LE PALAZZO
RG-MH-54547 · RERA P51900012304 · Last updated on MahaRERA portal: 8 Oct 2024
Source: official MahaRERA filing
Red flags
- 15 complaints at MahaRERA
- Completion date moved by 88 months
- 2 extensions taken
- Rs 770.00 crore secured on the land, in favour of EDELWEISS ASSET RECONSTRUCTION COMPANY LIMITED, VSJ INVESTMENTS PRIVATE LIMITED
- The charge is held by EDELWEISS ASSET RECONSTRUCTION COMPANY LIMITED, a distressed-debt buyer or stressed-asset fund rather than an originating lender
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
LE PALAZZO is a Others project by Sri Harsh Developers in NANA CHOWK, 400036, registered with MahaRERA as P51900012304 on 1 Sep 2017. The registration is recorded completed; possession was promised by 31 Aug 2026. The completion date has moved by 88 months from the original filing. 15 complaints are on record with the regulator.
At a glance
Project
- NameLE PALAZZO
- TypeOthers
- Location
- A.K MARG ROAD
- NANA CHOWK
- 400036
- Pincode400036
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900012304
- ReraGenie IDRG-MH-54547
Builder
- NameSri Harsh Developers
- Entity typePartnership
- GSTIN27AABFS2490M1ZU
- Partnersvijay chhotalal kamdar, SRI KHODIAR REALTECH SYNDICATION PVT LTD SRI KHODIAR REALTECH SYNDICATION PVT LTD
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on1 Sep 2017
- Promised completion31 Aug 2026
- Revised completionRevised to 31 Aug 2026 (originally 30 Apr 2019)
- Buildings1 building record
- Documents filed55 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| LE PALAZZO | NA | 44 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 8 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 90%.
LE PALAZZO: 85% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 8 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SPACE AGE CONSULTANTS |
| Engineer | DEEPAK SHAH |
| Chartered Accountant | S.U. RADHAKRISHNANI & CO |
| Chartered Accountant | mayur himatlal |
| Partner | Role in project |
|---|---|
| Sri Harsh Developers | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThis project is developed under 33(7) MHADA Scheme. And due to tenants legal and technical issues we couldn't complete the project and obtain O.C.
Reason as filed by the promoterWe required extension till 28.08.2026, due to various reasons and all the reasons are attached in the document upload tab
Complaints filed with MahaRERA15
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000012088 | Mr koimavalappil v madhusudhan and Mrs koimavalappil m harsha | SRI HARSH DEVELOPERS | 27/11/2017 |
| CC006000000057385 | JITENDRA KANTILAL SHAH AND OTHERS | SRI HARSH DEVELOPERS | 20/12/2018 |
| CC006000000110654 | Shah Investments | Sri Harsh Developers | 23/08/2019 |
| CC006000000110652 | Usha Metal Works | Sri Harsh Developers | 23/08/2019 |
| CC006000000110653 | Usha Metal Works | Sri Harsh Developers | 23/08/2019 |
| CC006000000197070 | Pinakin Laxmichand Shah | Sri Harsh Developers | 25/05/2021 |
| CC006000000197069 | Shailesh Kantilal Shah | Sri Harsh Developers | 25/05/2021 |
| CC006000000197082 | Shailesh Kantilal Shah | Sri Harsh Developers | 26/05/2021 |
| CC006000000197085 | Zeni Shailesh Shah | Sri Harsh Developers | 26/05/2021 |
| CC006000000197072 | Ankur J. Shah HUF through Karta Ankur Jitendra Shah | Sri Harsh Developers | 25/05/2021 |
| CC006000000197084 | Ramesh Kantibhai Patani | Sri Harsh Developers | 26/05/2021 |
| CC006000000197883 | Sanjana Cryogenic Storages Limited | Sri Harsh Developers | 09/09/2021 |
| CC006000000198267 | Manju Ramesh Vardhan | Sri Harsh Developers | 06/09/2021 |
| CC006000000198362 | Meenakshi Nitin Shah | Sri Harsh Developers | 18/09/2021 |
| CC006000000479925 | Mrs. Manju Ramesh Vardhan | Sri Harsh Developers | 04/04/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed55
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - Architect Certificate March 2024.pdf | 8 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - Architect Certificate June 2024.pdf | 8 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - Architect Certificate Sept 2024.pdf | 8 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2 - Engineer Certificate March 2024.pdf | 8 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 June 2024.pdf | 8 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 September 2024.pdf | 8 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 Updated_compressed.pdf | 8 Oct 2024 |
| Declaration in FORM BFile: Form B - Affidavit cum Declaration New.pdf | 8 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold or Booked Inventory.pdf | 8 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 2023 - 24.pdf | 8 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Scan 08-Oct-2024.pdf | 8 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Scan 08-Oct-2024.pdf | 8 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Scan 08-Oct-2024.pdf | 8 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Scan 08-Oct-2024.pdf | 8 Oct 2024 |
| Declaration in FORM BFile: Form B - Affidavit cum Declaration New.pdf | 8 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - Architect Certificate March 2024.pdf | 8 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - Architect Certificate June 2024.pdf | 8 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - Architect Certificate Sept 2024.pdf | 8 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 Updated_compressed.pdf | 8 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2 - Engineer Certificate March 2024.pdf | 8 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 June 2024.pdf | 8 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 September 2024.pdf | 8 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Scan 08-Oct-2024.pdf | 8 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Scan 08-Oct-2024.pdf | 8 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold or Booked Inventory.pdf | 8 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Scan 08-Oct-2024.pdf | 8 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Scan 08-Oct-2024.pdf | 8 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 2023 - 24.pdf | 8 Oct 2024 |
| Declaration in FORM BFile: FormB.pdf | 9 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A.pdf | 29 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure.pdf | 29 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form5.pdf | 29 Dec 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf | 26 Dec 2023 |
| Certificates of CA (Form 3)File: FORM3Certificate.pdf | 17 Dec 2023 |
| Declaration about Commencement CertificateFile: DeclarationCC.pdf | 16 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold OR Booked Inventory - Le Palazzo.pdf | 16 Dec 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DisclosureofInterestinOtherRealEstateOrg.pdf | 16 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form5 with udin.pdf | 16 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form5 with udin.pdf | 16 Dec 2023 |
| Architect’s Certificate on Completion of Project (Form 4)File: architects certificate shd_1.pdf | 3 Oct 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 23 Mar 2018 |
| Details of encumbrancesFile: Affidavit Cum Declaration - Nanachowk1.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Affidavit Cum Declaration - Nanachowk1.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CERTIFICATE OF C A - LE- PANAZZO.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG NANACHOWCK.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: CERTIFICATE OF C A - LE- PANAZZO.pdf | 31 Jul 2017 |
| Layout approvalFile: layout.pdf | 30 Jul 2017 |
| Building plan approvalFile: I O D.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: compressed_title certificate (2011) shd.pdf | 30 Jul 2017 |
| Details of encumbrancesFile: IMG_20170730_223818.pdf | 30 Jul 2017 |
| Details of encumbrancesFile: IMG_20170730_223831.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: layout.pdf | 30 Jul 2017 |
| Building Plan Approval (IOD)File: I O D.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: Draft Agreement for Sale - Le Palazzo.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: DRAFT Allotment Letter - Le Palazzo.pdf | 30 Jul 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Aster | sri parstha complex, station road, Nallasopara West | 100 | Completed | Apr 2004 | Late, Sep 2005 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 55 filed documents as one ZIP, foldered, with a manifest
Keep LE PALAZZO on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NANA CHOWK
Filed coordinates, straight-line distance. 3 registered projects within 2 km.
SESEN
SESEN REALTY PVT LTD
SANJANA HEIGHTS
SAFEWAY PROJECTS PVT LTD
CRESCENT TOWER
CRESCENT BUILDERS
Lifescapes Altimo
Peccadily Estate Pvt Ltd
Terraces Forjett Hill
Suparshva Incorporation
Builder: Sri Harsh Developers
Sri Harsh Developers has 1 registration on MahaRERA, including LE PALAZZO. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record.
Frequently asked questions
What are my rights if LE PALAZZO is delayed beyond 31 Aug 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of LE PALAZZO?
The registered promoter entity is Sri Harsh Developers, a partnership as per the filing. Its GSTIN 27AABFS2490M1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in LE PALAZZO?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against LE PALAZZO?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for LE PALAZZO?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at LE PALAZZO?
The professionals named in the filing: Architect: SPACE AGE CONSULTANTS; Engineer: DEEPAK SHAH; Chartered Accountant: S.U. RADHAKRISHNANI & CO; Chartered Accountant: mayur himatlal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in LE PALAZZO?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.