LAVIVANT

By ATCO Projects Private Limited

RG-KA-85944 · RERA PRM/KA/RERA/1251/308/PR/090623/005986 · Last updated on RERA Karnataka portal: 22 Aug 2026

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Jan 2030Possession promisedno revision filed
2 of 18Construction stages donefurthest along: Upto Plinth Level, 90%
279 of 521Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 276 documents Report an error

LAVIVANT is a Residential/Group Housing project by ATCO Projects Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/090623/005986 on 9 Jun 2023. Possession is promised by 25 Jan 2030. 242 of the 521 units on this registration are recorded sold or booked, and 2 of 18 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameLAVIVANT
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/090623/005986
  • ReraGenie IDRG-KA-85944

Builder

  • NameATCO Projects Private Limited
  • Entity typeCompany
  • CINU70109DL2006PTC152452
  • GSTIN29AACCV3344H1Z8
  • Authorized SignatoryGAVRAV KUMAR GUPTA
  • MANAGING DirectorGAVRAV KUMAR GUPTA
  • DirectorsGAVRAV KUMAR GUPTA, RAM KRISHNA KUMAR
  • Project HeadGAVRAV KUMAR GUPTA
  • Declared earlier projects1 →

Key dates

this monthRegisteredJun 2023PromisedJan 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on9 Jun 2023
  • Promised completion25 Jan 2030
  • Revised completionNone
  • Buildings7 building records
  • Documents filed276 files

Current status

46%242 of 521 units booked
21.7%Of the estimated cost spent so far

Figures as on 22 Aug 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block 1---28028
Block 2---30030
Block 3---30030
Block 4---22022
Block 5---27027
Block 6---2880288
Block 7---96096

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 22 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 18 construction stages are filed complete. The stage furthest along is Upto Plinth Level, at 90%.

Building: 56% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level90%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)90%
Retaining wall (All types)90%
RCC or MS Framed structure70%
Masonry Construction65%
Plastering inside , outside & Ceiling60%
Joinery: Doors, Windows, Ventilators etc40%
Basic work of Water supply, Sanitary and Electrification50%
Dadoing, Skirting, Flooring, Tiles work (All types)40%
Railing and Grill fixing25%
Electrification, Water supply and Sanitary Finishing40%
Painting25%
Fire prevention and fire fighting fitting and fixture with network10%
Weather Proof work(tile,concrete)50%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work50%
Internal and External work including landscapes as per sanctioned drawings10%

Progress on shared amenities40

As on 22 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes60%
Sewage and Drainage SystemYes60%
Water conservation/rain water harvesting/recharge of ground waterYes20%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes10%
Emergency Evacuation servicesYes1%
Internal Roads & FootpathsYes60%
Electricity supply transformer and substationYes0%
Storm water drainsYes40%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes40%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityNoNot applicable
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes50%
LiftsYes0%
Corridor/LobbiesYes50%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes80%
TerraceYes60%
Outer WallYes100%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes0%
Common storage spacesYes0%

Land and ownership12

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners12
LandownerVillageDistrict
ATCO Projects Private Limited--
Atco Infrastructure pvt ltd--
ATCO Projects Private Limited--
Atco Infrastructure pvt ltd--
Atco Infrastructure pvt ltd--
ATCO Projects Private Limited--
ATCO Projects Private Limited--
Atco Infrastructure pvt ltd--
Atco Infrastructure pvt ltd--
ATCO Projects Private Limited--
ATCO Projects Private Limited--
Atco Infrastructures Pvt Ltd--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 409.02 cr
Cost incurredRs 88.60 cr
Spent of the estimate21.66%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 409.02 crRs 18.99 cr
On-site expenditure-Salaries of workers-Rs 69.62 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRachita Bhonsle
EngineerPRAVEEN B V
Chartered AccountantM/s. SANJAY K PATHAK & ASSOCIATES

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
01007/2025-ATCO Projects Private Limited08/08/2025

Documents filed276

As listed on the registration, under the names the promoter filed them with; the newest 80 of 276 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/090623/005986 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CERTIFICATE_compressed.pdf22 Aug 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: SIGNATURE & SEALED Copy-Form-5, Architect (Quarter-1 2026-27).pdf22 Aug 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6-Engineer Quarter-1 2026-2027.pdf22 Aug 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CERTIFICATE_compressed.pdf8 Aug 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Q4 2025-26.pdf8 Aug 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6-Engineer Quarter-4 2025-2026.pdf8 Aug 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4 CERTIFICATE_compressed.pdf19 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Q3 2025-26.pdf19 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6-Engineer Quarter-3 2025-2026.pdf19 Feb 2026
Sy No 68-1 Legal ReportFile: 68-1 Legal Report.pdf2 Jun 2023
Sy No 68-1 Old RTCFile: RTC 1969 to 2001.pdf2 Jun 2023
Sy No 68-1 - New Computer RTCFile: New Computer RTC.pdf2 Jun 2023
Sy No 68-1 All Mutation RegistrarFile: mr .pdf2 Jun 2023
Survey Records sy no 68-1 Mulla Tippani and Hissa TippaniFile: Survey Records.pdf2 Jun 2023
Sy No 68-1AkarbandhFile: Akarband.pdf2 Jun 2023
Sale Deed in the Name of N.V DevikaFile: Sale Deed 2247 -2006-07.pdf2 Jun 2023
Sy No 68-1 Sale Deed in the name Atco InfraFile: SALE DEED INFRA 68-1.pdf2 Jun 2023
Sy No 68-1 Sale Deed in the name of Atco ProjectsFile: sale deed 68-1(0-16 guntas).pdf2 Jun 2023
Sy No 68-1 Sale Deed in the name of Atco ProjectsFile: sale deed 68-1(0-14-12 guntas).pdf2 Jun 2023
EC for SY No 68-1 Old and NewFile: EC 1964 to 2022.pdf2 Jun 2023
Survey Number 68-2 Legal ReportFile: 68-2 Legal Report.pdf2 Jun 2023
Sy No 68-2 Old RTCFile: Old RTC.pdf2 Jun 2023
Sy No 68-2 New Computer RTCFile: New RTC.pdf2 Jun 2023
Sy No 68-2 all mutation registrarFile: aLL mr 68-2.pdf2 Jun 2023
Sale Deed in the name of Muniswamy Reddy and Devika NFile: Sale Deed Doc No 3719-2014-15.pdf2 Jun 2023
Survey Records, Mulla Tippani and Hissa Tippani of sy no 68-2File: Survey Records.pdf2 Jun 2023
Sh No 68-2 AkarbandhFile: Akarbandh.pdf2 Jun 2023
Sale Deed in the name of Atco Infra Sy No 68-2File: SALE DEED INFRA 68-2.pdf2 Jun 2023
Sale Deed in the name of Atco Projects Sy No 68-2File: Sale deed 68-2(0-01-04 guntas).pdf2 Jun 2023
Sy No 68-2 Old and New ECFile: EC from 1920 to till.pdf2 Jun 2023
Sy No 68-3 Legal ReportFile: 68-3 Legal Report.pdf2 Jun 2023
Sy No 68-3 Old RTCFile: 7-RTC1969 to 2001.pdf2 Jun 2023
Sy No 68-3 Computer RTCFile: 8-RTC Computer RTC.pdf2 Jun 2023
Sy No 68-3 all Mutation registrarFile: 13ALL MR 68-3.pdf2 Jun 2023
Sy No 68-3 Survey Records, Mulla Tippani and Hissa TippaniFile: 11-Survey Records.pdf2 Jun 2023
Sy No 68-3 AkarbandhFile: 14-Akarband.pdf2 Jun 2023
Sy No 68-3 Sale deed in the name of N DevikaFile: 6-Sale deed 1324-2009-10.pdf2 Jun 2023
Sy No 68-3 Sale Deed in the name of Atco ProjectsFile: 3-Sale Deed 2981-2019-20.pdf2 Jun 2023
Sy No 68-3 Sale Deed in the name of Atco InfraFile: 4-Sale Deed 2987-2019-20.pdf2 Jun 2023
Sy No 68-3 Old and New ECSFile: 17-Ec 1920 to 2022.pdf2 Jun 2023
Sy No 71 Legal ReportFile: 71 Legal Report.pdf2 Jun 2023
Sy No 71 Old RTCFile: Old RTC.pdf2 Jun 2023
Sy No 71 New RTCFile: New RTC.pdf2 Jun 2023
Sy No 71 All Mutation RegistrarFile: ALL MR 71.pdf2 Jun 2023
Sy No 71 Survey RecordsFile: Survey Records.pdf2 Jun 2023
Sy no 71 AkarbandFile: Akarband.pdf2 Jun 2023
Sy No 71 Sale Deed in the name of DevikaFile: Sale Deed to N V Devika Doc No 2263-2006-07.pdf2 Jun 2023
Sy No 71 Sale Deed in the name of Atco InfraFile: Sale Deed Doc No 2983-2019-20.pdf2 Jun 2023
Sy No 71Sale deed in the name of Atco ProjectsFile: Sale Deed Doc No 2986-2019-20.pdf2 Jun 2023
Sy no 71 Old ad New ECSFile: EC from 1920 to till date.pdf2 Jun 2023
Legal Report of SY No 72-3 & 72-5File: 72-3 & 72-5 Legal Report.pdf2 Jun 2023
sy no 72-3 Old RTCFile: old RTC 72-3.pdf2 Jun 2023
sy no 72-3 & 72-5 new rtcFile: New RTC 72-3 & 5.pdf2 Jun 2023
sy no 72-3 & 72-5 all mutation registrarFile: All MR 72-3 & 5.pdf2 Jun 2023
72-3 & 72-5 AkarbandhFile: Akarband.pdf2 Jun 2023
sale deed in the name of DevikaFile: SALE DEED 2.pdf2 Jun 2023
Sale Deed in the name of muniswamy ReddyFile: SALE DEED.pdf2 Jun 2023
Sale deed in the name of Atco InfraFile: sale deed INFRA 72-3.pdf2 Jun 2023
EC for sy no 72-3 & 5File: pdf24_merged (6).pdf2 Jun 2023
Sale Deed 72-5 in the name of Atco projectsFile: sale deed ATCO PROJECTS 72-5.pdf2 Jun 2023
Sale Deed 72-3 in the name of Atco projectsFile: sale deed ATCO PROJECTS 72-3.pdf2 Jun 2023
sy no 73-3 legal reportFile: 73-3 Legal Report.pdf2 Jun 2023
sy no 73-3 old RTCFile: Old RTC.pdf2 Jun 2023
sy no 73-3 new rtcFile: New RTC.pdf2 Jun 2023
sy no 73-3 all mutation registrarFile: ALL MR.pdf2 Jun 2023
sy no 73-3 survey records and mulla tippani and hissa tippaniFile: Survey Records.pdf2 Jun 2023
sy no 73-3 AkarbandhFile: Akarbandh.pdf2 Jun 2023
73-3 sake deed in the name muniswamy reddyFile: Doc No 1703-2007-08.pdf2 Jun 2023
73-3 sale deed in the name of atco infraFile: sale deed INFRA 73-3.pdf2 Jun 2023
73-3 EC old and NewFile: E from 1920 to till date.pdf2 Jun 2023
need notarized Non-Litigation Affidavit on stamp paper.File: AFFIDAVIT - No Cases.pdf2 Jun 2023
Form-B require to mention end date in DD/MM/YYFile: New form B for RERA.pdf2 Jun 2023
Guidance valueFile: Guidance value - HANDENAHALLI.pdf2 Jun 2023
KSPCB NOCFile: kspcb.pdf2 Jun 2023
Carpet Area Mentioned in the project details Page not matching with the sanction plan clarify / uplFile: Engneer certificate for Carpet area.pdf2 Jun 2023
Upload Single plot layout OrderFile: BMRDA Approval for Singale Lyaout Order No APA-LAO-19-2021-22, dated 29-07-2022.pdf2 Jun 2023
Upload certified Carpet area calculationFile: Engneer certificate for Carpet area.pdf2 Jun 2023
cdp plan - yellow zoneFile: Handenahalli 67 LU (1)- CDP.pdf2 Jun 2023
clarification for CDPFile: change of land use clarification.pdf2 Jun 2023
village map showing the proposed siteFile: Village Map.pdf2 Jun 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
ATCO SAPPHIRESy.No.502/1, 502/2, Khatha No.3081/1283,3082/1284, Sarjapura Village, Sarjapura Hobli, Anekal TalukCompleted-No date filed

How this compares with Bengaluru Urban

46%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep LAVIVANT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: ATCO Projects Private Limited

ATCO Projects Private Limited has 1 registration on RERA Karnataka, including LAVIVANT. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if LAVIVANT is delayed beyond 25 Jan 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of LAVIVANT?

The registered promoter entity is ATCO Projects Private Limited, a company as per the filing. Its CIN U70109DL2006PTC152452 and GSTIN 29AACCV3344H1Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in LAVIVANT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against LAVIVANT?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at LAVIVANT?

The professionals named in the filing: Architect: Rachita Bhonsle; Engineer: PRAVEEN B V; Chartered Accountant: M/s. SANJAY K PATHAK & ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LAVIVANT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LAVIVANT. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LAVIVANT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.