ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / LALBAG VILLA

Registered No litigation declared Residential / Group Housing project

LALBAG VILLA

By RELIABLE PROPERTIES

RG-MH-63502 · RERA P52100053287 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Feb 2027Possession promisedmoved 12 months from the original
3 of 11Construction stages donefurthest along: Staircases, 90%
16 of 24Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 76 documents Report an error

LALBAG VILLA is a Residential / Group Housing project by RELIABLE PROPERTIES in Pune, Maharashtra, registered with MahaRERA as P52100053287 on 23 Oct 2023. Possession is promised by 6 Feb 2027. The completion date has moved by 12 months from the original filing. 8 of the 24 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameLALBAG VILLA
  • TypeResidential / Group Housing
  • Location
    • Manchar Road
    • Manchar
    • Mordewadi
    • Ambegaon
    • Pune
    • 410503
  • Pincode410503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100053287
  • ReraGenie IDRG-MH-63502

Builder

  • NameRELIABLE PROPERTIES
  • Entity typePartnership
  • PartnersPRASHANT BHIVSEN BAGAL, BALKRISHNA MAHADU SAWANT, SUMIT GANPAT KALE, AVDHUT TUKARAM SHETE
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredOct 2023First promiseFeb 2026Revised toFeb 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Oct 2023
  • Promised completion6 Feb 2027
  • Revised completionRevised to 6 Feb 2027 (originally 6 Feb 2026)
  • Buildings1 building record
  • Documents filed76 files

Current status

33%8 of 24 units booked
42.7%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LALBAG VILLANA3324024

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.

LALBAG VILLA: 45% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes70%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed24

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots24
Closed/Covered24

Land and ownership7

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners7
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Jun 2025
LandownerVillageDistrict
PUSHPA RAGHUNATH SHINDEManchar (CT)Pune
Kisan Ganpat BagalAmbegaonPune
Popat Bhanudas BagarMordewadiPune
Sakharam Ganpat BagalAmbegaonPune
Bhivsen Ganpat BagalAmbegaonPune
Tukaram Ganpat BagalAmbegaonPune
Vinod Bhanudas BagalManchar (CT)Pune

Approvals and building plan

Sanctioning authorityMANCHAR NAGARPANCHAYAT, MANCHAR
Permissible FSI2876.22
Proposed, not sanctioned2,876 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMANCHAR, PUNE 410503
Estimated costRs 4.66 cr
Cost incurredRs 1.99 cr
Work done42.72%
BuildingWingEstimatedIncurred
LALBAG VILLANARs 4.66 crRs 1.99 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSACHIN LADKAT & ASSOCIATE
EngineerAVDHUT SHETE
EngineerKAJAL ARJUN BORKAR
EngineerRATHIS GROUP
Chartered AccountantSANTOSH SUTAR
Chartered AccountantPGMJ & ASSOCIATES
Chartered AccountantNITISH VAIDYA & ASSOCIATES
PartnerRole in project
RELIABLE PROPERTIES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA20012619512Feb 2026 → Feb 2027

Reason as filed by the promoterThe progress of our project was unavoidably delayed mainly because temporary financial constraints arising from certain personal reasons, which adversely affected the availability of funds and slowed down construction activities. The said constraints have since been addressed, and necessary financial arrangements have been made. Construction work has resumed and is progressing steadily. All efforts are being made to complete the remaining work at the earliest.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Sep 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Aug 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Aug 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 6 Feb 2027

Documents filed76

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Q1 FY 2026-27.pdf20 Jul 2026
Withdrawal Update Form 2File: Form 2 Q1 FY 2026-27.pdf20 Jul 2026
Withdrawal Update Form 3File: Form 3 Q1 FY 2026-27.pdf20 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A FY 25-26.pdf9 Jun 2026
Withdrawal Update Form 1File: Form 1.pdf19 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf19 Apr 2026
Withdrawal Update Form 3File: Form 3.pdf19 Apr 2026
Form 2A (FY 2024-2025)File: Form 2A Final.pdf26 Feb 2026
Withdrawal Update Form 1File: Form 1.pdf19 Jan 2026
Withdrawal Update Form 2File: Form 2.pdf19 Jan 2026
Withdrawal Update Form 3File: Form 3.pdf19 Jan 2026
Form 5 (FY 2023-2024)File: Form 5 Final.pdf17 Nov 2025
Form 5 (FY 2024-2025)File: Form 5 Final.pdf17 Nov 2025
Withdrawal Update Form 1File: Form 1 Final.pdf19 Oct 2025
Withdrawal Update Form 2File: Form 2 Final.pdf19 Oct 2025
Withdrawal Update Form 3File: Form 3 Final.pdf19 Oct 2025
Withdrawal Update Form 1File: Form 1 Final.pdf16 Oct 2025
Withdrawal Update Form 2File: Form 2 Final.pdf16 Oct 2025
Withdrawal Update Form 3File: Form 3 Final.pdf16 Oct 2025
Form 2File: Form 2.pdf19 Jul 2025
Form 3File: Form 3 Final.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Cir (1).pdf19 Jul 2025
Form 1File: Form 1 Final.pdf19 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Cir (1).pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 Final.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Final.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Final.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Final.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3 (Q2 24-25).pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Final.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3 (Q2 24-25).pdf16 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3 (Q1 24-25).pdf16 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3 (Q4 23-24).pdf16 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3 (Q3 23-24).pdf16 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf16 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf16 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf16 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf16 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf16 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf16 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf16 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Circular.pdf16 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: PLAN3compressed.pdf1 Oct 2023
Other - TechnicalFile: PLAN3compressed.pdf1 Oct 2023
Other - TechnicalFile: Email to Authority.pdf29 Sep 2023
Copy of the legal title reportFile: Search Report Reliable Properties reracompressed.pdf10 Sep 2023
Proforma of Allotment letterFile: Allotment letter new lalbaug.pdf10 Aug 2023
Proforma of Agreement for saleFile: Reliable Model agreement as per RERA.pdf10 Aug 2023
Layout approvalFile: LAYOUT001compressed.pdf8 Aug 2023
Building plan approvalFile: PLAN1compressed.pdf8 Aug 2023
Building plan approvalFile: PLAN2compressed.pdf8 Aug 2023
Building plan approvalFile: PLAN4compressed.pdf8 Aug 2023
Copy of Layout Approval (in case of layout)File: LAYOUT001compressed.pdf8 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: PLAN1compressed.pdf8 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: PLAN2compressed.pdf8 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: PLAN4compressed.pdf8 Aug 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DECLARATION ABOUT SEPARATE BANK ACCOUNT FOR REAL ESTATE PROJECT 2.pdf24 Jul 2023
Deviation Report with respect to Allotment letterFile: DEVIATION REPORT WITH RESPECT TO MODEL FORM OF ALLOTMENT LETTER.pdf24 Jul 2023
Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT WITH RESPECT TO MODEL FORM OF AGREEMENT.pdf24 Jul 2023
CERSAI detailsFile: CERSAI Undertaking.pdf28 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf28 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST -AVDHUT.pdf28 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST -BALKRISHNA.pdf28 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST -PRASHANT.pdf28 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST -SUMIT.pdf28 Apr 2023
Declaration in FORM BFile: Form B_Partner.pdf25 Apr 2023
PAN CardFile: Reliable Properties PAN.pdf24 Apr 2023
Details of encumbrances concerned to FinanceFile: encumbrances lettter.pdf24 Apr 2023
Details of encumbrances concerned to LegalFile: encumbrances lettter.pdf24 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf24 Apr 2023
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf24 Apr 2023

How this compares with Pune

33%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LALBAG VILLA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Manchar13,700+ in Pune

2 kmLALBAG VILLACompleted 2Lapsed / revoked 7Other 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: RELIABLE PROPERTIES

RELIABLE PROPERTIES has 2 registrations on MahaRERA, including RELIABLE PARK and LALBAG VILLA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if LALBAG VILLA is delayed beyond 6 Feb 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LALBAG VILLA?

The registered promoter entity is RELIABLE PROPERTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LALBAG VILLA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for LALBAG VILLA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LALBAG VILLA?

The professionals named in the filing: Architect: SACHIN LADKAT & ASSOCIATE; Engineer: AVDHUT SHETE; Engineer: KAJAL ARJUN BORKAR; Engineer: RATHIS GROUP; Chartered Accountant: SANTOSH SUTAR; Chartered Accountant: PGMJ & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LALBAG VILLA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LALBAG VILLA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LALBAG VILLA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.