Registration approved Residential/Group Housing project

Life+ at Godrej Eternity

By Godrej Home Constructions Private Limited

RG-KA-49393 · RERA PRM/KA/RERA/1251/310/PR/171102/002199

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Jul 2023Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 57 documents Report an error

Life+ at Godrej Eternity is a Residential/Group Housing project by Godrej Home Constructions Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/171102/002199 on 2 Nov 2017. Possession is promised by 31 Jul 2023. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameLife+ at Godrej Eternity
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/171102/002199
  • ReraGenie IDRG-KA-49393

Builder

  • NameGodrej Home Constructions Private Limited
  • Entity typeCompany
  • CINU70102MH2015PTC263486
  • Authorized SignatoryUday Bhaskar
  • DirectorsKaran Bolaria, Rajendra Khetawat
  • Other registrations2 more →

Key dates

this monthRegisteredNov 2017First promiseOct 2022Revised toJul 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on2 Nov 2017
  • Promised completion31 Jul 2023
  • Revised completionRevised to 31 Jul 2023 (originally 31 Oct 2022)
  • Buildings5 building records
  • Documents filed57 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C---56056
D---52052
E---40040
F---68068
G---84084

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
Ground Clearance-
Earth Excavation-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etcNot applicable
Plastering inside , outside & CeilingNot applicable
Joinery: Doors, Windows, Ventilators etcNot applicable
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)Not applicable
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities42

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalNoNot applicable
Water conservationYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupNoNot applicable
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-
Water Tanks, Sumps And Other Electrical EquipmentYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area23,526 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 146.16 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRamesh Kumar M.B
EngineerDesignTree Service Consultants Pvt Ltd

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionOct 2022 → Jul 2023

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed57

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/171102/002199 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Company Incorporation Certificate.pdf-
Commencement Certificate for Building from BMICAPA dated 21-04-2016-
Eternity DP or Single site plan-
Eternity DP or Single site plan-
DEED OF SALE-
ATS-
Sale Deed-
Section-
site_plan-
Application FORM-Allotment Letter- Eternity-
Godrej-Eternity-Brochure-
Speci-
EC-
Khata ( Kanakpura)-
Sale Deed-
ETERNITY Conversion orders (1)-
BESCOM NOC-
BWSSB NOC-
KSPCB 11th April 2016-
EC MOEF NOC-
BSNL NOC-
Unnamed document-
Section-
Section-
Balance Sheet 2016 - 2017File: Blank Document.pdf-
Balance Sheet 2015 - 2016File: Balancesheet 2015.pdf-
Balance Sheet 2014 - 2015File: Blank Document.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Blank Document.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Profit Loss 2015.pdf-
Audited Profit and Loss Statement 2014 - 2015File: Blank Document.pdf-
Director's Report 2016 - 2017File: Blank Document.pdf-
Director's Report 2015 - 2016File: Blank Document.pdf-
Director's Report 2014 - 2015File: Blank Document.pdf-
Cash Flow Statement 2016 - 2017File: Blank Document.pdf-
Cash Flow Statement 2015 - 2016File: Cash Flow 2015.pdf-
Auditor's Report 2016 - 2017File: Blank Document.pdf-
Auditor's Report 2015 - 2016File: Audit Report 2015.pdf-
Auditor's Report 2014 - 2015File: Blank Document.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: Blank Document.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: IT returns.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: Blank Document.pdf-
Form-B-
Prospectus/BrochureFile: Life+ Flipchart.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_171102_002199 (2).xlsx-
Stability CertificateFile: STABILITY CERTIFICATE.PDF-
Occupancy CertificateFile: Partial OC - Life plus.pdf-
Consent for operation issued by KSPCBFile: CFO - Eternity - Life+ - Zest.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: license 10_38_LT13024_EI000110539419.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: BWSSB NOC.pdf-
Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: Confirmation.pdf-
Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: Confirmation.pdf-
Details of undivided share of land handed over to the association of allotteesFile: Eternity DOD.pdf-
Architect certificate for having completed the work(in format no 5)File: Form-5 Architect (QU) JULY 23.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: CA GODREJ HOME CONSTR-LIFE_compressed.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Form -6 Engineer (QU) Life plus-R1.pdf-
Engineer CertificateFile: Form -6 Engineer (QU) Life plus-R1.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Life+ at Godrej Eternity on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmLife+ at Godrej EternityOther 36Dot size: filed unitsN

Filed coordinates, straight-line distance. 36 registered projects within 2 km.

Builder: Godrej Home Constructions Private Limited

Godrej Home Constructions Private Limited has 3 registrations on RERA Karnataka, including Godrej Eternity and Zest at Godrej Eternity. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Life+ at Godrej Eternity is delayed beyond 31 Jul 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Life+ at Godrej Eternity?

The registered promoter entity is Godrej Home Constructions Private Limited, a company as per the filing. Its CIN U70102MH2015PTC263486 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Life+ at Godrej Eternity?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Life+ at Godrej Eternity?

The professionals named in the filing: Architect: Ramesh Kumar M.B; Engineer: DesignTree Service Consultants Pvt Ltd. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Life+ at Godrej Eternity?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Life+ at Godrej Eternity. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Life+ at Godrej Eternity to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.