Laaffaires Avenue Commercial and Laflor Residency Commercial
By SSV Realtors
RG-MH-62414 · RERA P51800012063 · Last updated on MahaRERA portal: 2 Nov 2020
Source: official MahaRERA filing
Red flags
- Registration revoked
- 6 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Laaffaires Avenue Commercial and Laflor Residency Commercial is a Others project by SSV Realtors in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800012063 on 1 Sep 2017. Possession is promised by 30 Dec 2028. 6 complaints are on record with the regulator.
At a glance
Project
- NameLaaffaires Avenue Commercial and Laflor Residency Commercial
- TypeOthers
- Location
- Kurla
- Mumbai Suburban
- 400083
- Pincode400083
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800012063
- ReraGenie IDRG-MH-62414
Builder
- NameSSV Realtors
- Entity typePartnership
- PartnersHemant Vinaykant Parikh, Ami Vipul Parikh
Key dates
Key facts
Registration and timeline
- StatusRegistration revoked
- Registered on1 Sep 2017
- Promised completion30 Dec 2028
- Revised completionNone
- Buildings6 building records
- Documents filed56 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| LA AFFAIRES AVENUE COMMERCIAL | NA | 20 | 0 | 0 | 0 | 0 |
| Laflor Residency Commercial | NA | 52 | 0 | 0 | 0 | 0 |
| Ashtavinayak Society Residence Commercial Sale Rehab Composite | NA | 20 | 0 | 0 | 0 | 0 |
| Ashtavinayak Annexe | NA | 16 | 0 | 0 | 0 | 0 |
| Damji Sadan Society Residence Commercial Sale Rehab Composite | NA | 20 | 0 | 0 | 0 | 0 |
| Laxmi Society Residence Commercial Sale Rehab Composite | NA | 20 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building6
As on 2 Nov 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Excavation, at 50%.
LA AFFAIRES AVENUE COMMERCIAL11%
| Activity | Progress |
|---|---|
| Excavation | 50% |
| Basement (if any) | 25% |
| Podiums (if any) | 0% |
| Plinth | 25% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 10% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Laflor Residency Commercial0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Ashtavinayak Society Residence Commercial Sale Rehab Composite36%
| Activity | Progress |
|---|---|
| Excavation | 40% |
| Basement (if any) | 40% |
| Podiums (if any) | 40% |
| Plinth | 40% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 40% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 40% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 40% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 40% |
Ashtavinayak Annexe0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Damji Sadan Society Residence Commercial Sale Rehab Composite0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Laxmi Society Residence Commercial Sale Rehab Composite0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 2 Nov 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 10% |
| Water Supply | Yes | 20% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 10% |
| Storm Water Drains | Yes | 10% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 10% |
| Water conservation /Rain water harvesting | Yes | 10% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 10% |
| Electrical meter room, sub-station, receiving station | Yes | 20% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed210
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| LA AFFAIRES AVENUE COMMERCIAL | 50 | 50 |
| Laflor Residency Commercial | 160 | 160 |
Land and ownership6
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| ASHTAVINAYAK SRA CHS | Mumbai City | Mumbai City |
| RAVILAL K PATEL AND OTHERS | Mumbai City | Mumbai City |
| TENANTS ASSOCIATION OF DAMJI SADAN | Mumbai City | Mumbai City |
| HPA SPACES PVT LTD | Mumbai City | Mumbai City |
| SSV DEVELOPERS AND BUILDERS PVT LTD | Mumbai City | Mumbai City |
| LAXMI SRA CHS | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | HEMANT PARIKH & ASSOCIATES |
| Partner | Role in project |
|---|---|
| SSV Realtors | - |
Complaints filed with MahaRERA6
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000056750 | Priyanka Maheshwari | Hemant Parikh | 28/10/2018 |
| CC006000000023369 | Aspandiar Rashid Irani | M/s. SSV Realtors | 15/02/2018 |
| CC006000000023523 | Gustad Rashid Irani | M/s. SSV Realtors | 28/02/2018 |
| CC006000000056386 | SAMEER TYAGI | Hemant Parikh | 15/10/2018 |
| CC006000000089925 | VINI DESAI | M/S. S.S.V. REALTORS | 01/07/2019 |
| CC006000000100383 | ASHTHVINAYAK SRA CHS | SSV REALTORS | 01/08/2019 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Nov 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Dec 2028
Documents filed56
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| OtherFile: 2 Draft SSV- Ashtavinayak Writ Petition copy.pdf | 2 Nov 2020 |
| Building plan approvalFile: Laaffairs_approval.pdf | 3 Nov 2019 |
| Building plan approvalFile: laaffairs_1.pdf | 3 Nov 2019 |
| Building plan approvalFile: Laaffairs_approval_2.pdf | 3 Nov 2019 |
| Building Plan Approval (IOD)File: Laaffairs_approval.pdf | 3 Nov 2019 |
| Building Plan Approval (IOD)File: laaffairs_1.pdf | 3 Nov 2019 |
| Building Plan Approval (IOD)File: Laaffairs_approval_2.pdf | 3 Nov 2019 |
| OtherFile: laaffairs_1.pdf | 3 Nov 2019 |
| OtherFile: Laaffairs_approval_2.pdf | 3 Nov 2019 |
| OtherFile: Laaffairs_approval.pdf | 3 Nov 2019 |
| OtherFile: project listed under P51800012063.pdf | 3 Nov 2019 |
| OtherFile: sample flat laaffairs.pdf | 3 Nov 2019 |
| Certificates of CA (Form 5)File: Form no 5 La affaires.pdf | 25 Jul 2019 |
| Certificates of CA (Form 3)File: ITR FORM SSV RELOTRS.pdf | 25 May 2019 |
| Certificates of CA (Form 3)File: ITR FORM SSV REALOTRS.pdf | 25 May 2019 |
| Certificates of CA (Form 3)File: ITR V SSV REALOTRS.pdf | 25 May 2019 |
| OtherFile: asthavinayak.pdf | 24 May 2019 |
| Certificates of CA (Form 3)File: SSVR - IT -2017.pdf | 22 May 2019 |
| OtherFile: ahaval_sadar.pdf | 22 May 2019 |
| OtherFile: asthavinayak.pdf | 22 May 2019 |
| OtherFile: Cost incurred for Ashtavinayak CHS.pdf | 22 May 2019 |
| OtherFile: minutes_of_decision.pdf | 22 May 2019 |
| OtherFile: SSVR-Ashtavinayak- Minutes of Decision.pdf | 19 May 2018 |
| Building plan approvalFile: 7 Attachment -Ashtavinayak Rehab IOA rsz.pdf | 31 Jul 2017 |
| Building plan approvalFile: 9 Attachment -Ashtavinayak Sale Bldg 2 IOA rsz.pdf | 31 Jul 2017 |
| Building plan approvalFile: 9 Attachment -Ashtavinayak Sale Bldg 2 IOA rsz.pdf | 31 Jul 2017 |
| Layout approvalFile: 1st floor parking plan.pdf | 31 Jul 2017 |
| Layout approvalFile: Damji Laxmi Slum plan_15-01-Model.pdf | 31 Jul 2017 |
| Layout approvalFile: ground floor plan.pdf | 31 Jul 2017 |
| Layout approvalFile: master layout 1.pdf | 31 Jul 2017 |
| Layout approvalFile: 4 Attachment - LA AFFAIRES APPROVED PLANS rsz (1).pdf | 31 Jul 2017 |
| Layout approvalFile: 4 Attachment - LA AFFAIRES APPROVED PLANS rsz (1) rsz.pdf | 31 Jul 2017 |
| Layout approvalFile: 5 Attachment -LA FLOR APPROVED PLANS rsz.pdf | 31 Jul 2017 |
| PAN CardFile: pan card.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: 2 Attachment -Titel Report- ashtavinayak.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: Encumbrance.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 1st floor parking plan.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Damji Laxmi Slum plan_15-01-Model.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: ground floor plan.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: master layout 1.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 4 Attachment - LA AFFAIRES APPROVED PLANS rsz (1).pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 4 Attachment - LA AFFAIRES APPROVED PLANS rsz (1) rsz.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 5 Attachment -LA FLOR APPROVED PLANS rsz.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: 7 Attachment -Ashtavinayak Rehab IOA rsz.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: 9 Attachment -Ashtavinayak Sale Bldg 2 IOA rsz.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: 9 Attachment -Ashtavinayak Sale Bldg 2 IOA rsz.pdf | 31 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: 10 Attachment -Ashtavinayak CC for rehab bldg 1 rsz.pdf | 31 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: 11 Attachment -Ashtavinayak CC for rehab bldg rsz.pdf | 31 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: 12 Attachment -Ashtavinayak CC for Sale bldg No 1 rsz.pdf | 31 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: 13 Attachment -Ashtavinayak CC for Sale bldg No 2 rsz.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: ashtavinayak Chs SSV R.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 25 Attachment - FORM -1 -SSVR-ilovepdf-compressed.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ssv realtor form 2 rsz.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: affidavid ssvr.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Attachment - allotment letter draft Ashtravinayak.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: AGREEMENT FOR SALE-Ashtavinayak.pdf | 31 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 56 filed documents as one ZIP, foldered, with a manifest
Keep Laaffaires Avenue Commercial and Laflor Resi on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kurla6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 151 registered projects within 2 km.
Cons 1221 MIG T/S and 100 Shops S. No. 113 (pt
Mumbai Housing And Area Development Board
Om Siddhivinayak CHS and Gurukrupa CHS
Shreeji Developers
AKASSH AMAZONIA TOWER 1
HEER MEHTA LANDMARK DEVELOPERS PRIVATE LIM
Ajmera Solis
Shree Yogi Realcon Private Limited
CENTRAL PARK
V LAXMI NURSES DEVELOPERS LLP
Swastik Platinum
SUVASYA BUILDERS AND DEVELOPERS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: SSV Realtors
SSV Realtors has 1 registration on MahaRERA, including Laaffaires Avenue Commercial and Laflor Residency Commercial. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Laaffaires Avenue Commercial and Laflor Residency Commercial shows as registration revoked on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Laaffaires Avenue Commercial and Laflor Residency Commercial is delayed beyond 30 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Laaffaires Avenue Commercial and Laflor Residency Commercial?
The registered promoter entity is SSV Realtors, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Laaffaires Avenue Commercial and Laflor Residency Commercial?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Laaffaires Avenue Commercial and Laflor Residency Commercial?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Laaffaires Avenue Commercial and Laflor Residency Commercial?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Laaffaires Avenue Commercial and Laflor Residency Commercial?
The professionals named in the filing: Architect: HEMANT PARIKH & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Laaffaires Avenue Commercial and Laflor Residency Commercial?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback