ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / LANAI By PCOC

Registration approved Residential/Group Housing project

LANAI By PCOC

By PCOC Eastland Structures LLP

RG-KA-86169 · RERA PRM/KA/RERA/1251/310/PR/171223/001579

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Dec 2019Possession promisedmoved 12 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 57 documents Report an error

LANAI By PCOC is a Residential/Group Housing project by PCOC Eastland Structures LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/171223/001579 on 23 Dec 2017. Possession is promised by 31 Dec 2019. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameLANAI By PCOC
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/310/PR/171223/001579
  • ReraGenie IDRG-KA-86169

Builder

  • NamePCOC Eastland Structures LLP
  • Entity typeOther
  • Authorized SignatoryAbdul Mueed Kadli
  • OthersHasaan Kadli

Key dates

this monthRegisteredDec 2017First promiseDec 2018Revised toDec 2019

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on23 Dec 2017
  • Promised completion31 Dec 2019
  • Revised completionRevised to 31 Dec 2019 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed57 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LANAI---15015

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemNoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes-
Swimming PoolNoNot applicable
GymYes-
ParksNoNot applicable
Power BackupNoNot applicable
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area941 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 12.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectStudio Parametric architects ind pvt ltd
EngineerPalaksha V.G.

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/310/PR/200103/001579Dec 2018 → Dec 2019

Reason as filed by the promoterFinancial crunch

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed57

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/171223/001579 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Certificate of LLP Incorporation.PDF-
Architect Certificate for Work Completion Schedule till DateFile: Arch - RERA.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer certificate.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Proposed.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Proposed.pdf-
CA Certificate for Funds required for Project CompletionFile: Proposed.pdf-
AffidavitFile: FORM B (1).pdf-
Latest Encumbrance Certificate-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Document 1File: Affidevite.pdf-
Document 2File: Apr 18 to May 19.pdf-
Document 3File: Challan a.pdf-
Document 4File: DD.pdf-
Document 5File: Apr 17 to Mar 18.pdf-
Document 6File: Affidevit Sec18.pdf-
Document 7File: CA certificate.pdf-
Document 8File: funds requiement certificate.pdf-
Document 9-
Commencement certificate-
Plan-
Site Plan-
Sale Deed-
Plan-
Site Plan-
Brouchers-
PES?LAN?009-ilovepdf-compressed-
Brouchers-
Encumbrance Certificate 1-
BDA Khata-
BDA-
Balance Sheet 2015 - 2016File: NOT Aplicable.pdf-
Balance Sheet 2014 - 2015File: NOT Aplicable.pdf-
Balance Sheet 2013 - 2014File: NOT Aplicable.pdf-
Audited Profit and Loss Statement 2015 - 2016File: NOT Aplicable.pdf-
Audited Profit and Loss Statement 2014 - 2015File: NOT Aplicable.pdf-
Audited Profit and Loss Statement 2013 - 2014File: NOT Aplicable.pdf-
Director's Report 2015 - 2016File: NOT Aplicable.pdf-
Director's Report 2014 - 2015File: NOT Aplicable.pdf-
Director's Report 2013 - 2014File: NOT Aplicable.pdf-
Cash Flow Statement 2015 - 2016File: NOT Aplicable.pdf-
Cash Flow Statement 2014 - 2015File: NOT Aplicable.pdf-
Auditor's Report 2015 - 2016File: NOT Aplicable.pdf-
Auditor's Report 2014 - 2015File: NOT Aplicable.pdf-
Auditor's Report 2013 - 2014File: NOT Aplicable.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: NOT Aplicable.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: NOT Aplicable.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: NOT Aplicable.pdf-
FORM B-
Prospectus/BrochureFile: e-Brochure--1.pdf-
Advertisement Copy 1File: Image1.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_310_PR_171223_001579.xlsx-
Delay ReasonFile: Document1.pdf-
NOC issued by the Fire Force department after completion of workFile: NOC FIRE.pdf-
Occupancy CertificateFile: Pcoc Oc copy.pdf-
Consent for operation issued by KSPCBFile: NOC BESCOM.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: NOC BWSSB.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit cum declaration.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep LANAI By PCOC on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: PCOC Eastland Structures LLP

PCOC Eastland Structures LLP has 1 registration on RERA Karnataka, including LANAI By PCOC. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if LANAI By PCOC is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of LANAI By PCOC?

The registered promoter entity is PCOC Eastland Structures LLP. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in LANAI By PCOC?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at LANAI By PCOC?

The professionals named in the filing: Architect: Studio Parametric architects ind pvt ltd; Engineer: Palaksha V.G.. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LANAI By PCOC?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LANAI By PCOC. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LANAI By PCOC to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.