  • Completion date moved by 33 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 33 months from the original
101 of 583Construction stages doneacross 54 buildings; furthest along: Slabs of Super Structure, 50%
54 of 106Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 152 documents Report an error

MADHUSUDAN RETREAT is a Mixed project by MADHUSUDAN LEISURE HOMES in Thane, Maharashtra, registered with MahaRERA as P51700030973 on 29 Sep 2021. Possession is promised by 31 Mar 2027. The completion date has moved by 33 months from the original filing. 52 of the 106 units on this registration are recorded sold or booked, and 101 of 583 construction stages are filed complete.

At a glance

Project

  • NameMADHUSUDAN RETREAT
  • TypeMixed
  • Location
    • MURBAD
    • THANE
    • Patgaon
    • 421401
  • Pincode421401
  • RERA no.P51700030973
  • ReraGenie IDRG-MH-30343

Builder

  • NameMADHUSUDAN LEISURE HOMES
  • Entity typeOthers
  • Named personADITYA JAJODIA
  • Other registrations1 more →

Key dates

this monthRegisteredSep 2021First promiseJun 2024Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Sep 2021
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Jun 2024)
  • Buildings53 building records
  • Documents filed152 files

Current status

49%52 of 106 units booked
82.6%Work done, per cost certificate

Figures as on 30 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUNGALOW NO 81NA33101
BUNGALOW NO 80NA33101
BUNGALOW NO 83NA33101
BUNGALOW NO 84NA33101
BUNGALOW NO 7NA33101
BUNGALOW NO 6NA33101
BUNGALOW NO 5NA33101
BUNGALOW NO 79NA33101
BUNGALOW NO 78NA33101
BUNGALOW NO 77NA33101
BUNGALOW NO 76NA33101
BUNGALOW NO 75NA33101
BUNGALOW NO 74NA33101
BUNGALOW NO 110NA33101
BUNGALOW NO 109NA33101
BUNGALOW NO 108NA33101
BUNGALOW NO 107NA33101
BUNGALOW NO 106NA33101
BUNGALOW NO 105NA33101
BUNGALOW NO 104NA33101
BUNGALOW NO 103NA33101
BUNGALOW NO 102NA33101
BUNGALOW NO 101NA33101
BUNGALOW NO 133NA33101
BUNGALOW NO 73NA33101
BUNGALOW NO 43NA33101
BUNGALOW NO 4NA33101
BUNGALOW NO 3NA33101
BUNGALOW NO 42NA33101
BUNGALOW NO 72NA33101
BUNGALOW NO 132NA33101
BUNGALOW NO 41NA33101
BUNGALOW NO 40NA33101
BUNGALOW NO 39NA33101
BUNGALOW NO 38NA33101
BUNGALOW NO 37NA33101
BUNGALOW NO 36NA33101
BUNGALOW NO 35NA33101
BUNGALOW NO 34NA33101
BUNGALOW NO 33NA33101
BUNGALOW NO 32NA33101
BUNGALOW NO 31NA33101
BUNGALOW NO 30NA33101
BUNGALOW NO 62NA33101
BUNGALOW NO 63NA33101
BUNGALOW NO 64NA33101
BUNGALOW NO 65NA33101
BUNGALOW NO 66NA33101
BUNGALOW NO 67NA33101
BUNGALOW NO 68NA33101
BUNGALOW NO 69NA33101
BUNGALOW NO 70NA33101
BUNGALOW NO 71NA33101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 30 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 54 buildings; the table lists the first 20.

101 of 583 construction stages are filed complete across 54 buildings. The stage furthest along is Slabs of Super Structure, at 50%.

BUNGALOW NO 8127%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 809%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 839%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 8432%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 79%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 60%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 527%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 7927%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 7827%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 7732%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 7627%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 7527%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 7427%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 11027%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 10927%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 1089%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 1079%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 1069%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 1059%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOW NO 10432%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed51

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots51
Closed/Covered51
BuildingClosed/CoveredTotal
BUNGALOW NO 8311
BUNGALOW NO 8411
BUNGALOW NO 711
BUNGALOW NO 611
BUNGALOW NO 511
BUNGALOW NO 7911
BUNGALOW NO 7811
BUNGALOW NO 7711
BUNGALOW NO 7611
BUNGALOW NO 7511
BUNGALOW NO 7411
BUNGALOW NO 11011
BUNGALOW NO 10911
BUNGALOW NO 10811
BUNGALOW NO 10711
BUNGALOW NO 10611
BUNGALOW NO 10511
BUNGALOW NO 10411
BUNGALOW NO 10311
BUNGALOW NO 10211
BUNGALOW NO 10111
BUNGALOW NO 13311
BUNGALOW NO 7311
BUNGALOW NO 4311
BUNGALOW NO 411
BUNGALOW NO 311
BUNGALOW NO 4211
BUNGALOW NO 7211
BUNGALOW NO 13211
BUNGALOW NO 4111
BUNGALOW NO 4011
BUNGALOW NO 3911
BUNGALOW NO 3811
BUNGALOW NO 3711
BUNGALOW NO 3611
BUNGALOW NO 3511
BUNGALOW NO 3411
BUNGALOW NO 3311
BUNGALOW NO 3211
BUNGALOW NO 3111
BUNGALOW NO 3011
BUNGALOW NO 6211
BUNGALOW NO 6311
BUNGALOW NO 6411
BUNGALOW NO 6511
BUNGALOW NO 6611
BUNGALOW NO 6711
BUNGALOW NO 6811
BUNGALOW NO 6911
BUNGALOW NO 7011
BUNGALOW NO 7111

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,823 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityThe Assistant Director of Town Planning
Permissible FSI14734.43
Proposed, not sanctioned14,734 sq m
Buildings approved53
Buildings sanctioned53

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No G 115, 116, 117, 118 High Street Cum Highland Corporate Centre Kapurbawdi Junction Thane Mah
Estimated costRs 14.04 cr
Cost incurredRs 11.60 cr
Work done82.64%
BuildingWingEstimatedIncurred
-NARs 2.48 crRs 1.65 cr
BUNGALOW NO 7NARs 33.90 lakhRs 29.17 lakh
BUNGALOW NO 6NARs 33.90 lakhRs 29.17 lakh
BUNGALOW NO 4NARs 33.90 lakhRs 29.17 lakh
BUNGALOW NO 42NARs 33.90 lakhRs 29.17 lakh
BUNGALOW NO 81NARs 24.44 lakhRs 21.03 lakh
BUNGALOW NO 80NARs 24.44 lakhRs 21.03 lakh
BUNGALOW NO 83NARs 24.44 lakhRs 21.03 lakh
BUNGALOW NO 84NARs 24.44 lakhRs 21.03 lakh
BUNGALOW NO 5NARs 24.44 lakhRs 21.03 lakh
BUNGALOW NO 79NARs 24.44 lakhRs 21.03 lakh
BUNGALOW NO 101NARs 24.44 lakhRs 21.03 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectASHISH AGARWAL
EngineerAshish Shribhagwan Agarwal
Chartered AccountantBhavin mistry & co
Chartered AccountantNikhil Shah
Chartered AccountantSharma Radha and Associates
Chartered AccountantNitin Gala & Co.
PartnerRole in project
MADHUSUDAN LEISURE HOMES-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700019735Jun 2024 → Jun 2025

Reason as filed by the promoterContractor Suspension: The existing contractor was suspended due to consistent failure to meet project deadlines. This led to disruptions and setbacks in the project timeline, impacting progress significantly. Suspension was deemed necessary to mitigate further delays and ensure project completion within stipulated timelines. Unavailability of Skilled Manpower: Difficulty in sourcing skilled workers, particularly in rural areas, resulted in a shortage of manpower. This shortage impeded progress, slowing down construction activities and affecting project timelines. Despite extensive efforts, fi

EA11072502044Jun 2024 → Mar 2026

Reason as filed by the promoterThe project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labour and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction. However, we are trying to complete the project at the earliest. b. The cost of balance work to complete the construction is Rs. 1,32,39,764.14 /- which can be easily met out of receivable from sold units of Rs. 4,62,68,244/- The project can be complet

EA26062621542Jun 2024 → Mar 2027

Reason as filed by the promoter1. Impact of the COVID-19 Pandemic The project commenced post to the outbreak of the COVID-19 pandemic. However, from March 2020 to February 2022, construction activities were severely affected due to nationwide lockdowns, movement restrictions, and mandatory safety protocols. The pandemic caused widespread disruption in the availability of skilled and unskilled labour, as well as in the supply chain for construction materials and equipment. These constraints resulted in prolonged inactivity and slow progress on site. Despite these unprecedented conditions, continuous efforts were made to sust

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Jul 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Jan 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Jan 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed152

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 152 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A.pdf30 Jul 2026
Withdrawal Update Form 1File: Q1 FORM1.pdf29 Jul 2026
Withdrawal Update Form 2File: Form 2 Q4.pdf29 Jul 2026
Withdrawal Update Form 3File: Form 3 Q4.pdf29 Jul 2026
Withdrawal Update Form 1File: Form 1.pdf18 Jun 2026
Withdrawal Update Form 1File: Form 1.pdf18 Jun 2026
Withdrawal Update Form 1File: Form 1.pdf18 Jun 2026
Withdrawal Update Form 2File: Form 2.pdf18 Jun 2026
Withdrawal Update Form 2File: Form 2.pdf18 Jun 2026
Withdrawal Update Form 2File: Form 2 Q4.pdf18 Jun 2026
Withdrawal Update Form 3File: Form 3.pdf18 Jun 2026
Withdrawal Update Form 3File: Form 3.pdf18 Jun 2026
Withdrawal Update Form 3File: Form 3 Q4.pdf18 Jun 2026
Form 5 (FY 2024-2025)File: Form 5.pdf9 Jun 2026
Withdrawal Update Form 1File: Form 1.pdf24 Sep 2025
Withdrawal Update Form 2File: Form 2.pdf24 Sep 2025
Withdrawal Update Form 3File: Form 3.pdf24 Sep 2025
Form 1File: Architect Certificate1.pdf27 Jun 2025
Form 2File: Engineer Certificate2.pdf27 Jun 2025
Form 3File: CA Certificate Madhusudan Retreat3.pdf27 Jun 2025
Disclosure of Sold and Booked InventoryFile: Inventory.pdf27 Jun 2025
Form 1File: Architect Form 1.pdf19 Jun 2025
Form 2File: Engineer Form2 JAN 25.pdf19 Jun 2025
Form 3File: CA CERTIFICATE FORM 3.pdf19 Jun 2025
Disclosure of Sold and Booked InventoryFile: SOLD booked DSCL-31-12-24.pdf19 Jun 2025
Form 1File: 6)Architect form 1-signed.pdf18 Jun 2025
Form 2File: Annexure B Form 2 Engineer Certificate.pdf18 Jun 2025
Form 3File: CA Certificate560.pdf18 Jun 2025
Disclosure of Sold and Booked InventoryFile: 4)SOLD booked DSCL.pdf18 Jun 2025
Form 1File: Architect Form 1 .pdf18 Jun 2025
Form 2File: ENGINEERS CERTIFICATE Form 2.pdf18 Jun 2025
Form 3File: CA Certificate Form 3_Dec-22 .pdf18 Jun 2025
Disclosure of Sold and Booked InventoryFile: SOLD booked DSCL-DEC.pdf18 Jun 2025
Form 1File: Architech Certificate Form 1.pdf18 Jun 2025
Form 2File: Annexure B Form 2-Engineer Certificate.pdf18 Jun 2025
Form 3File: CA CERTIFICATE FORM 3.pdf18 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold and booked inventary.pdf18 Jun 2025
Form 1File: rera architect certificate_260422.pdf18 Jun 2025
Form 2File: Annexure -B- Form 2- Engineer Certificate.pdf18 Jun 2025
Form 3File: CA CERTIFICATE FORM 3.pdf18 Jun 2025
Disclosure of Sold and Booked InventoryFile: SOLD booked DSCL (1)-signed-signed.pdf18 Jun 2025
Form 2A (FY 2024-2025)File: Form 2A.pdf18 Jun 2025
Form 2A (FY 2023-2024)File: Letter 15 Feb 2025.pdf18 Jun 2025
Form 1File: Architect Form 1.pdf17 Jun 2025
Form 2File: Annexure -B- Form 2- Engineer .pdf17 Jun 2025
Form 3File: Bhavin Mistri & Co CA Certificate 009 Form 3_compressed.pdf17 Jun 2025
Disclosure of Sold and Booked InventoryFile: 4)SOLD booked DSCL .pdf17 Jun 2025
Form 1File: ARCHITECT CERTIFICATE.pdf16 Jun 2025
Form 2File: ENGG CERTIFICATE.pdf16 Jun 2025
Form 3File: Form 3_CA Certificate.pdf16 Jun 2025
Disclosure of Sold and Booked InventoryFile: SOLD booked DSCL-MAR.pdf16 Jun 2025
Form 1File: Architects Certficate_Retreat.pdf16 Jun 2025
Form 2File: Engineers Certificate_310723.pdf16 Jun 2025
Form 3File: Final Form 3_Madhusudan Retreat_June_2023.pdf16 Jun 2025
Disclosure of Sold and Booked InventoryFile: SOLD booked DSCL-JUNE.pdf16 Jun 2025
Form 1File: Architects Certificate_051023.pdf16 Jun 2025
Form 2File: Engg Certificate_051023 .pdf16 Jun 2025
Form 3File: CA Certificate _Form 3_Madhusudan Retreat_Sept_2023.pdf16 Jun 2025
Disclosure of Sold and Booked InventoryFile: SOLD booked DSCL-SEPT.pdf16 Jun 2025
Form 1File: Architects Certificate_051023.pdf16 Jun 2025
Form 2File: Engg Certificate_050124 .pdf16 Jun 2025
Form 3File: CA certificate M-Retreat Dec 23.pdf16 Jun 2025
Disclosure of Sold and Booked InventoryFile: SOLD booked DSCL-DEC.pdf16 Jun 2025
Form 1File: FORM 1 Architect Certificate_040424.pdf16 Jun 2025
Form 2File: Engineer certificate .pdf16 Jun 2025
Form 3File: CA certificate 1.pdf16 Jun 2025
Disclosure of Sold and Booked InventoryFile: SOLD booked DSCL-31-3-24.pdf16 Jun 2025
Form 5 (FY 2021-2022)File: Form 5 21-22.pdf13 Jun 2025
Form 5 (FY 2023-2024)File: Form 5 23-24.pdf13 Jun 2025
Commencement Certificates / NA Order for plotted developmentFile: Madhusudan Retreat CC.pdf21 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form_2A UDL ARCHITECTS.pdf24 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate - M Retreat.pdf11 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1.pdf15 Jan 2025
Disclosure of sold/ booked inventoryFile: SOLD booked DSCL-31-12-24.pdf4 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM - 5 RETREAT 23-24.pdf17 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect letter.pdf25 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Rera Doc.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: SOLD AND BOOKED.pdf15 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Retreat .pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate_090724.pdf9 Jul 2024

How this compares with Thane

49%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 33 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MADHUSUDAN RETREAT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near THANE7,600+ in Thane

Builder: MADHUSUDAN LEISURE HOMES

MADHUSUDAN LEISURE HOMES has 2 registrations on MahaRERA, including MADHUSUDAN RETREAT and MADHUSUDAN RETREAT TERRACES. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if MADHUSUDAN RETREAT is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MADHUSUDAN RETREAT?

The registered promoter entity is MADHUSUDAN LEISURE HOMES, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MADHUSUDAN RETREAT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MADHUSUDAN RETREAT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MADHUSUDAN RETREAT?

The professionals named in the filing: Architect: ASHISH AGARWAL; Engineer: Ashish Shribhagwan Agarwal; Chartered Accountant: Bhavin mistry & co; Chartered Accountant: Nikhil Shah; Chartered Accountant: Sharma Radha and Associates; Chartered Accountant: Nitin Gala & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MADHUSUDAN RETREAT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MADHUSUDAN RETREAT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MADHUSUDAN RETREAT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.