Completed No litigation declared Residential / Group Housing project

LAIJAI NAGARI

By KAMLESH BACHEWAR

RG-MH-00486 · RERA P51100005371 · Last updated on MahaRERA portal: 17 Feb 2021

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Nanded registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
1135 of 1782Construction stages doneacross 162 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 32 documents Report an error

LAIJAI NAGARI is a Residential / Group Housing project by KAMLESH BACHEWAR in Nanded, Maharashtra, registered with MahaRERA as P51100005371 on 11 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2021.

At a glance

Project

  • NameLAIJAI NAGARI
  • TypeResidential / Group Housing
  • Location
    • Wadi Bk.
    • Nanded
    • 431605
  • Pincode431605
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51100005371
  • ReraGenie IDRG-MH-00486

Builder

  • NameKAMLESH BACHEWAR
  • Entity typeCompany
  • ChairpersonsUTTAM KISHANRAO BACHEWAR, ASHWINI KAMLESH BACHEWAR, REKHA UTTAMRAO BACHEWAR
  • Managing DirectorKAMLESH UTTAMRAO BACHEWAR
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredAug 2017PromisedDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on11 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionNone
  • Buildings162 building records
  • Documents filed32 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Row House-1NA30000
Row House-2NA30000
Row House-3NA30000
Row House-4NA30000
Row House-5NA30000
Row House-6NA30000
Row House-7NA30000
Row House-8NA30000
Row House-9NA30000
Row House-10NA30000
Row House-11NA30000
Row House-12NA30000
Row House-13NA30000
Row House-14NA30000
Row House-15NA30000
Row House-16NA30000
Row House-17NA30000
Row House-18NA30000
Row House-19NA30000
Row House-20NA30000
Row House-21NA30000
Row House-22NA30000
Row House-23NA30000
Row House-24NA30000
Row House-25NA30000
Row House-26NA40000
Row House-27NA40000
Row House-28NA30000
Row House-29NA30000
Row House-30NA30000
Row House-31NA30000
Row House-32NA30000
Row House-33NA30000
Row House-34NA30000
Row House-35NA30000
Row House-36NA30000
Row House-37NA30000
Row House-38NA30000
Row House-39NA30000
Row House-40NA30000
Row House-41NA30000
Row House-42NA30000
Row House-43NA30000
Row House-44NA30000
Row House-45NA30000
Row House-46NA30000
Row House-47NA30000
Row House-48NA30000
Row House-49NA30000
Row House-50NA30000
Row House-51NA30000
Row House-52NA30000
Row House-53NA30000
Row House-54NA30000
Row House-55NA30000
Row House-56NA30000
Row House-57NA30000
Row House-58NA30000
Row House-59NA30000
Row House-60NA30000
Row House-61NA30000
Row House-62NA30000
Row House-63NA30000
Row House-64NA30000
Row House-65NA30000
Row House-66NA30000
Row House-67NA30000
Row House-68NA30000
Row House-69NA30000
Row House-70NA30000
Row House-71NA30000
Row House-72NA30000
Row House-74NA30000
Row House-73NA30000
Row House-75NA30000
Row House-76NA30000
Row House-77NA30000
Row House-78NA30000
Row House-79NA30000
Row House-80NA30000
Row House-81NA30000
Row House-82NA30000
Row House-83NA30000
Row House-84NA30000
Row House-85NA30000
Row House-86NA30000
Row House-87NA30000
Row House-88NA30000
Row House-89NA30000
Row House-90NA30000
Row House-91NA30000
Row House-92NA30000
Row House-93NA30000
Row House-94NA30000
Row House-95NA30000
Row House-96NA30000
Row House-97NA30000
Row House-98NA30000
Row House-99NA30000
Row House-100NA30000
Row House-101NA30000
Row House-102NA30000
Row House-103NA30000
Row House-104NA30000
Row House-105NA30000
Row House-106NA30000
Row House-107NA30000
Row House-108NA30000
Row House-109NA30000
Row House-110NA40000
Row House-111NA30000
Row House-112NA30000
Row House-113NA30000
Row House-114NA30000
Row House-115NA30000
Row House-116NA30000
Row House-117NA30000
Row House-118NA30000
Row House-119NA30000
Row House-120NA30000
Row House-121NA30000
Row House-122NA30000
Row House-123NA30000
Row House-124NA30000
Row House-125NA30000
Row House-126NA30000
Row House-127NA30000
Row House-128NA30000
Row House-129NA30000
Row House-130NA30000
Row House-131NA30000
Row House-132NA30000
Row House-133NA30000
Row House-134NA30000
Row House-135NA30000
Row House-136NA30000
Row House-137NA30000
Row House-138NA30000
Row House-139NA30000
Row House-140NA30000
Row House-141NA30000
Row House-142NA30000
Row House-143NA30000
Row House-144NA30000
Row House-145NA30000
Row House-146NA30000
Row House-147NA30000
Row House-148NA30000
Row House-149NA30000
Row House-150NA30000
Row House-151NA30000
Row House-152NA30000
Row House-153NA30000
Row House-154NA30000
Row House-155NA30000
Row House-156NA30000
Row House-157NA30000
Row House-158NA30000
Row House-159NA30000
Row House-160NA30000
Row House-161NA30000
Row House-162NA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 17 Feb 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 162 buildings; the table lists the first 20.

1135 of 1782 construction stages are filed complete across 162 buildings. The stage furthest along is Podiums (if any), at 0%.

Row House-164%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-264%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-364%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-464%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-564%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-664%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-764%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-864%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-973%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-1064%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-1164%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-1264%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-1364%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-1464%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-1564%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-1664%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-1764%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-1864%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-1964%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Row House-2064%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 17 Feb 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed100

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots100
Closed/Covered6
Open Space94
BuildingClosed/CoveredOpen SpaceTotal
Row House-11011
Row House-12011
Row House-13011
Row House-14011
Row House-15011
Row House-16011
Row House-17011
Row House-18011
Row House-19011
Row House-20011
Row House-21011
Row House-22011
Row House-26101
Row House-27101
Row House-28101
Row House-29011
Row House-30011
Row House-31011
Row House-32011
Row House-33011
Row House-34011
Row House-35011
Row House-36011
Row House-37011
Row House-38011
Row House-44011
Row House-45011
Row House-46011
Row House-47101
Row House-52011
Row House-55011
Row House-56011
Row House-61011
Row House-62011
Row House-63011
Row House-64011
Row House-68011
Row House-69011
Row House-74101
Row House-78011
Row House-79011
Row House-80011
Row House-81011
Row House-82011
Row House-83011
Row House-84011
Row House-85011
Row House-94011
Row House-95011
Row House-96011
Row House-97011
Row House-98011
Row House-99011
Row House-100011
Row House-101011
Row House-102011
Row House-110101
Row House-112011
Row House-113011
Row House-114011
Row House-115011
Row House-116011
Row House-117011
Row House-118011
Row House-119011
Row House-120011
Row House-121011
Row House-124011
Row House-125011
Row House-128011
Row House-129011
Row House-134011
Row House-135011
Row House-136011
Row House-137011
Row House-138011
Row House-139011
Row House-140011
Row House-141011
Row House-142011
Row House-143011
Row House-144011
Row House-145011
Row House-146011
Row House-147011
Row House-148011
Row House-149011
Row House-150011
Row House-151011
Row House-152011
Row House-153011
Row House-154011
Row House-155011
Row House-156011
Row House-157011
Row House-158011
Row House-159011
Row House-160011
Row House-161011
Row House-162011

Land and ownership9

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area17,384 sq m
Land owned byThe promoter, with other names on the file
Named landowners9
LandownerVillageDistrict
RAMESH VITHALRAO PAWADEWadi Bk.Nanded
TANAJI PAWDEWadi Bk.Nanded
SINDUTAI SUBHASHRAO PAWDEWadi Bk.Nanded
VASANTRAO PAWDEWadi Bk.Nanded
SHANKAR PAWDEWadi Bk.Nanded
SHYAM PAWDEWadi Bk.Nanded
SAHEB PAWDEWadi Bk.Nanded
SANTOSH PAWDEWadi Bk.Nanded
SOPAN BABARAO PAWADEWadi Bk.Nanded

Approvals and building plan

Permissible FSI19864.16
Proposed, not sanctioned19,864 sq m
Buildings approved162
Buildings sanctioned162

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWADI BK

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectABHISHEK NERALKAR
PartnerRole in project
KAMLESH BACHEWAR-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Nov 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 17 Feb 2021

Documents filed32

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 14-B Grampanchayat Work complition.pdf17 Feb 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 14-B.pdf31 Jan 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf31 Jan 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Task Activity.pdf31 Jan 2021
Details of Restarting of Construction work post lockdownFile: Task Activity.pdf31 Jan 2021
Architect’s Certificate on Completion of Project (Form 4)File: form 4 14-B.pdf31 Jan 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Engineer's Certificate.pdf19 Jul 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Task Activity.pdf19 Jul 2019
Certificates of CA (Form 3)File: CA certificate.pdf19 Jul 2019
Certificates of CA (Form 3)File: 14-B.pdf1 Dec 2018
Commencement Certificates / NA Order for plotted developmentFile: 14-B.pdf21 Nov 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: 14-B.pdf31 Mar 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: 14-B.pdf31 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect.pdf10 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect.pdf10 Mar 2018
Certificates of CA (Form 3)File: 14-B CA certificate.pdf10 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Enginer Certificate 14 B.pdf22 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Task Activiy 01.pdf22 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Task Activiy 02.pdf22 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate (PDF).pdf21 Jul 2017
Certificates of CA (Form 3)File: CA certificate.pdf21 Jul 2017
OtherFile: 01.pdf21 Jul 2017
OtherFile: 02.pdf21 Jul 2017
Details of encumbrancesFile: Sopan Pawade.pdf20 Jul 2017
Declaration in FORM BFile: PDF.pdf18 Jul 2017
Layout approvalFile: 02.pdf16 Jul 2017
Building plan approvalFile: 01.pdf16 Jul 2017
Copy of Layout Approval (in case of layout)File: 02.pdf16 Jul 2017
Building Plan Approval (IOD)File: 01.pdf16 Jul 2017
Proforma of Allotment letterFile: Agreement Full sale.pdf16 Jul 2017
PAN CardFile: Pan card.pdf10 Jul 2017
Copy of the legal title reportFile: 1-6.pdf10 Jul 2017

How this compares with Nanded

3%of Nanded projects moved their completion datethis one has not
25%of Nanded registrations have lapsed or been cancelledthis one is completed

Computed across the 100+ Nanded projects on ReraGenie, from their own filings.

Keep LAIJAI NAGARI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wadi Bk.100+ in Nanded

Builder: KAMLESH BACHEWAR

KAMLESH BACHEWAR has 2 registrations on MahaRERA, including LAIJAI NAGARI and LAIJAI NAGARI 14/A/1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nanded district page.

Frequently asked questions

What are my rights if LAIJAI NAGARI is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LAIJAI NAGARI?

The registered promoter entity is KAMLESH BACHEWAR, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LAIJAI NAGARI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for LAIJAI NAGARI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LAIJAI NAGARI?

The professionals named in the filing: Architect: ABHISHEK NERALKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LAIJAI NAGARI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LAIJAI NAGARI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LAIJAI NAGARI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.