MAHALASA CLASSIC

By MHALASA CONTRACTORS

RG-KA-61993 · RERA PRM/KA/RERA/1274/351/PR/300124/006583 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2027Possession promisedno revision filed
5 of 14Construction stages donefurthest along: Masonry Construction, 85%
36 of 36Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 120 documents Report an error

MAHALASA CLASSIC is a Residential/Group Housing project by MHALASA CONTRACTORS in Uttara Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1274/351/PR/300124/006583 on 30 Jan 2024. Possession is promised by 31 Dec 2027. 0 of the 36 units on this registration are recorded sold or booked, and 5 of 14 construction stages are filed complete.

At a glance

Project

  • NameMAHALASA CLASSIC
  • TypeResidential/Group Housing
  • Location
    • Karwar
    • Uttara Kannada
    • 581301
  • Pincode581301
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1274/351/PR/300124/006583
  • ReraGenie IDRG-KA-61993

Builder

  • NameMHALASA CONTRACTORS
  • Entity typePartnership Firm
  • Authorized SignatorySARTHAK NAGESH VERNEKAR

Key dates

this monthRegisteredJan 2024PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on30 Jan 2024
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed120 files

Current status

0%0 of 36 units booked
63.2%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MAHALASA CLASSIC BLOCK A---18018
MAHALASA CLASSIC BLOCK B---18018

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 14 construction stages are filed complete. The stage furthest along is Masonry Construction, at 85%.

Building: 79% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction85%
Plastering inside , outside & Ceiling70%
Joinery: Doors, Windows, Ventilators etc65%
Basic work of Water supply, Sanitary and Electrification85%
Dadoing, Skirting, Flooring, Tiles work (All types)75%
Railing and Grill fixing70%
Electrification, Water supply and Sanitary Finishing55%
Painting55%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work50%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes70%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes70%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes100%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes80%
Storm water drainsYes60%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes80%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes50%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes50%
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes65%
LiftsYes55%
Corridor/LobbiesYes60%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,328 sq m
Named landowners1
LandownerVillageDistrict
MAHALASA CONTRACTORS--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 6.45 cr
Cost incurredRs 4.08 cr
Spent of the estimate63.19%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 6.40 crRs 4.08 cr
On-site expenditure-Consultants FeesRs 5.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGEETA NAGESH VERNEKAR
EngineerNAGESH VAMAN VERNEKAR
Chartered AccountantRajesh Balkrishna Patange

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed120

As listed on the registration, under the names the promoter filed them with; the newest 80 of 120 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1274/351/PR/300124/006583 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 4.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5, Architect (QU).pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (QU).pdf15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 4.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5, Architect (QU) 30-06-2026 Mahalasa Classic.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (QU) 30-06-2026 Mahalasa Classic.pdf14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Signed Q4 2025-26 CERTIFICATE.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5, Architect (QU) 31-03-2026.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (QU) 31-03-2026.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Certificate under KRERA 31032025 DIG SIGNED.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5, Architect (QU) 31-12-2025 Mahalasa Classic.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: engineer certificate with OC Block A.pdf13 Jan 2026
ca adharFile: ADHAR.pdf23 Jan 2024
ca membership certificateFile: MemberCard.pdf23 Jan 2024
form 1 ca certificateFile: form 1 ca report.pdf23 Jan 2024
source of fundFile: source of fund.pdf23 Jan 2024
ITR 2022-23 FIRMFile: ITR AY 2023-24.pdf23 Jan 2024
BS 2022-23 FIRMFile: BS AY 2023-24.pdf23 Jan 2024
PL 2022-23 FIRMFile: PL AY 2023-24.pdf23 Jan 2024
IS 2022-23 FIRMFile: IS AY 2023-24.pdf23 Jan 2024
KETHKI FS 2023 -PARTNERFile: Ketaki Pawaskar FS 2023.pdf23 Jan 2024
SARTHAK FS 2023 -PARTNERFile: Sarthak FS 2023.pdf23 Jan 2024
Amenities and common area details Certified by engineerFile: certified amentioes and common area.jpeg23 Jan 2024
self attested engineer licenceFile: ENGINEER LICENCE.jpeg23 Jan 2024
self-attested hescom nocFile: Hescom NOC.pdf23 Jan 2024
self-attested water nocFile: Water NOC.pdf23 Jan 2024
clarificationFile: clarification on notice.pdf23 Jan 2024
RTC, survey 106/3+5+6+9+10/D-
Mutation, survey 106/3+5+6+9+10/D-
Encumbrance Certificate, survey 106/3+5+6+9+10/D-
Conversion/Alienation Order, survey 106/3+5+6+9+10/D-
Sale/Title/Gift Deed, survey 106/3+5+6+9+10/D-
Khatha, survey 106/3+5+6+9+10/D-
Registration CertificateFile: Firm Registration Certificate.pdf-
Partnership DeedFile: Partnership Deed.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: form 1 ca report.pdf-
Certificate issued by Architect Form 2File: Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: affidavit for non litigation on land.pdf-
Certificate from Chartered AccountFile: form 1 ca report.pdf-
building licence-
Sanction Drawing Mahalasa Classic-1-
single plot-
Sanction Drawing Mahalasa Classic-1-
Sanction Drawing Mahalasa Classic-2-
Sanction Drawing Mahalasa Classic-1-
specification-
single plot-
single plot-
stability certificate-
search report-
title deed-
Conversion order-
Conversion order-
title deed-
Proforma AOS-
Proforma allotment letter-
broucher_compressed-
Form B-
Affidavit-
Hescom NOC-
Water NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
pollution control board-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-

How this compares with Uttara Kannada

0%of this project is bookeddistrict median 27%
22%of Uttara Kannada projects moved their completion datethis one has not
0%of Uttara Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 100+ Uttara Kannada projects on ReraGenie, from their own filings.

Keep MAHALASA CLASSIC on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Uttara Kannada100+ in Uttara Kannada

2 kmMAHALASA CLASSICOther 15Dot size: filed unitsN

Filed coordinates, straight-line distance. 15 registered projects within 2 km.

Builder: MHALASA CONTRACTORS

MHALASA CONTRACTORS has 1 registration on RERA Karnataka, including MAHALASA CLASSIC. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Uttara Kannada district page.

Frequently asked questions

What are my rights if MAHALASA CLASSIC is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of MAHALASA CLASSIC?

The registered promoter entity is MHALASA CONTRACTORS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in MAHALASA CLASSIC?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at MAHALASA CLASSIC?

The professionals named in the filing: Architect: GEETA NAGESH VERNEKAR; Engineer: NAGESH VAMAN VERNEKAR; Chartered Accountant: Rajesh Balkrishna Patange. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAHALASA CLASSIC?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAHALASA CLASSIC. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAHALASA CLASSIC to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.