/RERA/1251/446/PR/170726/008823 · Last updated on RERA Karnataka portal: 16 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Sep 2031Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 116 documents Report an error

MAHAVEER CREST is a Residential/Group Housing project by REDDY STRUCTURES PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/170726/008823 on 17 Jul 2026. Possession is promised by 30 Sep 2031.

At a glance

Project

  • NameMAHAVEER CREST
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/170726/008823
  • ReraGenie IDRG-KA-19255

Builder

  • NameREDDY STRUCTURES PRIVATE LIMITED
  • Entity typeCompany
  • CINU07010KA2002PTC031181
  • GSTIN29AACCR6953L1ZQ
  • Authorized SignatoryM NISHANTH REDDY
  • DirectorsK PRAVEEN, K PRAVEEN, K BHAGYA LAXMI
  • Project HeadPutha Sreenivas Reddy
  • Other registrations10 more →
  • Declared earlier projects25 →

Key dates

this monthRegisteredJul 2026PromisedSep 2031

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on17 Jul 2026
  • Promised completion30 Sep 2031
  • Revised completionNone
  • Buildings12 building records
  • Documents filed116 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING 1 (Block A)---40040
WING 2 (Block A)---45045
WING 3 (Block A)---35035
WING 4 (Block A)---40040
WING 5 (Block A)---45045
WING 6 (Block A)---35035
WING 7 (Block A)---45045
WING 8 (Block A)---40040
WING 9 (Block A)---25025
WING 10 (Block B)---80080
WING 11 (Block B)---50050
WING 12 (Block B)---40040

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes-
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesYes-
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areasYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners4
LandownerVillageDistrict
M R Shivakumar--
M R Shivakumar--
K Malini--
N Kodanda Reddy--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 223.90 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 197.14 cr-
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 9.60 cr-
Administrative CostsRs 9.00 cr-
On-site expenditure-Consultants FeesRs 5.46 cr-
Payment of taxesRs 2.70 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSrinivas G Arvas
EngineerInturi Veeraiah
Chartered AccountantSAKALESHWARA D C

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed116

As listed on the registration, under the names the promoter filed them with; the newest 80 of 116 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/170726/008823 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Clarification on QueriesFile: 1 Clarification on Queries.pdf16 Jul 2026
ECC-Sy No 99-1File: 2 ECC-Sy No 99-1.pdf16 Jul 2026
ECC-Sy No 99-2File: 3 ECC-Sy No 99-2.pdf16 Jul 2026
ECC-Sy No 100-1File: 4 ECC-Sy No 100-1.pdf16 Jul 2026
ECC-Sy No 100-2File: 5 ECC-Sy No 100-2.pdf16 Jul 2026
Form-6 Engineer certificateFile: 6 Form-6 Engineer certificate.pdf16 Jul 2026
Proforma Sale Agreement CrestFile: 7 Proforma Sale Agreement Crest.pdf16 Jul 2026
Proforma Allotment Letter- UpdatedFile: 8 Proforma Allotment Letter- Updated.pdf16 Jul 2026
Land Cost Calculation SignedFile: 9 Land Cost Calculation Signed.pdf16 Jul 2026
Construction Estimation SummaryFile: 10 Construction Estimation Summary.pdf16 Jul 2026
STP DrawingFile: 11 STP Drawing.pdf16 Jul 2026
RTC, survey 99/1-
Mutation, survey 99/1-
Encumbrance Certificate, survey 99/1-
Conversion/Alienation Order, survey 99/1-
Sale/Title/Gift Deed, survey 99/1-
JDA, survey 99/1-
Khatha, survey 99/1-
RTC, survey 99/2-
Mutation, survey 99/2-
Encumbrance Certificate, survey 99/2-
Conversion/Alienation Order, survey 99/2-
Sale/Title/Gift Deed, survey 99/2-
JDA, survey 99/2-
Khatha, survey 99/2-
RTC, survey 100/2-
Mutation, survey 100/2-
Encumbrance Certificate, survey 100/2-
Conversion/Alienation Order, survey 100/2-
Sale/Title/Gift Deed, survey 100/2-
JDA, survey 100/2-
Khatha, survey 100/2-
RTC, survey 100/1-
Mutation, survey 100/1-
Encumbrance Certificate, survey 100/1-
Conversion/Alienation Order, survey 100/1-
Sale/Title/Gift Deed, survey 100/1-
JDA, survey 100/1-
Khatha, survey 100/1-
Registration CertificateFile: Registeration certificate - RSPL.pdf-
Memorandum of AssociationFile: MOA.pdf-
Article of AssociationFile: AOA.pdf-
GST CertificateFile: GST Cert.pdf-
Certificate issued by CA Form 1File: Form 1 CA Certificate Mahaveer Crest.pdf-
Certificate issued by Architect Form 2File: Form 2 Arc Cert - Mahaveer Crest.pdf-
Certificate issued by Engineer Form 3File: Form 3 Eng Cert - Mahaveer Crest.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non litigation Affidavit.pdf-
Balance Sheet 2024 - 2025File: Financials FY 2024-25.pdf-
Balance Sheet 2023 - 2024File: Financials FY 2023-24.pdf-
Balance Sheet 2022 - 2023File: Financials FY 2022-23.pdf-
Audited Profit and Loss Statement 2024 - 2025File: Financials FY 2024-25.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Financials FY 2023-24.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Financials FY 2022-23.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: ITR FY 2024-25.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: ITR FY 2023-24.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR FY 2022-23.pdf-
Director's Report 2024 - 2025File: Financials FY 2024-25.pdf-
Director's Report 2023 - 2024File: Financials FY 2023-24.pdf-
Director's Report 2022 - 2023File: Financials FY 2022-23.pdf-
Cash Flow Statement 2024 - 2025File: Financials FY 2024-25.pdf-
Cash Flow Statement 2023 - 2024File: Financials FY 2023-24.pdf-
Auditor's Report 2024 - 2025File: Financials FY 2024-25.pdf-
Auditor's Report 2023 - 2024File: Financials FY 2023-24.pdf-
Auditor's Report 2022 - 2023File: Financials FY 2022-23.pdf-
BDA Approval letter-
BDA Plan 1-8-
BDA Plan 8-8-
Crest Structural Stability Certificate-
Project Specification -crest-
Relinquishment Deed-
Form B Affidavit - Crest-
Section 3(1) Notarized Affidavit-
JD AFFIDAVIT CUM DECLARATION-
Legal Opinion - Signed-
Crest - BESCOM NOC-
Crest - Water - Panchayath NOC-
KSPCB NOC - Affidavit-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep MAHAVEER CREST on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: REDDY STRUCTURES PRIVATE LIMITED

REDDY STRUCTURES PRIVATE LIMITED has 11 registrations on RERA Karnataka, including MAHAVEER PALATIUM and Mahaveer Palatium Sy No 41. Its filings declare 25 earlier projects, 8 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if MAHAVEER CREST is delayed beyond 30 Sep 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of MAHAVEER CREST?

The registered promoter entity is REDDY STRUCTURES PRIVATE LIMITED, a company as per the filing. Its CIN U07010KA2002PTC031181 and GSTIN 29AACCR6953L1ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in MAHAVEER CREST?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at MAHAVEER CREST?

The professionals named in the filing: Architect: Srinivas G Arvas; Engineer: Inturi Veeraiah; Chartered Accountant: SAKALESHWARA D C. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAHAVEER CREST?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAHAVEER CREST. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAHAVEER CREST to a free account