ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Mahadev Enterprises, branded as 'Esteem Kings Court'

Registration approved Residential/Group Housing project

Mahadev Enterprises, branded as 'Esteem Kings Court'

By Esteem Kings Dwelling Private Limited

RG-KA-65048 · RERA PRM/KA/RERA/1251/310/PR/181122/002159

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • Separate project account declared
Feb 2023Possession promisedmoved 9 months from the original
1Complaints at RERA Karnatakaon this registration
Jump to the 61 documents Report an error

Mahadev Enterprises, branded as 'Esteem Kings Court' is a Residential/Group Housing project by Esteem Kings Dwelling Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/181122/002159 on 22 Nov 2018. Possession is promised by 16 Feb 2023. The completion date has moved by 9 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMahadev Enterprises, branded as 'Esteem Kings Court'
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/181122/002159
  • ReraGenie IDRG-KA-65048

Builder

  • NameEsteem Kings Dwelling Private Limited
  • Entity typePartnership Firm
  • Authorized SignatoryGaurav Ahuja
  • OthersAbhishek Ahuja, Gaurav Ahuja, Lakshmi Gopal Makhija, Naraindas Bodaram
  • Other registrations2 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredNov 2018First promiseMay 2022Revised toFeb 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on22 Nov 2018
  • Promised completion16 Feb 2023
  • Revised completionRevised to 16 Feb 2023 (originally 16 May 2022)
  • Buildings3 building records
  • Documents filed61 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---16016
G---16016
F---808

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,978 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 26.08 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArchitects Inc
EngineerM. THARANATH

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMay 2022 → Feb 2023

No reason recorded in the filing

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00870/2026-Esteem Kings Dwelling Private Limited27/07/2026

Documents filed61

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/181122/002159 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: FORM - C Registration Certificate-ilovepdf-compressed.pdf-
Commencement Certificate for FIrst Phase-
Sanctioned Building Plan-
approved sanction plan all-
awaiting sale deed draft0001-
awaiting sale agreement draft-
Brief Note Sale Deeds and RTC-
Apprd Sec of Bldg Infr pln of Pltg - Mahadev-
Santion Plan - Site plan - Mahadev 1-
Allotment Letter - MAHADEV ENTERPRISES-
mahadev Leaflet- low res (1)-
Esteem Kings court-Specification Amenity List(1)-
EC for past twelve years-
Katha - Mahadev Enterprises-
Letter & Architecture Plans for Phase -1-
Conversion - Mahadev Enterprises-
Mahadev Enterprises BWSSB NOC--
Mahadev Enterprises KSPCB NOC-
Mahadeva Enterprises SEIAA NOC-min-min_Compressed-
Existing Layout Plan - Mahadev-
Existing Section Plan - Mahadev-
Balance Sheet 2016 - 2017-
Balance Sheet 2015 - 2016File: Mahadev 2016-17 BS.pdf-
Balance Sheet 2014 - 2015File: Mahadev Enterprises IT AY 2015-16 BS.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Mahadev Enterprises P&L IT AY 2017-18.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Mahadev 2016-17 P&L.pdf-
Audited Profit and Loss Statement 2014 - 2015File: Mahadev Enterprises IT AY 2015-16 P&L.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR ACk 2017-18.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR Ack 2016-17.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR ACK 2015-16.pdf-
affidavit cum declaration0001-
Prospectus/BrochureFile: Brochure EKC - 1.pdf-
Advertisement Copy 1File: Brochure EKC - 1.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_181122_002159.xlsx-
Loan raised documentFile: EKC 1 completion Details of Borrowings on the project.pdf-
Stability CertificateFile: Structrual Stablity Certificate.pdf-
Occupancy CertificateFile: EKC OC.pdf-
Consent for operation issued by KSPCBFile: CFO -KSPCB -EKDPL.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: LIFT LICENSE -EKDPL.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: EKC 1 completion Bescom.pdf-
Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: All works are completed.pdf-
Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: All works are completed.pdf-
Details of undivided share of land handed over to the association of allotteesFile: All works are completed.pdf-
Architect certificate for having completed the work(in format no 5)File: FOrm 5 Arch COMPLETION CERTIFICATE-PHASE-1.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: EKC completion 1 Form-4CC_Signed-compressed.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: EKC completion 1 Form-4CC_Signed-compressed.pdf-
poolFile: EKC - Indoor pool.jpg-
play areaFile: EKC - Kids Play area.jpg-
drivewayFile: EKC - Northside Driveway.jpg-
party hallFile: EKC - Part Hall Reception.jpg-
party hallFile: EKC - Party Hall.jpg-
basementFile: EKC - Car Parking.jpg-
DrivewayFile: EKC - Southside Driveway.jpg-
SteamFile: EKC - Steam Room.jpg-
saunaFile: EKC - Sauna.jpg-
TheatreFile: EKC - Theatre.jpg-
WTPFile: EKC - WTP.jpg-
STPFile: EKC - STP.jpg-
A BlockFile: A Block - EKC.jpeg-
f BlockFile: F Block - EKC.jpeg-
G blockFile: G Block - EKC.jpeg-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Mahadev Enterprises, branded as 'Esteem King on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Esteem Kings Dwelling Private Limited

Esteem Kings Dwelling Private Limited has 3 registrations on RERA Karnataka, including Mahadev Enterprises, branded as 'Esteem Kings Court' and Mahadev Enterprises branded as Esteem Kings Court Phase 2. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Mahadev Enterprises, branded as 'Esteem Kings Court' is delayed beyond 16 Feb 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Mahadev Enterprises, branded as 'Esteem Kings Court'?

The registered promoter entity is Esteem Kings Dwelling Private Limited, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Mahadev Enterprises, branded as 'Esteem Kings Court'?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Mahadev Enterprises, branded as 'Esteem Kings Court'?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Mahadev Enterprises, branded as 'Esteem Kings Court'?

The professionals named in the filing: Architect: Architects Inc; Engineer: M. THARANATH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mahadev Enterprises, branded as 'Esteem Kings Court'?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mahadev Enterprises, branded as 'Esteem Kings Court'. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mahadev Enterprises, branded as 'Esteem King to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.