Red flags

  • 3 complaints at RERA Karnataka
  • Completion date moved by 41 months
  • 3 extensions taken

Clear

  • Separate project account declared
Mar 2025Possession promisedmoved 41 months from the original
3Complaints at RERA Karnatakaon this registration
Jump to the 58 documents Report an error

MAHAVEER CARNATION is a Residential/Group Housing project by RED CORAL PROPERTIES in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/180504/001613 on 4 May 2018. Possession is promised by 31 Mar 2025. The completion date has moved by 41 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NameMAHAVEER CARNATION
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/180504/001613
  • ReraGenie IDRG-KA-43526

Builder

  • NameRED CORAL PROPERTIES
  • Entity typePartnership Firm
  • Authorized SignatoryKUMBALA PRAVEEN
  • OthersKUMBALA PRAVEEN
  • Other registrations3 more →

Key dates

this monthRegisteredMay 2018First promiseOct 2021Revised toMar 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on4 May 2018
  • Promised completion31 Mar 2025
  • Revised completionRevised to 31 Mar 2025 (originally 31 Oct 2021)
  • Buildings1 building record
  • Documents filed58 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER 1---1030103

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,502 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 30.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCHAKRAVARTHI TNS
EngineerVEERAIAH I

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionOct 2021 → Jul 2022

No reason recorded in the filing

EX/PRM/KA/RERA/1251/310/PR/221109/001613Jul 2022 → Jul 2023

Reason as filed by the promoterShortage of Labour

ExtensionJul 2023 → Mar 2025

No reason recorded in the filing

Complaints filed with RERA Karnataka3

Case no.ComplainantRespondentFiled
00805/2023-RED CORAL PROPERTIES22/05/2023
00867/2023-RED CORAL PROPERTIES01/06/2023
01253/2025-RED CORAL PROPERTIES08/10/2025

Documents filed58

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/180504/001613 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Registration Certificate.pdf-
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: ARCHITECT CERTIFICATE -Work As on date.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineers Certificates_Pending work as on date.pdf-
CA Certificate for Funds UtilizationFile: Chartered Accountant Certificate -Fund Utilization.pdf-
Architect Certificate for Pending Work Completion Schedule.File: ARCHITECT CERTIFICATE -Work Pending.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineers Certificates_Pending work as on date.pdf-
CA Certificate for Funds required for Project CompletionFile: Chartered Accountant Certificate -Funds Required.pdf-
AffidavitFile: Affidavit_0001.pdf-
Latest Encumbrance CertificateFile: EC.pdf-
Details Of Sold/ Un-sold UnitsFile: Carnation Sold and unsold.xlsx-
Document 1File: NOC Request letter.pdf-
Document 2File: FORM - B - Affidavit cum Declaration_0001.pdf-
carnation sanction plan Compressed-
carnation sanction plan Compressed-
site plan-
proforma Sale Deed-
proforma SALE AGREEMENT-
Sale Deed and RTC-
site plan-
site plan-
BOOKING FORM - ALLOTMENT-
project brochure-
NOC_Compressed-
specifications-
EC-
katha-
JDA-
JDA-
conversion order-
Bescom-
BWSSB-
KSPCB-
carnation sanction plan Compressed-
site plan-
DC CONVERSION-
Balance Sheet 2016 - 2017File: balance sheet.pdf-
Balance Sheet 2015 - 2016File: 02-balance sheet.pdf-
Balance Sheet 2014 - 2015File: balance sheet.pdf-
Audited Profit and Loss Statement 2016 - 2017File: profit and loss account.pdf-
Audited Profit and Loss Statement 2015 - 2016File: 02-profit and loss account.pdf-
Audited Profit and Loss Statement 2014 - 2015File: Profit and loss account.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: Red coral properties ITR V FY 2016-17.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: 06-ITR copy.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR Copy.pdf-
Affidavit Form B-
Prospectus/BrochureFile: Leaflet_Carnation58x20.pdf-
Advertisement Copy 1File: Carnation.jpg-
Tower Excel SheetFile: 5_Carnation-PRM_KA_RERA_1251_310_PR_180504_001613.xlsx-
Stability CertificateFile: Carnation Stability Certificate.pdf-
Occupancy CertificateFile: Carnation - OC.pdf-
Consent for operation issued by KSPCBFile: KARNATAKA STATE POLLUTION CONTROL BOARD.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Approval of Electrical Installation.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM NOC.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: BWSSB NOC.pdf-
Architect certificate for having completed the work(in format no 5)File: Form 5 -CC Carnation.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: Form 4 CC Carnation.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit - mahaveer Carnation.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 41 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep MAHAVEER CARNATION on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: RED CORAL PROPERTIES

RED CORAL PROPERTIES has 4 registrations on RERA Karnataka, including MAHAVEER CYGNET and MAHAVEER CARNATION. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if MAHAVEER CARNATION is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of MAHAVEER CARNATION?

The registered promoter entity is RED CORAL PROPERTIES, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in MAHAVEER CARNATION?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MAHAVEER CARNATION?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at MAHAVEER CARNATION?

The professionals named in the filing: Architect: CHAKRAVARTHI TNS; Engineer: VEERAIAH I. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAHAVEER CARNATION?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAHAVEER CARNATION. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAHAVEER CARNATION to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.